Idaho Transportation Board approves funding to study US-95 Long Bridge for replacement

Aerial view of the Long Bridge looking north into Sandpoint

 

Today the Idaho Transportation Board approved $200,000 to start studying replacement options for the Long Bridge on U.S. Highway 95 near Sandpoint. 

“Up until now, we have been performing maintenance projects to delay replacing this expensive structure until it reached 100 years old,” District Engineer Damon Allen said. “But as we’ve looked to widen US-95 south of town, we’ve heard from the public that they want us to look at this sooner rather than later.”  

The study is expected to start in 2025, with the goal of seeking grant funding to finish the study and design. It would include public outreach and updating environmental evaluations. This would be separate from the ongoing plans to make US-95 safer and capable of handling the increase of traffic between Sagle and Lakeshore Drive, though neither is funded for construction.  

The existing bridges—one for vehicles, and the other for pedestrians—were built in 1981 and 1956 respectively. The pedestrian bridge, which originally served vehicles, is no longer able to safely carry traffic and is severely weight restricted.  

Previous studies have identified one four-lane bridge with shoulders and a separated bike and pedestrian facility to replace the two existing two-lane bridges. Costs and staging would be identified in later studies, but the initial estimate for building the northbound half of the proposed structure, including a bike and pedestrian facility, is at least $225 million.  

“This money will allow staff to begin preliminary planning and pursue grant applications for design,” Allen said.  

Crash renders US-95 overpass partially unusable until repairs in the spring

Close up of damage caused to the Brunner Road overpass

 
After being struck by an oversized load on Monday, the bridge on Brunner Road over U.S. Highway 95 will experience a long-term westbound lane closure through winter until repairs can be made in the spring.

An excavator being hauled on a large semi-trailer was not properly secured, and the bucket shifted during transport, causing it to exceed the posted height clearance and strike the bridge overhead as the truck passed beneath.

Idaho Transportation Department staff were immediately dispatched to the scene of the crash to inspect the bridge and determine an appropriate course of action. Based on their findings and expert recommendations, the outside westbound lane of the bridge will be closed for the remainder of winter to prevent load restrictions from being put in place on the entire structure. That will still leave one lane in each direction open for travel.

Crews will also be inspecting the damaged areas weekly to ensure the bridge remains safe for travelers both on Brunner Road and US-95 beneath.

The driver who caused the crash was located and cited by law enforcement. ITD will be working with the private insurance company to recover costs for damage repairs.

It is important to understand that incidents like this are extremely costly and can easily be prevented by taking care—especially when hauling large equipment or oversized loads—to ensure they are properly secured, and remain properly secured, during travel.

Public invited to give input on potential transportation improvements across the Rathdrum Prairie

Logo for the Rathdrum Prairie PEL Study and aerial photos of the prairie.

The Idaho Transportation Department invites the community to attend one of two upcoming public meetings for a study evaluating the state and local roadway system across the Rathdrum Prairie. Input will help develop a range of alternatives for consideration that will improve mobility and connectivity, enhance safety, and address growth. 

This study began in 2023, and since that time the public has participated in the screening process by providing input about the environment, growth, and their unique perspective on a variety of community issues. The input provided during the June public meetings has been incorporated into the current transportation alternatives that will be presented at the meetings next week.  

ITD will also share more information about the Planning and Environmental Linkages study process and timeline of events. 

Identical information will be shared at both meetings, which will be held in an open-house style to allow participants to drop in at their convenience anytime between 4:30 p.m. and 7:00 p.m. to review the information, talk with project staff, and provide feedback 

Public Meetings 

November 13, 2024 

4:30 p.m. -7 p.m. 

Lake City Center 

1916 N. Lakewood Drive 

Coeur d’Alene, ID 83814 

November 14, 2024  

4:30 p.m. -7 p.m. 

Trailhead Event Center at Q’emiln Park 

12361 W. Parkway Drive 

Post Falls, ID 83854 

For those who are unable to attend in person, an online version of this public meeting, including the same content, will be available from November 15-29 at https://itdprojects.idaho.gov/pages/rathdrum-prairie-pel. 

Recommendations from the PEL study, and public and agency input, may be adopted, or incorporated into future National Environmental Policy Act studies. 

Tribal discoveries, wildlife protection propel ITD projects to national awards

Cultural discoveries on a highway construction project in northern Idaho that changes the narrative for Native American heritage in the area, and the state’s first wildlife overpass, were the catalysts for a pair of awards Oct. 31 from the nation’s premiere transportation governing body.

The awards were presented to the Idaho Transportation Department (ITD) at the annual meeting Thursday of the American Association of State Highway and Transportation Officials (AASHTO) in Philadelphia, Pennsylvania.

“These two AASHTO national awards again prove that our employees are fantastic,” confirmed ITD Chief Deputy and Chief Operations Officer Dan McElhinney. “The SH-21 Lucky Peak wildlife crossing is a great partnering example, and the U.S. 95 McArthur Lake Bridge showcased excellent Tribal teamwork. Partnerships solved wildlife safety with cultural preservation success.”

