Historic System Interchange rebuild nearing successful completion

Aerial view of the system interchange at Pocatello.

With the painting of final lane markers on the new roadway, construction at the I-86/I-15 “Flying-Y” System Interchange in Pocatello is coming to a successful conclusion. Begun in July 2022, the three-year $112 million project has dramatically changed the drivability of the interchange.

“We spent over eight years from design to actual construction of the project. We’re pretty proud of it. It’s one of the bigger projects we’ve designed. It’s one of the largest projects ever designed entirely by ITD staff and inspected with ITD personnel. Most of the people on the team live here locally and this has been a really meaningful project for us to make sure we did our very best,” said Project Engineer Aaron Baird.

Critical areas that were improved include the northbound Pocatello Creek on-ramp, the northbound-to-westbound collector distributor, and the eastbound-to-northbound ramp. Each of those improvements made merging from one Interstate to the other smoother and safer for motorists.

“We’re excited for people to use the final product. We hope it’s something that will last a long time and keep the travelling public safe as they use it,” said Project Manager Greg Roberts.

The scale of the endeavor has been truly historic. Approximately 1 million cubic yards of excavation have been completed. In addition, about 490,000 tons of base material was brought in; 116,000 tons of asphalt were placed; and over 7,700 cubic yards of concrete were poured. Nearly 70,000 square feet of retaining walls were also built throughout the project area. Finally, ITD built eight new bridges. Four of those have precast concrete girders and four have steel girders. In all, over 5 million pounds of steel has been used in the new bridges.

Construction crews worked year-round and around the clock for approximately three years to complete the project. To minimize disruption to traffic, key demolition operations were conducted at night. These efforts minimized the impact on traffic while the interchange was being reconstructed.

In addition to the major changes inside the Flying-Y design, the Chubbuck Road overpass was reconstructed as an underpass to improve site distances and vertical clearance on I-15, and to improve access to the Wellness Center from Chubbuck. The new underpass is significantly wider and includes bike lanes and sidewalks.

ITD also worked closely with the Portneuf Greenway to construct a pedestrian and bicycle path on the east side of the worksite to connect the Greenway to the Wellness Center.

Work left to wrap up the project will be off the roadway and conducted on the shoulders. In addition, ITD will be seeding open ground with native grasses.

“Thank you for being patient with us and seeing our vision, seeing what we’re trying to do to positively impact this community,” said Project Manager Zak Johnson.

District Engineer Todd Hubbard echoed those sentiments, “This project has been a great success and is an important addition to the community for the safety of drivers. It has been a lot of work to get all of it completed and to keep traffic moving. I want to thank everyone for their patience as we have worked on this project over the last three years. And a thank you to the project team and Sundt-Cannon Joint Venture for a project well done.”

Drivers are encouraged to remain attentive, move over for workers and emergency vehicles, and follow posted speed limits.

Chubbuck Road to open for Fourth of July weekend

Chubbuck road underpass as viewed from the west.

Chubbuck Road is open for traffic under Interstate 15. As part of the redesign of the System Interchange project Chubbuck Road was rebuilt as an underpass with lanes for bicycles and sidewalks. Over the last month the new underpass was closed so crews could build the eastbound lane, construct sidewalks, paint permanent lines and add signs.

ITD expects no further closures of Chubbuck Road. However, crews will continue to work around the site adding vegetation and doing cleanup work. Drivers are encouraged to slow down for workers on and near the roadway.

No cleanup work will occur during the holiday.

Originally built in the 1960s, the I-86 and I-15 System Interchange is undergoing a rebuild to improve safety and replace aging infrastructure. This week crews are painting the final lane lines throughout the project area. Once the lines are completed the remainder of the project will consist of seeding vegetation and other cleanup work that will not affect traffic.

Motorists are encouraged to use 511.idaho.gov or the 511 app to keep track of project detours. Project details are available on ITD’s projects website at itdprojects.idaho.gov/i-86i-15-system-interchange.

