Nighttime lane closures begin next week on Long Bridge

Aerial view of the Long Bridge looking north into Sandpoint

Starting next week, the Idaho Transportation Department will begin a six-week project on the Long Bridge to address joints and improve winter maintenance operations. All work on U.S. Highway 95 will take place overnight, with crews setting up traffic control each evening at 7 p.m. and wrapping up by 6 a.m. the following morning.

What drivers can expect:

  • Lane closures: The bridge will be reduced to one lane at night. Unlike last year, the contractor will limit the work zone to sections of about 1,000–1,500 feet at a time rather than the full length of the bridge. This change is expected to significantly reduce wait times for drivers.
  • Flagging operations: Crews will alternate traffic through the work zone, but shorter closures should help queues clear more quickly.
  • Oversize loads: The work zone will be wider than last year, allowing more oversize loads to pass through unimpeded. Most oversize loads will be able to pass, but truckers should check Idaho 511 for specific limitations.
  • Rolling schedule: The contractor will use a 10-days-on, 4-days-off schedule to complete the project more quickly. This means the contractor will work some weekend nights.

“After a few seasons of working on the Long Bridge, we’ve learned a lot about what works for traffic control,” Project Manager Preston Sochovka said. “We’re listening to the community and using those lessons to fine-tune our approach this year. We’re optimistic these changes will make it easier for drivers with shorter delays and quicker trips across the bridge.”

ITD has also coordinated with the Lake Pend Oreille School District to help families get to varsity home games on time. On those nights, crews will start work later so traffic is not delayed by construction. While not all events can be accommodated, ITD is working with the district to find the best opportunities to lessen impacts and keep Bulldog spirit high and on time.

This project is necessary to address issues discovered after last year’s overlay work regarding raised joint edges created challenges for snowplows. Joints connect sections of the bridge and allow the structure to expand and contract with the weather. Drivers may not notice a big difference, but this will keep snowplows from catching on the joints and help equipment last longer. Crews will remove the raised edges. They will also add a thin layer of epoxy to protect the roadway from precipitation.

ITD acknowledges that this is the third consecutive year of construction on the Long Bridge and understands the frustration that goes along with it.

“We know it’s not easy to keep coming back,” Sochovka said. “But we’ve learned from last year, and this year’s work is about finishing strong and setting the bridge up for long-term performance.”

The bridge has long been a landmark in the community. The current road bridge, built in 1981, underwent a rehabilitation project a few years ago that extended its design life from 75 to 100 years. Next to it the pedestrian bridge, built in 1956 and now closed to vehicles, was reinforced during that same project.

Looking ahead, ITD is studying options to replace the pedestrian bridge with a new two-lane northbound structure that would also include a bike and pedestrian path. In that plan, the 1981 bridge could carry two lanes of southbound traffic. ITD anticipates pursuing federal grants to advance design work for the new bridge, followed by additional funding opportunities for construction.

Drivers are encouraged to plan extra time when traveling through the area at night and check Idaho 511 for the latest updates on restrictions and delays.

Power of Partnership: SH-3 Rescue Paving

When a stretch of State Highway 3 near Clarkia started showing signs it might not last another winter, District 1 and District 2 crews teamed up to hold it together until a full rebuild can happen next year.

Instead of waiting for contractor availability — and paying the steep price that come along with it — our own forces jumped in to pave the section in late July. The move saved thousands, kept the work on schedule, and gave employees from both districts a chance to step up and deliver a high-quality fix before the weather turns.

The partnership was impressive, to say the least! D2 sent 11 trucks and 11 people to haul asphalt from a plant in Lewiston, while D1 fielded 8 trucks and 14 people to haul from Coeur d’Alene and run the paving operation on site.

Together, crews made dozens of trips a day, at times logging up to three round trips per driver. The remote location also gave new employees in training the chance to rack up valuable CDL hours while contributing directly to the project’s success.

Though traffic is light on this rural stretch, a significant number of vehicles are log trucks hauling to and from the mill. This rescue work to keep SH-3 safe wasn’t just about moving people; it’s also about keeping commerce moving in a region of Idaho where logging and trucking are at the heart of the local economy.

The paving crew also got to put their skills to work on a near-new, high-performance paver recently acquired from Ada County. With top-notch operators and a machine built to deliver contractor-level results, the team produced a surface that’s smooth, durable, and ready to carry traffic safely through winter.

“This was a big lift, on a short timeline, but exactly the kind of situation where our internal forces shine,” said District Engineer Damon Allen. “These guys and gals know the road, they know the challenges, and they know how to work together to get it done. I really appreciate District 2 stepping in to help. This kind of collaboration made the project possible and is exactly what makes ITD strong.”

Beyond the road itself, the project highlighted the value of collaboration across districts and how much can be accomplished when employees bring their skills, equipment, and determination together.