US-95 McArthur Lake Bridge construction

The cultural award was received by Jyl Wheaton of the Kootenai Tribe of Idaho (KTOI) and ITD Project Manager on the construction, CarrieAnn Hewitt.

The project itself was fairly straightforward – an $11M project in Boundary County that rebuilt an existing two-lane section, adding wider shoulders, and replacing a box culvert over Deep Creek, which provides an outlet to McArthur Lake. The existing width-restricted box culvert was replaced with a 300-foot span bridge to provide safe animal passage under the highway. During excavation, tribal artifacts were found, requiring an orchestrated approach to planning for the preservation of these key cultural resources. A one-of-a-kind partnership was forged between ITD, the Kootenai Tribe of Idaho, and contractors to preserve the rich history of the area’s indigenous people. One of the discoveries was a game-changer in terms of traditional thought. Native American artifacts were found that pre-dated the earliest-known timelines – these artifacts showed that the earliest human existence in the upper Columbia River Basin came some 4,000 years earlier than previously thought!

ITD’s Scott Rudel managed the wildlife overpass project, built on State Highway 21 just east of Boise. The $7.5M project constructed a 150-foot long wildlife overpass and more than a mile of big-game fencing parallel to the highway to guide animals to the overpass, significantly reducing wildlife-vehicle collisions on this busy highway section. Improving motorist safety and protecting the well-being of residents and commuters, along with wildlife alike benefits the traveling public, hunting and recreational heritage, and helps sustain the benefits our valuable wildlife resources and public lands provide. ITD wildlife-vehicle crash safety data and Dept. of Fish and Game GPS data determined the location of the overpass by finding where most migrating mule deer and elk crossed the highway. This is the next step in the long-range vision to promote safety, mobility, and economic opportunity along SH-21 between Lucky Peak and Idaho City. The goal is to reduce wildlife collisions in the area by 80%.

The AASHTO President’s Transportation Awards are considered the highest honor for state departments of transportation. It is proof positive that ITD consistently produces great projects on behalf of the taxpayers of Idaho. The two awards mark 23 President’s Awards received since 2014.

Public meeting to share updated plans for US-95 through Sagle

Postcard invitation to public meeting

 

The Idaho Transportation Department will host a public meeting on Wednesday, Oct. 16, to present updated plans for improving U.S. Highway 95 between Dufort Road and Lakeshore Drive.

Project information will be on display between 4 and 7 p.m. at Sagle Elementary School, located at 550 Sagle Road. Community members are invited to stop by and speak with the project staff at any time during those hours.
Identical information and comment forms will be available online from Oct. 16-31 at itdprojects.idaho.gov/pages/us-95-dufort-to-lakeshore.

“We have updated our preferred concept based on continued engineering work and community input,” Project Manager Carrie Ann Hewitt said. “We appreciate the community’s interest in this project and the feedback we have received so far.”

Since the last public meeting in fall of 2023, the project team has updated design plans to include widening US-95, building interchanges, constructing underpasses and updating the frontage road network.
ITD’s plans for US-95 build on two extensive environmental studies from 1999 and 2010 between Garwood and the Long Bridge. Both studies have resulted in numerous construction projects since then.

More information about the project is available here.

Interchange construction on SH-53 set to begin in October aimed at reducing railroad crossings on the prairie

Aerial view of vehicles waiting for a train where Pleasant View Road intersects with SH-53.

The Idaho Transportation Department is beginning construction of an interchange at State Highway 53 and Pleasant View Road in early October. The project will enhance safety in this highly traveled corridor by ultimately eliminating three railroad/vehicle crossings, streamlining access to SH-53, and increasing capacity on key routes. Work will include these primary improvements:

• Constructing a diamond interchange at SH-53 and Pleasant View Road.
• Removing access to SH-53 from four roads: Hauser Lake Road, Hollister Hills Road, Prairie Avenue, and McGuire Road.
• Expanding Pleasant View Road to two lanes in each direction through the interchange.
• Widening SH-53 to two lanes in each direction with a new center median through the project limits.

Crews will start construction with tasks that likely won’t affect existing traffic flow for the remainder of the year. Impacts to drivers are anticipated to start in spring 2025.

This project was first identified in 2006 as part of the Bridging the Valley Study. The BTV’s goal was to improve safety by separating vehicle and train traffic in the 42-mile corridor between Spokane, Washington, and Athol, Idaho. The final design was completed in 2015 with input from interested parties and the community.

In mid-2023, the U.S. Department of Transportation’s Federal Railroad Administration awarded ITD a grant which made construction of this project possible now, rather than years in the future. The grant program was created to improve safety at rail crossings in communities across the country to save lives, time, and resources for American families.

“Communities along SH-53 are regularly impacted by noise and blocked traffic as trains move through this area,” said Project Manager James Dorman. “This project will minimize conflict points and streamline traffic by bringing them safely through the Pleasant View Road interchange.”

Additional financial contributions were made by ITD’s partnering organizations: BNSF Railway and the Post Falls Highway District. The estimated construction cost of this project is $30 million.