Idaho Transportation Department seeks feedback on draft seven-year transportation plan

Exit 93 interchange

The Idaho Transportation Department (ITD) is seeking feedback on the just-released draft Idaho Transportation Investment Program (ITIP). The ITIP outlines the state’s transportation priorities and guides investment decisions for the next seven years through 2032. ITD encourages everyone to review the draft and provide comments July 1-31.

Transportation projects included in the draft ITIP range from large-scale interstate improvements to smaller projects like the installation of new guardrail. Projects are located throughout Idaho’s 44 counties and involve all modes of transportation. Project selection is determined through technical data, as well as input from local officials and residents.

Visit itd.idaho.gov/funding to view an interactive map to learn about projects and submit a comment through the portal.

This draft ITIP shows plans for $5.8 billion in funding, including $200 million dedicated to pavements and $100 million dedicated to bridges each year.

ITD Chief Deputy Director Dan McElhinney outlined, “The Idaho practice of annually updating a seven-year highway transportation plan helps consider the growth of traffic we are all seeing which is accelerating the need for safety, preservation and capacity improvements supporting communities statewide.  This draft ITIP presents investment needs in highway pavement, bridge repairs, and congestion relief improvements that will provide the Idaho Transportation Board effective options to consider looking ahead for Idaho.”

In mid-June, the Idaho Transportation Board accepted staff recommendations to address congestion on priority corridors using Transportation Expansion and Congestion Mitigation funds. These funds came from House Bill 25, which was passed by the Idaho Legislature earlier this year. The legislation provides an additional $20 million a year to the TECM fund for the next three years and allows the department to invest an extra $1 billion in the Idaho transportation system.

The major projects included in the draft ITIP as part of the board’s action include:

  • I-15 and US-26 Interchange (Exit 93): The existing interchange will be replaced to accommodate additional lanes on the interstate and to include longer on- and off-ramps for safer merging. Construction is anticipated to start in 2026, five years earlier than planned.
  • I-15 widening from milepost 89 to 93: This project will add capacity by widening the interstate to three lanes in each direction between the US-26 Interchange and the South Blackfoot Interchange. construction was previously not funded but is now anticipated to start in 2027.
  • I-15 and US-91 South Blackfoot Interchange (Exit 89): The existing interchange will be upgraded to accommodate additional lanes on the interstate and include longer on- and off-ramps for safer merging. Construction is anticipated to start in 2028, three years earlier than planned.

Comments can be emailed to itipcomments@itd.idaho.gov, recorded at 208-334-8063 or mailed to:

ITIP – Comments
Attn: Noah Ipaye
P.O. Box 7129
Boise, ID 83707

Paper copies of the ITIP will be available at regional offices and provided upon request by contacting the Idaho Transportation Department at 208-334-8284.

After approval by the Idaho Transportation Board in September, the ITIP will then be submitted to the Federal Highway Administration, the Federal Transit Administration, and the Environmental Protection Agency in October.

Public input is crucial in ensuring that the ITIP includes the prioritized needs of Idaho’s communities.

Chip sealing to begin Wednesday at I-86 and I-15 System Interchange

Aerial photo of the system interchange at Pocatello.

Beginning tomorrow the Idaho Transportation Department will chip seal the System Interchange in Pocatello. Once this work is complete, the roadway will be restriped to indicate the final lane configurations.

Chip sealing covers temporary lane markings used throughout various phases of construction and maximizes the taxpayers’ investment by extending the lifespan of the pavement. A sticky slurry is sprayed on the pavement then rock chips are applied on top for a long-lasting seal. This treatment protects pavement from sun, oxidation, weather, water, oil and gas, and increases traction for safety.

Tabs will be placed on the new chip seal to indicate lanes for the short time before striping work can occur.

The previous connection between I-86 and I-15 was originally built in the 1960s. Now nearing completion, the System Interchange is a $112 million redesign to improve safety and replace aging infrastructure that began construction in 2022.

Motorists should carefully follow signs and slow down to posted speed limits while traveling through the construction area. With crews working day and night at the System Interchange, it is especially important that drivers be alert and travel safely.