 

Public invited to open house for proposed changes to US-20 west of Idaho Falls

Bus, equipment, commuter and recreational traffic all traveling on US-20 west of Idaho Falls toward the Twin Buttes.

The Idaho Transportation Department is hosting an open house next week to share proposed improvements to U.S. Highway 20 from Idaho Falls to Arco.

US-20 is one of the few highways that run east to west across the entire United States. This section is a vital route for commerce and the 6,000 eastern Idahoans who work at the Idaho National Laboratory.

Originally built in 1950, the roadway requires robust improvements to continue to serve motorists for years to come. The design proposes increasing safety by adding capacity, widening the road to two lanes in each direction starting at Idaho Falls and moving west. Widening will improve safety for freight, agricultural, recreational and commuter traffic where limited passing opportunities and lines of sight now exist.

Those attending the open house will have the chance to comment on these proposed designs, learn the project timelines and see how construction impacts are being mitigated.

Open house details:

Snake River Event Center at the Shilo Inn

780 Lindsay Blvd, Idaho Falls

Thursday, September 4

4:30 p.m. – 6:30 p.m.

For those unable to attend, an online option will be available September 4-18 at us20arcotoif.com.

“We know this route needs improvements and have been very focused on working towards them,” ITD District Engineer Jason Minzghor said. “We’re excited to get public input on the design and see construction happen in the very near future.”

Construction could begin as early as next summer due to additional funds dedicated to the Transportation Expansion and Congestion Mitigation program by Governor Little and the Idaho Legislature earlier this year. This bonding program enhances safety, improves mobility, further strengthens Idaho’s economy and positively impacts communities across the state for years to come.

How ITD teamwork and ingenuity delivered a safer intersection

When traffic starts backing up at the Banks-Lowman and SH-55 intersection in SW Idaho, especially during the busy summer months, locals feel it and so do ITD crews. For years, temporary flagging operations helped keep things moving, but concerns continued to build around congestion, public safety, and the risks faced by flaggers working in live traffic.

So, District 3 Operations took action. Without dedicated funding but with a deep understanding of the need, the department made a bold decision: build and install a traffic signal in-house.

It was the first time ITD crews had taken on a signal project from start to finish, including design, construction, and installation, and they pulled it off in just 15 months. A similar project delivered through the traditional method would have taken 3-5 years and cost around $1.5 million. By handling it internally, ITD completed the work for under $500,000.

“The crews’ efforts, communication, and coordination were exceptional,” Nestor Fernandez, District 3 Operations Engineer, said. “Each team, whether from our own district or assisting districts, was fully committed and invested in completing their tasks. The seamless collaboration across groups ensured work was completed efficiently and to a high standard.”

That creativity was especially important when it came to phasing the new signal. The intersection didn’t have existing turn lanes, and a single-lane bridge had to be managed without introducing excessive delay. Because the design was handled in-house, the team could think outside the box and the result was a tailored solution that worked.

While some highly specialized elements, like foundation drilling and pole installation, were contracted out, the majority of the project was delivered using state forces. ITD teams from across the agency contributed, and that statewide collaboration proved to be a game-changer.

From navigating environmental requirements to expediting material procurement, every step of the process came with a learning curve. But the result wasn’t just a safer intersection, it was a powerful example of what’s possible when teams work together and think creatively.

“Constructing this project with state forces was a unique and valuable experience for the district,” Nestor added. “The positive, seamless collaboration and communication across all sections, and with the contractors, was a key factor in its success, as was the strong ownership each team took in their role.”

The Banks-Lowman signal project has already made a difference for local residents and travelers alike.

Idaho’s historic highway markers get a modern makeover

Old highway sign

Travelers along Idaho’s roads and scenic byways will soon see the first of the new Idaho Historic Highway Markers. These refreshed signs combine storytelling with modern technology, offering visitors a more immersive experience and a stronger connection to the communities they pass through.

The initiative combines two projects across three state agencies. The Idaho Transportation Department and Idaho State Historical Society are partnering to update all highway markers with new historical research and signage. In tandem with these efforts, Visit Idaho is developing QR codes to be installed at each marker location, connecting travelers to an app that offers additional content about the site and nearby activities and amenities. The app will also translate to nine other languages. The digital component is funded in part by a $3.2 million federal economic development grant awarded to ITD in 2022.

The goal is to restore the historic markers to spark curiosity about the state’s expansive history and drive interaction with the app to encourage exploration of Idaho’s rural communities, helping increase overnight stays and drive economic impact across Idaho.

“This project aligns perfectly with many of the initiatives Visit Idaho is focused on. Idaho’s diverse and often rural landscape is filled with communities that we know travelers will enjoy once they go beyond the destinations they already know. We’re excited to incorporate the QR codes as an easy, accessible tool to help travelers find more to explore in our beautiful state,” said Natalie Jushinski, tourism manager at Visit Idaho.

