Child Pedestrian Safety projects start in spring

BOISE – A dozen sidewalk and pathway projects benefiting child pedestrian safety will be built this year across the state beginning this spring.

There were 71 eligible project applications requesting more than $12M in funds to consider in this year’s funding cycle (there was just $2M in funding available). The maximum award is $250,000. Construction must be completed before the end of the year.

The projects are thanks to collaboration between the Idaho Transportation Department and the Local Highway Technical Assistance Council, after a legislative effort last year. They are funded with general fund surplus money approved by the Idaho Legislature during the 2017 session.

The following 12 projects were approved for funding:

Location        Amount
Ashton            $250,000
Title: Main Street sidewalk improvements
Description: This project will provide new sidewalk and lighting improvements along Main St. (ID-47) to connect with the existing pedestrian system at the high school.

Blackfoot         $171,000
Title: Ridge Crest Elementary Safety Improvements Project
Description: This project will provide a 575-foot section of sidewalk along Airport Road to extend the sidewalk from Ridgecrest Elementary to the park. Additional safety improvements include a pedestrian crossing at East Airport Road.

Burley             $191,000
Title: Highland Avenue and East 19th Street Sidewalk Connection
Description: This project will provide nearly a half-mile of new sidewalk and Americans with Disabilities Act (ADA)-compliant ramps that connect two schools along Highland Avenue. The schools are White Pine Intermediate and Dworshack Elementary.

Caldwell          $109,446
Title: Sacajawea Elementary School Project
Description: This project will provide new sidewalk, updated ADA curb ramps, bike lanes, and streetlights, and a Pedestrian Hybrid Beacon along Illinois Avenue to provide a safe route to school for children travelling to Sacajawea Elementary.

Carey               $154,640
Title: Crosswalk Signage and Pedestrian Improvement Project
Description: This project will provide new curb, gutter, and sidewalk along ID-26 and a Pedestrian Hybrid Beacon to provide a safe crossing for pedestrians walking across the state highway.

Driggs               $125,000
Title: South 5th Street Pathway
Description: This project will provide approximately 1,600 feet of 10-foot-wide multiuse path and ADA ramps along South 5th Street, connecting four schools to residential areas. This project extends an existing safe route to school.

Firth                  $250,000
Title: Children Pedestrian Improvements
Description: This project will provide new curb, gutter, and sidewalk along Center Street from Main St. (ID-91) to the elementary school. Additional safety improvements include a Pedestrian Hybrid Beacon signal on Main St.

Idaho Falls         $240,000
Title: Iona Street, Riverside Drive and Bush Elementary Connections
Description: This project will provide new sidewalk along Iona Street and a Pedestrian Hybrid Beacon for safe crossings at Riverside Drive (a busy street near an interchange). A second location includes sidewalk connections to Bush Elementary.

Marsing              $35,326
Title: ID-55 Sidewalk Project
Description: This project will provide new sidewalk along ID-55, connecting the public library and downtown with the elementary, middle, and high schools.

Moscow             $250,000
Title: Third Street Corridor Improvements
Description: This project will provide about 970 feet of new sidewalk along 3rd Street, connecting two elementary schools and the high school along a safe route to school. Additional safety improvements include adding center medians, curb extensions, vertical tube delineator (high-visibility markings), and school-zone lighting.

Shelley                $135,000
Title: Locust and US-91 Improvements
Description: This project will install a Pedestrian Hybrid Beacon at the intersection of ID-91 and Locust Street to provide a safe pedestrian crossing for students going to the school or library.

Teton                  $28,000
Title: Child Pedestrian Safety Project
Description: This project will install Pedestrian Hybrid Beacons at two intersections along ID-33 south of Teton Elementary to provide safe crossing for students going to and from school.