ITD Projects Southwest Idaho I-84 Caldwell Franklin Interchange

I-84 Caldwell Franklin Interchange


Project Facts
Key Number: 7795
Project Number: NH-84-104329

The Idaho Transportation Department (ITD) reconstructed the Franklin Road Interchange to improve access to Caldwell from I-84, improve traffic flow, and ease congestion. The existing Franklin Road Overpass was rebuilt as a six-lane bridge. All four interchange ramps were widened at their intersection with Franklin Road, and Franklin Road itself was widened.


Project Background
The first Caldwell interchange on I-84 opened in 1966. Since then, interchange traffic has grown to 17,700 vehicles every day. In the next 20 years, that number is expected to nearly double.

Construction on the project began in December 2006. A ceremony to celebrate the completion of the project and official opening was held July 8, 2008.

Project Description
The reconstruction improved several aspects of the interchange:
  • The old three-lane Franklin Overpass was replaced with a six-lane bridge. The new overpass has two through lanes in each direction and dual left-turn lanes in each direction.
  • The interchange ramps were lengthened and widened to two lanes at their intersection with Franklin.
  • Franklin Road was widened from two to five lanes between the overpass and Specht Avenue. The improved road has curb, gutter, sidewalk, bicycle lanes and shoulder.
  • Aviation Way was widened at the intersection with Franklin Road. A new traffic signal was added.
Concrete Placing Co. was the contractor for the $25 million project.


Compliance with Title VI of the Civil Rights Act
The Idaho Transportation Department (ITD) is committed to compliance with Title VI of the Civil Rights Act of 1964 and all related regulations and directives. ITD assures that no person shall on the grounds of race, color, national origin, gender, age, or disability be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any ITD service, program, or activity. The department also assures that every effort will be made to prevent discrimination through the impacts of its programs, policies, and activities on minority and low-income populations. In addition, the department will take reasonable steps to provide meaningful access to services for persons with Limited English Proficiency.

Brochures and Newsletters

 
ITD Public Involvement Coordinator
comments@itd.idaho.gov
P.O. Box 7129
Boise, ID 83707-1129
Phone: (208) 334-8119
Fax: (208) 334-8563
TDD: (208) 334-4458

Page Last Modified: 2/13/2009 2:00:11 PM