Why it Matters
I-84 is a crucial commercial business route and commuter route, providing a critical pathway for in-state destinations and for those passing through Idaho. I-84 is the main east-west interstate route in the state, and one of the most important in the Pacific Northwest and Intermountain West.
Project Description
The I-84 roadway surface was repaired and improved beginning west of the Black Canyon Interchange and extending for five miles to east of the Sand Hollow Interchange.
Several badly damaged concrete slabs in that stretch were removed and replaced. Repairs also included resealing pavement joints, repairing pavement cracks and chips, grinding portions off of the existing pavement surface and completing guardrail safety improvements.
Current Status
Advertised: Fall, 2009
Bids opened: February 23, 2010
Contractor: Multiple Concrete Enterprises
Contract awarded: March 1, 2010
Estimated Construction Start: April 26, 2010
Current Project Phase: Complete
Estimated Completion: Mid-October, 2010
Project News Releases
News Releases: March 8, 2010 | April 13, 2010 | April 19, 2010
Project Materials:
|