Motorists are encouraged to use 511.idaho.gov or the 511 app to keep track of related detours. Project details are available on ITD’s website at itdprojects.idaho.gov/i-86i-15-system-interchange.

Inkom on-ramp to northbound I-15 (Exit 58) night closures planned for next week

Map of detour in construction area around Inkom.

Due to bridge demolition, the Inkom northbound entrance ramp onto I-15 will be closed for two nights. The West Inkom Interchange northbound entrance ramp (Exit 58) closure will take place from 9 p.m. to 6 a.m. on Monday, June 23 and Tuesday, June 24, weather and other factors permitting.

Traffic will be detoured to Old Highway 91 and then to Exit 63 to head north on I-15. Please watch for crews, use caution, and drive safely.

Due to the nature of the work, considerable noise is expected during the bridge demolition.

The Idaho Transportation Department is in the process of replacing bridges on I-15 at Inkom:

  • Over the Union Pacific Railroad tracks and Old Highway 91.
  • Over Rapid Creek Road (Main Street).
  • I-15 bridges and reconstructing the West Interchange.

ITD combined and streamlined the projects to reduce the construction timeline to approximately two years rather than doing one location at a time over three years. This approach minimizes disruption to the local community and the traveling public and efficiently uses construction funds.

To learn more about the project or sign up for construction updates, please visit: itdprojects.idaho.gov/pages/i15-inkom-corridor. This temporary closure and other traffic impacts will be posted to 511.idaho.gov.

Paving begins north of Blackfoot

A dump truck and paver working on repaving a road.

Tomorrow the Idaho Transportation Department will begin repaving the southbound lanes of Interstate 15 from the Rose/Firth Exit 98 to one mile north of West Blackfoot Exit 93. Traffic will be reduced to one lane in each direction and moved over to the northbound side of I-15.

The project will reconstruct the road to address rutting and potholes. Work is anticipated to be completed in mid-August. The northbound lanes were similarly repaved last year.

Motorists should carefully follow signs and posted speed limits while traveling through the construction area and are encouraged to use 511.idaho.gov or the 511 app to keep track of project detours.

I-15 corridor identified for further funding

Exit 93 interchange

Today at its regular monthly meeting the Idaho Transportation Board accepted staff recommendations on priority corridors across Idaho using TECM funds to address congestion, including three projects on Interstate 15 near Blackfoot. Since Transportation Expansion and Congestion Mitigation funds were first used by the department for bonding and advancing major projects in 2022, ITD has delivered timely construction of expansion projects across the state. Today’s actions are a continuation of that.  

Funding came from House Bill 25, which was passed by the Idaho Legislature earlier this year. The legislation provides an additional $20 million a year to the Transportation Expansion and Congestion Mitigation fund for the next three years and allows the department to invest an extra $1 billion in the Idaho transportation system. 

With this new funding, the following projects have been recommended for advancing to construction: 

  • I-15 and US-26 Interchange (Exit 93): The existing interchange will be replaced to accommodate additional lanes on the interstate and to include longer on- and off-ramps for safer merging. Construction is anticipated to start in 2026, five years earlier than planned. 
  • I-15 widening from milepost 89 to 93: This project will add capacity by widening the interstate to three lanes in each direction between the US-26 Interchange and the South Blackfoot Interchange. Construction was previously not funded but is now anticipated to start in 2027. 
  • I-15 and US-91 South Blackfoot Interchange (Exit 89): The existing interchange will be upgraded to accommodate additional lanes on the interstate and include longer on- and off-ramps for safer merging. Construction is anticipated to start in 2028, three years earlier than planned. 

With these projects now included in the draft Idaho Transportation Investment Program (ITIP), the public will have the opportunity to give feedback on this project and the department’s full list of planned projects from 2026-2032 during the annual comment period in July. Then the draft ITIP will be presented to the board for approval in September.  

The board’s action today reflects continued investment targeting congestion and capacity in major corridors that were previously funded by TECM bonds as authorized by the Idaho Legislature. TECM funds have allowed for the construction of the I-86 and I-15 System Interchange in Pocatello, as well as the widening of I-15 from Northgate to Fort Hall. 

