Community invited to review options to improve State Highway 16 between Sh-44 and SH-52

Freezeout Hill

The Idaho Transportation Department is holding a public meeting on Monday, December 4 in Ada County and Wednesday, December 6 in Gem County. The community is invited to learn about the project, give input on issues and concerns, and provide feedback on a range of plans to improve SH-16.

Details for the in-person meetings are listed below:

  • Monday, December 4 at Eagle Christian Church (100 S Short Rd, Eagle, ID 83616)
  • Wednesday, December 6 at Emmett High School (721 W 12th St, Emmett, ID 83617)
  • 4:30 – 7 p.m. (drop in anytime)
  • Please join at whichever location is most convenient for you.

An online meeting will be available for those that are not able to attend the in-person meetings. The online meeting will be open from December 7 – 21 at itdprojects.idaho.gov/pages/sh1644to52.

At the meetings, ITD will share details about:

  • The purpose and need for the environmental reevaluation.
  • Updated traffic and crash data information.
  • Modification to the 2005 preferred alternative.
  • The project timeline and next steps in the process.

“We look forward to sharing the range of modified improvement plans with the community and receiving their feedback,” said ITD Project Manager Mark Wasdahl. “Their input is very important to the reevaluation process and will help us moving forward.”

The SH-16, SH-44 to SH-52 project began in June 2023 and is expected to be complete in 2025. ITD has already met with numerous state and local agencies and property owners to identify concerns, discuss ongoing planning efforts and share information about the project.

To sign up for email updates or learn more about the project, please visit itdprojects.idaho.gov/pages/sh1644to52.

 

Public invited to open houses to comment on preliminary I-90 corridor designs

Traffic congestion I-90 near Huetter

ITD will host two open houses next week in Post Falls and Coeur d’Alene to present recommended designs to improve I-90 between the Washington state line and Sherman Avenue in Coeur d’Alene. The ongoing study is funded by the Leading Idaho program.

Each open house will present identical information and designs.

Post Falls

  • Tuesday, Nov. 1
  • 4 p.m. – 7 p.m.
  • Red Lion Hotel Templin’s on the River at 414 E 1st Ave

Coeur d’Alene

  • Wednesday, Nov. 2
  • 4 p.m. – 7 p.m.
  • Best Western Plus Coeur d’Alene Inn at 506 West Appleway Ave

For those not able to attend either open house, an online option will share the same information and will be available on Nov. 1 at itdprojects.org/i90corridor.

“Since the first stretch of I-90 was built in Kootenai County in 1960, ITD has made some upgrades, but the number of lanes has not changed,” said Erika Bowen, ITD Project Manager. “With traffic currently congested in various parts of the corridor and volumes expected to double by 2045, ITD is studying the interstate to identify improvements to modernize the system, reduce crashes and save drivers time.”

Proposed improvements include adding lanes on I-90, modifying access and upgrading interchanges with impacts to local roads in both cities. Areas with proposed improvements include:

  • Spokane Street and Seltice Way Interchanges
  • Northwest Boulevard Interchange
  • US-95 and Fourth Street Interchanges
  • Seventh Street Bridge
  • Sherman Avenue Interchange
Blue and white circular logo for "Leading Idaho" projects sponsored by Governor Little
Blue and white circular logo for “Leading Idaho” projects sponsored by Governor Little

Following the study and public input, the recommended projects will be prioritized and advanced into design and construction as funding becomes available.

The study is funded with Transportation Expansion and Congestion Mitigation (TECM) funds as part of Governor Little’s Leading Idaho initiative. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure today that would otherwise take many years to fund and build.

The corridor is one of 13 approved TECM corridors in the state. Funding for the future design and construction phases on this corridor will be determined based on project readiness and funding availability. Preliminary estimates value the improvements needed in this corridor at $1 billion to $1.2 billion, which includes design, right-of-way and construction costs. A previously funded project to redesign the SH-41 interchange at I-90 is currently under construction.

To stay up to date on the I-90 corridor project, visit itdprojects.org/i90corridor and sign up for email updates.

 

ITD shares future plans for State Highway 55 and I-84, Karcher Interchange at Nampa open house July 7

The Idaho Transportation Department (ITD) invites the public to an open house this month for two adjacent projects in Canyon County. Design plans will be shared for improvements to the Interstate 84, Karcher Interchange and several miles of State Highway 55 west of the interchange.

Community members may stop by an in-person open house on Thursday, July 7 between 5 and 7 p.m. at Nampa Christian School, 11920 W. Flamingo Avenue in Nampa. Online open houses for each project will also be available July 7-14 at itdprojects.org/karcheric and itdprojects.org/state-highway-55-farmway-to-middleton-road.

“These two projects are part of ITD’s ongoing work to address growth and the resulting congestion on highways in Canyon County, particularly State Highway 55,” said project manager Erika Bowen. “ITD is targeting the most urgent needs in this area while continuing to plan for long-term solutions.”

The I-84, Karcher Interchange project includes widening the interchange bridge and adding a new westbound lane across the interchange to Caldwell Boulevard. Several improvements are also planned on the interchange ramps, signals, and intersections. Details are available at itdprojects.org/karcheric.

