The Idaho Transportation Department is widening State Highway 44 between State Highway 16 and Star Road.

SH-44 Widening: SH-16 to Star Road

The Idaho Transportation Department is widening State Highway 44 between State Highway 16 and Star Road.


You're Invited! Thursday, October 22

ITD is inviting you to attend the drop in meeting for the State Highway 44 Widening project. Community members are invited to drop in anytime between 4:30-6:30 p.m. on Thursday, October 22 at Liberty Hall (960 S Main, Star)

Overview

The Idaho Transportation Department is widening State Highway 44 to five lanes between Star Road and SH-16. The project is anticipated to be complete in fall/winter 2027.

Stay up to date

Sign up for construction updates

Sign up to receive construction updates via email or text.

Improvements

Improvements will include:

  • Widening State Highway 44 to five lanes to include two lanes of travel in each direction with a center turn lane.
  • Replacing the existing roadway surface.
  • Connecting pedestrian pathways on the south side of State Highway 44.
  • Relocating utilities.

What to Expect

Construction will happen in stages. Below are impacts you will see throughout the project.

  • Shifting traffic patterns.
  • Most work will occur during the day.
  • One lane will remain open in each direction along SH-44 during the day.
  • Nighttime work is expected.
  • Overnight lane closures and flagging along SH-44 may be necessary.
  • Nighttime noise with equipment and backup alarms.
  • Access to local businesses will be open.
SH-44 and Star Road Intersection in the City of Star.
SH-44/Star Road Intersection

Community Input

Two community members at a State Highway 16 Quarterly meeting in front of a few display boards.

ITD wants to make sure the Star Community is involved throughout the project. ITD will hold several drop-in meetings throughout the project. The first drop-in meeting will be held Thurs., Oct. 22 at Liberty Hall in Star. Additional meetings will occur in 2027.

To stay informed please sign up for updates:


Timeline

The project will begin in fall 2026 with an estimated construction completion date in fall-winter 2027.

  • Fall 2026

    Utility and paving work begins

  • Spring 2027

    Widening & paving operations continue

  • Fall/Winter 2027

    Construction complete


Frequently Asked Questions


Downloads and Resources


Contact the project team