ITD is widening I-84 between the South Jerome Interchange and the Twin Falls Interchange. These improvements will increase capacity and improve safety on I-84 to serve the region for years to come.

I-84 Jerome to Twin Falls

ITD is widening I-84 between the South Jerome Interchange and the Twin Falls Interchange. These improvements will increase capacity and improve safety on I-84 to serve the region for years to come.


I-84 lane closures

Intermittent lane closures will occur on I-84 between Jerome and Twin Falls through the end of construction in 2026. Motorists are encouraged to plan their route in advance by using 511.idaho.gov.

Overview

 

Drone shot of I-84 between Jerome and Twin Falls

Major milestone – Week of March 9

Crews plan to open the newly completed third lane of I-84 between the South Jerome and Twin Falls interchanges (exits 168 and 173) the week of March 9!

All week, motorists can expect lane closures on I-84. Work is weather-dependent and may be delayed due to conditions.

Additional I-84 work near the Twin Falls Interchange

Crews will complete additional work that will require intermittent lane and ramp closures on I-84 near the Twin Falls Interchange through late 2026. Beginning the week of March 9, crews will:

  • Replace aging asphalt on I-84 with new concrete.
  • Re-stripe I-84 to tie the new third lane in with the loop westbound on-ramp.
Drone photo of the Twin Falls Interchange (Exit 173)

2025 project update

Check out the 2025 video update about the I-84 South Jerome Interchange and I-84 Jerome to Twin Falls projects! Work on these projects is expected to be completed in 2026.

What to expect during construction: 

  • Intermittent lane closures will occur on I-84 during the daytime and nighttime. 
  • Traffic shifts and lane changes will occur. 
  • The speed limit on I-84 is reduced. 
  • Ramp changes will occur at exits 168 and 173.
Drone photo of paving work on I-84 between Jerome and Twin Falls
Drone photo of the 400 South Road Bridges under construction.

Improvements include:

  • Widening I-84 to three lanes in each direction. 
  • Replacing the roadway with a new concrete surface. 
  • Reconstructing the 400 South Road bridges. 

Leading Idaho

This project is being funded with Transportation Expansion and Congestion Mitigation (TECM) funds as a part of the Leading Idaho TECM Program. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure today that would otherwise take many years to fund and build. 

Leading Idaho With Transportation Logo
Drone photo of the I-84 South Jerome Interchange (Exit 168) under construction.

I-84 South Jerome Interchange

ITD is also working on the I-84 South Jerome Interchange (Exit 168) in Jerome.  Click here to view the project website.

Stay in touch!

To sign up for construction updates:

  • Click here to sign up for emails
  • Click here or text 84JTF to 1-866-483-8422 to sign up for texts