The Idaho Transportation Department will rehabilitate US-95 from Fruitland to Payette starting in May 2026.

US-95, Fruitland to Payette

The Idaho Transportation Department will rehabilitate US-95 from Fruitland to Payette starting in May 2026.


Construction Update October 5 to October 11

Paving in Payette

Crews are preparing US-95 between the Y intersection and 7th Avenue N for paving operations, which are expected to begin late next week.

Flaggers are still directing traffic on US-95 at the following intersections:

  • Y intersection
  • NE 10th Ave
  • 6th Ave S

US-95 from 6th Avenue S to 7th Avenue N is reduced to one lane of traffic in each direction.

Paving in Fruitland

Paving continues on the southbound lanes of US-95 from just before Gayway Junction to NW 24th St.

Crews are expected to finish paving US-95 between these intersections sometime next week.

What to expect:

  • One lane open in each direction with occasional flagging
  • 35 mph speed limit in the work zone
  • Shifting traffic patterns
  • Delays, allow extra time and consider an alternate route

Construction activity, locations and schedule may be subject to change.

Overview

The Idaho Transportation Department is rehabilitating 5.3 miles of US-95 in Fruitland and Payette this summer. Work will start just south of Gayway Junction and end north of Payette. Crews will start by replacing several irrigation and utility crossings, with paving operations following.
Work is expected to finish in fall 2026.


Stay informed

Project Schedule

  • Early spring 2026

    Replace utilities

  • Late spring/early summer 2026

    Begin paving operations

  • Fall 2026

    Finish construction


Expected Traffic Impacts

  • Lane closures on US-95 depending on activity and location
    • Single lane closures
    • Reduced to one lane with flaggers when necessary
  • Daytime and nighttime work
  • Delays, consider using an alternate route

Frequently Asked Questions

Downloads and Resources