Each of the three state agencies plays a distinct role in this multi-year project:

  • ITD owns and maintains the physical markers and is managing the installation and updated marker designs, which now feature state symbols like the mountain bluebird and the syringa.
  • Visit Idaho, a division of the Idaho Department of Commerce, is developing the QR codes and web-based app connecting travelers to information to explore more in the area.
  • ISHS is responsible for the historical content for the markers, and their historians are updating the text on each marker to amplify understanding of the significance of each site.

The project not only enhances the travel experience but also supports rural tourism and local economies by encouraging deeper exploration. The revitalized markers and digital information provide new opportunities for education, storytelling and visitor engagement for all travelers—both residents and visitors.

“We are grateful to be a part of the Historical Highway Marker program, which continues to create a powerful sense of place for Idahoans. These markers share the stories that make the Gem State truly unique — stories that have been updated and thoroughly researched at a local level, deepening our understanding of Idaho’s vibrant history,” said Janet Gallimore, executive director at ISHS. “They remind us of where we’ve been, connect us to one another, and strengthen the sense of community that defines our state.”

All updated markers and QR codes in ITD’s District 1 in North Idaho are expected to be installed by the end of 2025, with no impact on traffic. The remaining markers and QR codes will be installed in phases by district through 2027.

“We are excited to partner with others to ensure that these roadside displays reflect the beauty and rich history of Idaho,” said Mike Johnson, the division administrator for engineering services at ITD.

Drive sober or get pulled over — Idaho celebrates the heroes who make it home safely

Blonde woman driving car, she is sober and attentive.

BOISE – The Idaho Transportation Department’s Office of Highway Safety (OHS) is joining law enforcement agencies across the state for the 2025 “Drive Sober or Get Pulled Over” campaign, running August 15 through September 1. The effort focuses on preventing impaired driving ahead of Labor Day, one of the deadliest times on Idaho roads.

The numbers are sobering. In 2024, impaired driving claimed 86 lives in Idaho. That’s 36% of all traffic fatalities in Idaho which is the equivalent of losing over three Idahoans every week to a preventable cause.

Nationwide, alcohol-impaired driving accounts for about 30% of all crash fatalities. In 2023 alone, 12,429 people were killed in alcohol-related crashes. That’s one person every 42 minutes, according to the National Highway Traffic Safety Administration (NHTSA).

“These aren’t just statistics,” said Josephine Middleton, ITD Highway Safety Manager. “Every number is a person; someone’s family member, friend, or coworker. This campaign is about more than the legal consequences of driving impaired. It’s about saving lives. If you’re impaired, don’t drive. It’s that simple.”

While these numbers are a stark reminder of what’s at stake, OHS also wants to highlight the everyday heroes who help prevent tragedy. The designated drivers, the friends who call a rideshare, and the people who plan ahead before their first drink. Every sober ride home is a life protected, a crash prevented, and a family kept whole.

ITD urges all Idahoans to join the movement to end impaired driving by following these simple steps:

  • Use a sober driver, rideshare, or taxi.

  • Never let friends drive impaired.

  • Have a plan before the first drink.

Enforcement will be visible, and the message remains clear: Drive sober or get pulled over. But the ultimate goal is not to write tickets. It’s to make sure everyone makes it home safely.

For more information, visit shift-idaho.org.

Public invited to weigh in on US-95 project near Parks Road

Aerial view of US-95 near the Parks Road intersection.

The Idaho Transportation Department invites the community to learn about and provide feedback on a future project to improve safety and increase mobility on U.S. Highway 95 near Parks Road. Construction is still several years away, but design is starting now. Proposed improvements include:

• Eliminating left turns and median crossing to allow right-in/right-out only access to US-95 from Parks Road.
• Building a new frontage road on the east side of US-95 from Parks Road to Lawrence Road, connecting to the existing dead-end and completing the route to SH-53 and even further south.
• Coordinating with the Lakes Highway District on a separate project as they plan to realign Old Highway 95 to Parks Road.
• Addressing congestion issues around the Bunco Road interchange and also near the Bunco Road/Pope Road intersection caused by surges in traffic to and from the neighboring theme park.

In-Person Meeting
Tuesday, August 19, 2025
4:30-6:30 p.m.

ITD Athol Shed
6303 E. Parks Road
Athol, ID

Feel free to drop in anytime between 4:30 p.m. and 6:30 p.m. to view project displays and talk with members of the design team. Staff will be available to walk you through plans, answer questions, and hear your feedback.

Parents, feel free to bring your children along with you! This is a casual, drop-in event and families are welcome.

For anyone who can’t attend in person, the same information shared at the meeting will be available online starting August 19 through September 5 at US-95: Parks Road | ITD Projects.

This project is currently funded for design and construction beginning in 2031 for approximately $10 million.