Four-lane section of US-95 south of Moscow to fully open by Sunday

View of the new pavement near the southern section on the US-95 Thorn Creek to Moscow route.

Starting Sunday drivers will be able to take all six miles of the new four-lane section of U.S. Highway 95 from Reisenauer Hill to Moscow.

Drivers had only been able to travel the first five miles that opened in early July as crews needed to finish work at the Thorn Creek Bridge. With the bridge now complete, drivers can experience the route with minimal delays. Some construction will continue over the next several weeks as crews finish installing permanent barrier, signs, delineators and rumble strips.

Construction of this nearly $90 million realignment began in 2022 to shift the curving, two-lane highway to the east and expand it to four lanes. The new route was funded partially by Governor Little’s Leading Idaho program and was designed to be safer with a flatter grade, fewer curves and better access control.

“We are honored and pleased to provide this much-needed expansion to the region,” District Engineer Doral Hoff said. “Completing this last portion between Lewiston and Moscow gives drivers a safer and more efficient route.”

The project first began in 1999 when the Idaho Transportation Department started efforts to expand all of US-95 to four lanes from the top of Lewiston Hill to Moscow. This six-mile segment was the last to be improved, with most of the corridor undergoing construction in the early 2000s.