The first project from the I-90 Corridor Study—targeting the busiest five-mile stretch between SH-41 and US-95—is set to begin construction in summer 2025, aiming to improve safety and capacity.

I-90 Widening: SH-41 to US-95

The first project from the I-90 Corridor Study—targeting the busiest five-mile stretch between SH-41 and US-95—is set to begin construction in summer 2025, aiming to improve safety and capacity.


Construction began August 11, 2025!

Initial construction tasks include tree removal from the center median and shoulders, placing temporary barriers, installing work zone signs, minor traffic shifts, and starting construction on the Prairie Trail Bridge. As work begins and continues through fall and winter, drivers can expect:

  • Work will typically occur Monday through Friday with both daytime and nighttime activity, though some weekend work may occur as well.
  • Two lanes of travel being maintained in both directions during daylight hours (lanes may be reduced during nighttime hours as needed).
  • Variable speed limits, with digital signs adjusting speeds based on nearby work activity. Drivers should pay extra close attention to the posted speed limits and drive accordingly.

Please note, construction schedules and impacts are subject to change.

Overview

The five miles of Interstate 90 from State Highway 41 to U.S. Highway 95 are the most heavily traveled and congested in the corridor. This is the first construction project to advance from the I-90 Corridor Study from SH-41 to 15th Street to enhance safety and add capacity to support future traffic volumes. Construction started in August 2025 and is scheduled to take four construction seasons to build, ending in 2029.

Traffic on I-90 near Northwest Boulevard in Coeur d'Alene.

Under construction

Improvements on I-90 from the SH-41 Interchange to the US-95 Interchange include: 

  • Add two lanes in both eastbound and westbound directions of I-90 for a total of four lanes in each direction
  • Replace and widen bridges over Huetter Road, Atlas Road, and Prairie Trail
  • Realign and improve adjacent sections of Prairie Trail and Centennial Trail
  • Lengthen existing on- and off-ramps to allow for a safer merging with I-90 mainline traffic.
    • All ramps at the Northwest Blvd. Interchange
    • Eastbound off-ramp at US-95
    • Westbound off-ramp at US-95

Traffic impacts during construction

Once construction begins, travelers can expect a variety of impacts throughout the project area aimed at maintaining traffic flow and ensuring safety. It’s important to understand that schedules and construction impacts may change.

Key changes will include:

  • Two-lane traffic maintained in each direction during daytime hours.
  • Reduced speed limits and increased fines in work zones for safety.
  • Short-term detours on Huetter Road and Atlas Road during bridge construction.
  • Ramp closures for up to one week for widening and reconstruction, as needed.
  • Reduced shoulder widths throughout the project area.
  • Intermittent impacts to the trails including detours and gravel surfaces.

Safety Benefits

Widening the interstate will allow for better flow of traffic, eliminating stop-and-go conditions that result in rear-end crashes. With more lanes available, drivers wouldn’t need to make last-minute, unpredictable lane changes to jockey for better positioning.

Ramps will be lengthened and brought up to standard, allowing more time to merge safely. Drivers will also be able to address emergency issues with wider shoulders that put more space between them and high-speed traffic, as well as allow for better response time for emergency services during crashes.

Noise Analysis

Noise walls will not be constructed as part of this project.

The project team completed a comprehensive noise analysis of the corridor from SH-41 to 15th Street and determined that only three sections of the corridor meet the requirements of the ITD Noise Policy for feasibility and reasonability. The Traffic Noise Analysis Report recommends noise barriers in the following sections:

  • South of I-90 from 9th Street to E Hazel Avenue
  • North of I-90 from 7th Street to 9th Street
  • North of I-90 from 9th Street east past Burl Lane, ending at the Avista facility

In the full report, these sections are labeled as Barrier 9c (page 139), Barrier 10b (page 141), and Barrier 10c (page 142). Design and construction of these noise barriers will not occur until a project is funded for these sections of I-90.

The ITD Noise Abatement Policy states that specific conditions must be met before traffic noise abatement is implemented. Noise mitigation must be considered feasible and reasonable. The factors considered when determining if mitigation is feasible include engineering considerations and effectiveness. The factors considered when determining if mitigation is reasonable include noise abatement design goals, cost effectiveness, and desirability. Desirability is determined by the benefitted owners and/or renters of the proposed noise barrier once a design project is funded.

ITD Noise Abatement Process

Community involvement

Since 2021, several open houses, surveys, meetings with interested parties, and other public involvement opportunities took place as part of the I-90 Corridor Study. The feedback gathered during those efforts helped shape the final design for this project.

Funding

The I-90 widening between SH-41 and US-95 is funded by Governor Little’s Leading Idaho initiative. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure that would otherwise take many years to fund and build.

The widening improvements from SH-41 to US-95 are estimated at approximately $200 million to $210 million*, which includes design, right of way, and construction costs.

Future design and construction phases of this corridor will be determined based on statewide needs and funding availability.

View TECM Funding

*Costs are estimated in 2025 dollars.

Governor Brad Little's Leading Idaho initiative logo.

Contact the project team

For questions or comments about this project, please contact the project team at info@i90corridor.com or (208) 738-4190

Sign up for email notifications

Stay up to date with important information and news about the I-90 expansion project between Post Falls and Coeur d'Alene!