These projects were identified because they are existing high-priority corridor needs that will improve traffic flow and increase safety.  

Construction to begin Monday in American Falls

Map showing final configuration of the intersection of Pocatello Avenue and SH-39

The Idaho Transportation Department will begin construction Monday at the intersection of Pocatello Avenue and State Highway 39 in American Falls. The $3.5 million project will redesign the busy intersection to improve safety.

Work will place a signal at the intersection Pocatello Avenue and SH-39. SH-39 will also be widened to four lanes from the intersection to Fairgrounds Road. New turn lanes will also be built on SH-39 for traffic heading to Pocatello Avenue.

This year construction will take place through August and will focus on realigning and widening the intersection. All lanes will remain open, but traffic will be slowed in the construction zone. Flaggers will be present during different phases of the project. Access to the American Falls Airport and the Power County Fairgrounds will remain open throughout construction.

In the spring of 2026 ITD will return to install the traffic signal. Project details are available on ITD’s projects website at itdprojects.idaho.gov/pages/pocatelloave-i86b.

Night work Tuesday and Wednesday on I-15 at 2.5 Mile Road

Northgate interchange

The Idaho Transportation Department will move Interstate 15 traffic Tuesday and Wednesday nights to accommodate girder placement at 2.5 Mile Road Bridge.

Traffic will be reduced to a single lane in each direction and shifted onto the same side of the interstate. Work will be conducted between 7 p.m. and 5 a.m. each night with a speed limit of 55 miles per hour through the work zone.

Motorists should carefully follow signs and posted speed limits while traveling through the construction area. With crews working day and night on the project to make I-15 three lanes from Northgate to Fort Hall it is especially important that drivers be alert and travel safely.

I-15 serves as a major transportation corridor through eastern Idaho. These improvements will increase capacity and improve safety to serve the region’s growing transportation needs for years to come.

Motorists are encouraged to use 511.idaho.gov or the 511 app to keep track of project detours. Project details are available on ITD’s projects website at itdprojects.idaho.gov/pages/i15northgatetoblackfoot.

Seven-person crash in Southeast Idaho caused by impaired driver; officials urge DUI education

Flowers laying on the dirt beside a road

The Idaho State Police (ISP) and the Idaho Transportation Department (ITD) urge drivers to make safe, sober choices behind the wheel following confirmation that the at-fault driver in a recent fatal crash on U.S. Highway 20 near Henry’s Lake had a blood alcohol content of 0.20 — more than twice the legal limit of 0.08.

The May 1 crash on one of the main corridors to Yellowstone National Park, which claimed the lives of seven people, occurred just as Idaho entered the 100 Deadliest Days — the period between Memorial Day and Labor Day when traffic fatalities typically rise due to increased summer travel, holidays, and impaired driving. Law enforcement and transportation officials say this preventable tragedy underscores the consequences of impaired driving.

“This tragedy should be a wake-up call,” ISP Captain Chris Weadick said. “No one plans to cause a crash or take a life when they get behind the wheel, but choices have consequences. Impaired driving isn’t just illegal — it’s deadly. If you see someone unfit to drive, speak up. Lives depend on it.”

Alcohol-related crashes remain one of the leading causes of traffic deaths in Idaho.

“Idaho’s roads are especially busy during the summer,” ITD Operations Manager Bryan Young said. “With more construction, increased travel, and an influx of visitors, we’re seeing more families and more drivers on the road. It only takes one impaired driver to change lives forever. This is a preventable problem, and it starts with each of us making responsible choices.”

DUI Prevention Tips

  • Plan ahead: If you plan to drink, arrange for a designated driver, rideshare, taxi, or public transportation.
  • Always buckle up: Seatbelts save lives and reduce injuries, though they do not replace the need for safe driving.

This summer, ISP and ITD are partnering to strengthen DUI enforcement and expand public outreach. We ask everyone to help protect lives by staying sober behind the wheel. The public is encouraged to report suspected impaired driving by calling *ISP (*477) or 911 if they observe erratic or dangerous behavior on the road.