People are encouraged to stay informed by visiting the project website and subscribing to emails at itdprojects.idaho.gov/pages/sh53corridor. For statewide traffic information, visit 511.idaho.gov or download the app.

 

 

Lane closures on I-90 between Cataldo and Pinehurst begin Thursday for paving

Map of I-90 work zone between Cataldo and Pinehurst

Starting Thursday the Idaho Transportation Department will begin a nighttime project to resurface a 9-mile section of Interstate 90 from River Road near Cataldo to Pinehurst. This project will involve milling down the driving surface to remove fractures, ruts and flaws and replacing it with a fresh, smooth layer of asphalt.

Work will be conducted Monday through Friday, beginning at 6 p.m. each evening until 6 a.m. the following morning and is expected to be complete by early October.

Although work will be performed at night, drivers will experience single-lane closures during daytime hours as well where the roadway has been milled due to the difference in elevation between lanes.

Several on- and off-ramps within the work zone will have temporary, intermittent nighttime closures during active milling and paving but will be open during the day for access.

  • Exit 39 at Mission Road
  • Exit 40 at Latour Creek Road
  • Exit 43 at Kingston
  • Exit 45 at Pine Creek

Roadside digital signs will inform drivers of specific information regarding ramp closures.

Drivers, especially motorcyclists, should exercise caution when accessing these ramps as they travel over between milled and un-milled lanes.

This work zone will encompass ongoing work at the I-90 Coeur d’Alene River Bridges. Traffic control will be coordinated with the existing work zone to guide drivers through the area safely.

Up-to-the-minute information about lane and ramp closures, traffic impacts, and delays can be found by using the Idaho 511 system.

 

   

Hazard trees removed from North Idaho highways 

Logs after a recent tree removal project along SH-5 in North Idaho.

Operators with the Idaho Transportation Department have spent over 3,000 hours clearing hazard trees from more than 12 miles of highways in the Panhandle this summer.

“In 2023 we initiated a statewide roadside tree assessment and enhanced removal plan to understand the scope of work to expand our ability to address Idaho highway hazards, “ confirms ITD Chief Deputy Director Dan McElhinney, “Working with federal partners and local owners, we have taken lead in clearing highway adjacent hazard trees for improving errant driver safety recovery zones, wildlife visibility, and fire protection widths by using innovative new cutting equipment resources for ITD employees and now adding contracts with local firms to tackle larger removal projects with ITD during the next few years.”

This summer alone ITD maintenance operators addressed a five-mile stretch of State Highway 5 near Heyburn State Park, roughly four miles of State Highway 54 between Athol and Farragut State Park, a three-mile stretch of State Highway 97, multiple zones adjacent to I-90 and several emergency tree removals across State Highway 57 after falls across the roadway.

Next year the department plans to work with the Priest River Ranger District to clear all 37 miles along State Highway 57. Besides making the road safer for travelers, tree removal is also heavily supported from the perspective of the U.S. Forest Service as a fire break through this densely wooded area between Priest River and Priest Lake.

This year staff in North Idaho were also able to test out several new machines to best utilize funding for equipment. One operation planned for two days along Interstate 90 was completed in just four hours with the use of a FAE Forestry Mulcher. The mulcher not only grinds downed trees to eliminate the cost and work of waste removal, but also has the capability to cut and fall trees up to 18 inches in diameter, which represent the vast majority of trees within the roadway clear zone. With the help of its cutting and falling capabilities, this single-operator mulcher also enhances safety by eliminating the need for sawyers to work on the ground within the fall zone.

ITD plans to continue its focus on tree removal along highways by working with agency and utility partners, dedicating staff time to this effort and purchasing new equipment to make operations safer and more efficient.

Short-term railroad crossing closure on SH-54 in Athol begins Tuesday

Traffic crosses a railroad crossing on SH-54

Starting Tuesday, our partners with the BNSF Railway will begin work on their crossing at State Highway 54 in Athol that will require the closure of this intersection for two days.

During this time drivers will need to utilize an alternate route around the work area.

Updates about this closure will be available through the Idaho 511 system, either online, by phone, or through the ap.

Temporary signals to be used ahead of traffic shift on US-95 near McArthur Lake this week

A view of the new bridge surface on US-95 near McArthur Lake

 

Beginning tomorrow drivers can expect to see the return of temporary traffic signals through the end of the week on US-95 near McArthur Lake as guardrail and temporary barrier are installed. By the end of Friday traffic is expected to be shifted onto the bridge, at which time, the temporary signals will be permanently removed.

The adjacent shoofly- the temporary roadway that was constructed last year to divert traffic around the bridge- will begin excavation and work to complete the wildlife underpass will begin.

This project will continue to require reduced lanes, speeds, and intermittent flagging as crews continue to work. Trucks will also be entering and exiting the highway during work days to haul excavated material.

Ongoing updates regarding traffic impacts can be found using the Idaho 511 system.

This project is expected to be completed in late October. Some work, such as final paving, will be dependent on weather conditions as we approach the fall season.