The SH-55, Farmway Road to Middleton Road project will widen SH-55 to two lanes in each direction in the busy area between Farmway and Middleton roads. More information is on the project website at itdprojects.org/state-highway-55-farmway-to-middleton-road/.

Once construction funding has been confirmed, work on the Karcher Interchange could begin as early as 2023, and the widening of SH-55 could start in 2024.

Funding for this design stage of both projects comes from the Leading Idaho Transportation Expansion and Congestion Mitigation Program. The program allows ITD to build critical infrastructure today that would otherwise take many years to build.

A Spanish interpreter will be present at the July 7 open house. Community members can also request written materials in Spanish by calling (208) 334-8002.

Public open house planned May 24 for US-20/26 Chinden West corridor improvements

The Idaho Transportation Department (ITD) invites the public to learn more about the future widening of U.S. Highway 20/26 between Middleton Road and Star Road.

ITD will host an open house on Tuesday, May 24 to share preliminary design plans and gather feedback on proposed improvements to this heavily traveled section of US-20/26.

This project will widen the highway and improve intersections to enhance safety and mobility for all users of the transportation system, including nearby residents, businesses, commuters, and freight carriers.

The public is encouraged to attend the drop-in style open house, share input on the plans, and meet members of the project team.

Tuesday, May 24, 2022
5-7 p.m.
Middleton United Methodist Church
104 E. Main Street (State Highway 44)
Middleton, ID

All materials provided at the open house will also be available online at itdprojects.org/chindenwest beginning May 25, for those who can’t attend in person. Comments will be accepted through June 7.

The design of this project is funded with Transportation Expansion and Congestion Mitigation (TECM) funds as part of the Leading Idaho TECM Program. The program allows ITD to accelerate project timelines to address Idaho’s rapid growth and build critical infrastructure today that would otherwise take many years to fund and build. Funding for the next phase of work will be determined when the project progresses to that stage.

To learn more about the project and sign up for email updates, visit itdprojects.org/chindenwest.

Public comment sought on plan for Idaho highway rail grade crossings

BOISE – Public input is being sought on the action plan to guide Irail grade crossings on Idaho Highways. Through Jan. 21, members of the public are invited to comment at https://arcg.is/1DqS4b or via the QR code posted below.
QR code to review action plan to guide Irail grade crossings on Idaho Highways
The action plan identifies, analyzes, and develops solutions to issues affecting safety at approximately 1,400 public, highway-rail grade crossings in Idaho.

 

ITD seeks feedback on draft Americans with Disabilities Act Transition Plan update

As the Idaho Transportation Department updates its Americans with Disabilities Act (ADA) Transition Plan, the public is encouraged to learn more about plans to invest nearly $35 million into projects and services over the next 15 years.

ADA Transition is the process of eliminating accessibility barriers to existing pedestrian infrastructure on the state highway system. It also helps identify programs that fund improvements through a coordinated effort with local highway districts and other municipalities.

In an effort to gather feedback about the plan, ITD will host an online survey as part of a 30-day public comment period that begins Sept. 17. The survey can be accessed at itd.idaho.gov/planning by clicking on the link. The survey is available 24 hours a day.

Staff will also hold a virtual public information meeting on Tuesday, Sept. 28 at 6:00 p.m. Mountain time. 
You can find the meeting link posted online at itd.idaho.gov/planning or by emailing ADA@itd.idaho.gov.

Comments and feedback shared during this public involvement phase will be incorporated into a draft ADA Transition Plan, that will become official after review and approval by the Federal Highway Administration and Idaho Transportation Board later this fall.

For questions or to learn more about ADA Transition, please email ADA@itd.idaho.gov or call (208)332-7823.

Idaho Transportation Department now taking comments for all upcoming projects

Cars cross Lake Pend Oreille on the Long Bridge

The Idaho Transportation Department (ITD) is asking for input on the just-released draft Idaho Transportation Investment Program (ITIP). The 2022-2028 ITIP is a seven-year master plan of the state’s transportation improvement projects. Everyone is encouraged to participate starting in July.

Projects can range from large-scale interstate improvements to smaller projects like the installation of a new guardrail. In all, the draft ITIP includes projects in all 44 counties and all modes of transportation. Projects were selected based on technical data, as well as input from local officials and residents.

A complete breakdown of the draft plan can be found at itd.idaho.gov/funding, as well as an interactive map that allows users to learn about projects by narrowing it down to specific categories and locations.

A few of the major projects throughout Idaho are:

  • Bridge replacement and adding a travel lane on west bound I-86 in Pocatello.
  • Interchange improvements to the I-15 Exit 113 interchange in Idaho Falls including constructing roundabouts.
  • Full road reconstruction on ID-33 from the US-20/ID-33 interchange to Newdale.
  • Replacement of the structure at the I-84/ID-50 Junction (Exit 182).
  • Replacement of Yankee Fork Bridge on ID-75 in Custer County.
  • Widening ID-44 from Star Road to Linder Road.
  • Extending ID-16 from US-20/26 to I-84.
  • Redesign of the interchange at I-90 and ID-41, with construction planned to start in 2023.
  • Study to begin this fall to examine potential expansion of US-95 to four lanes from Moscow to north of the Mineral Mountain Rest Area.

