Pavement restoration to begin from Payette to Weiser in April

Pavement restoration on 12 miles of US-95, from the Payette north city limit to the Weiser River Bridge, is set to begin early April 2018.

Completion is anticipated by June. The project will extend the life of the road and provide for a smoother ride.

Construction crews plan to complete the project in two phases. In early April (Phase 1), traffic will be reduced to one lane with a pilot car leading motorists through the work zone. Traffic will return to normal conditions in mid/late April.

In early May (Phase 2), crews will return to complete the restoration. Traffic will again be reduced to one lane with a pilot car. During both phases, motorists should anticipate delays of 15 minutes or more.

Work is scheduled Monday-Friday, 24 hours a day. Night work is anticipated. Saturday work is permitted, although not anticipated. During weekends, traffic will return to normal conditions with reduced speeds.
Area businesses and residents may experience construction-related noise and lights.

Western Construction is the contractor on this $6.1 million project.

For up-to-date construction information, visit 511.idaho.gov.