Garrity Interchange Repaving Update
Crews are repaving the eastbound off-ramp at the Garrity Interchange (Exit 38) in Nampa starting Friday, August 7.
The eastbound off-ramp will close on Friday, Aug. 7 at 9 p.m. and reopen Monday, Aug. 10 at 5 a.m.
- Motorists will be detoured to the Franklin Boulevard Interchange (Exit 36) in Nampa. See the detour map.
Overview
The Idaho Transportation Department will begin repaving multiple on- and off-ramps along I-84 and I-184 in the Treasure Valley.
Repaving is an extensive process that involves removing the old roadway and placing new pavement. This process addresses flaws in the roadways and restores the surface of the ramps.
ITD will pave ramps at the following interchanges:
- Franklin Road Interchange (Exit 1A) in Boise
- Eagle Road Interchange (Exit 46) in Meridian
- Ten Mile Interchange (Exit 42) in Meridian
- Garrity Interchange (Exit 38) in Nampa

Anticipated Traffic Impacts
Here’s what to expect:
- Work will begin the week of July 13 and is anticipated to be complete by mid-September.
- Most work will take place at night between 9 p.m. and 5 a.m.
- Only one ramp will be closed at a time.
- Traffic will be detoured.
- Some weekend closures will be necessary. Stay tuned for more details.




Frequently Asked Questions
This project includes repaving multiple on- and off-ramps along I-84 and I-184 in the Treasure Valley. Repaving will improve safety and extend the service life of the ramps. The project is scheduled to take place during the summer of 2026.
Repaving is a regular maintenance activity that addresses issues created by high level of use and weather damage on a roadway. Paving can also restore the surface of the ramps. I-84 is the main thoroughfare connecting the west and east ends of the Treasure Valley and experiences high volume of traffic each day.