Comments will be taken from July 1-31 and can be e-mailed to ITDcommunication@itd.idaho.gov or mailed to:

ITIP – Comments
Attn: Office of Communication
P.O. Box 7129
Boise, ID  83707

Paper copies of the ITIP will be provided upon request by contacting the Idaho Transportation Department (208) 334-8119.

All comments will be reviewed, incorporated into the ITIP where appropriate, and responses will be sent in September once the comment period has ended.

After approval by the Idaho Transportation Board in September, the ITIP will then be submitted to the Federal Highway Administration, the Federal Transit Administration, and the Environmental Protection Agency in October.

 

 

Hearing begins today on 129,000-pound truck route application for Custer and Butte counties

Graphic of truck on highway with text reading Comment on proposed 129k route

The Idaho Transportation Department is hosting a virtual public hearing to collect comments on a proposal to reclassify a portion of US-93 in Custer and Butte counties as legal for commercial loads weighing up to 129,000 pounds.

In the application submitted to ITD, Amalgamated Sugar Company requested reclassification of the following route in order to transport lime rock from the US Calcium mine near Darlington to their plants in Twin Falls and Paul:

– US-93 from the Idaho Highway 75 junction near Challis to the US-20 junction in Arco (MP 160.38 to 82.60)

The public hearing begins today and continues until June 23.

The hearing provides an opportunity for citizens to learn about 129,000 pound loads. Individuals are also able to review the evaluation and comment on the current route application.

To access the hearing, visit itd.idaho.gov/freight

Comments will be accepted through Wednesday, June 23 and may be submitted in the following ways:

– recorded by calling (855) 790-4988
– via the online hearing: itd.idaho.gov/freight
– emailed to: officeofthechiefengineer@itd.idaho.gov
– mailed to: Idaho Transportation Department
ATTN: Scott Luekenga
PO Box 7129
Boise, ID  83707

Individuals may also contact Scott Luekenga directly with questions or comments regarding this application, 129k routes, or the approval process by calling 208-334-8057.

The Department is required to conduct an analysis and public hearing on all requests to operate 129,000 lbs. on the state highway system before the Idaho Transportation Board makes a final decision.

ITD launches two-week virtual meeting (May 21-June 4) to share next steps for Idaho 16 extension

Idaho Highway 16 in the Treasure Valley

The Idaho Transportation Department launches a two-week online meeting today (May 21) to share plans for the next phase of extending Idaho Highway 16 through the central Treasure Valley. The meeting will be available from May 21 to June 4 at itdprojects.org/idaho16.

The meeting includes a virtual tour and design plans for the future north-south corridor, which is currently the primary route to Emmett. ITD is extending the corridor 5.5 miles south to connect with I-84.

Online Public Meeting Invite

The extension of Idaho 16 will operate as a high-speed expressway, with limited access on or off it. By 2040, the highway is expected to serve 60,000 motorists each day in the growing area between Ada and Canyon counties.

“This corridor has been in the making for many years and the community has given input at many important stages of this significant highway corridor,” said ITD Program Manager Amy Schroeder. “All of the design plans in this online meeting are consistent with the overall vision and allows ITD to proceed to construction next year.”

Phase 1 of the corridor was completed in 2014 and involved bridging Idaho 16 over the Boise River and connecting U.S. 20/26 and Idaho 44.

On Wednesday, the Idaho Transportation Board approved funding to construct the next phase of the extension. Phase 2, the focus of the online meeting, will build the remaining five miles of highway from U.S. 20/26 to I-84. This includes an interchange with I-84, connections at Franklin and Ustick Roads, and bridge structures over local roads, canals, and a railroad.

The estimated cost of this work is $170 million. It will be funded using bonds and paid off using new sales tax funds approved by the Idaho Legislature in 2021.

“The work we have done on the Idaho 16 corridor in the last few years has prepared us to quickly leverage this new funding stream,” said Schroeder. “We have an obligation to the taxpayer to make the most of the today’s low interest rates and bring needed transportation investments to Idaho quickly.”

The online meeting will include live Q&A sessions from 12-1 p.m. and 5:30-6:30 p.m. on June 2. Alternate versions of the meeting are available for those without Internet access. Please contact ITD at (208) 334-8008 or Idaho16@ITD.Idaho.gov.

Comment period open for the I-86/I-15 system interchange project in Pocatello

I-15/I-86 Interchange Southbound

 
POCATELLO – The Idaho Transportation Department (ITD) has opened a two week comment period to the public on recent project updates to the I-86/I-15 System Interchange project.

The public can now comment on the system interchange project updates which include but are not limited to:  a new separated pedestrian/bicycle pathway east of the interstate; construction detour information; project FAQs and other proposed improvements.

The community can utilize an interactive map showing the project details and proposed improvements before submitting their comments. The comment period is open now through Monday, May 24.

Project construction will begin in 2022 with plans of interchange completion in 2025.

For project information, updates and to comment please visit: