The Idaho Transportation Department will rehabilitate US-95 from Fruitland to Payette starting in May 2026.

US-95, Fruitland to Payette

The Idaho Transportation Department will rehabilitate US-95 from Fruitland to Payette starting in May 2026.


Overview

The Idaho Transportation Department is rehabilitating 5.3 miles of US-95 in Fruitland and Payette this summer. Work will start just south of
Gayway Junction and end north of Payette. Crews will start by replacing several irrigation and utility crossings, with paving operations following.
Work is expected to finish in fall 2026.


Stay informed

Current Traffic Impacts

Paving Work in Fruitland

Paving on US-95 between the south end of the Payette River Bridge and 16th Avenue is scheduled to begin this week. Crews will not pave through the intersection of US-95 and 16th Avenue (US-30). Paving through the intersection will happen at a later date.

What to expect:

  • One lane open in each direction with occasional flagging
  • 35 mph speed limit in the work zone
  • Shifting traffic patterns
  • Delays, allow extra time and consider an alternate route

Shoulder Work in Payette

Crews continue to demolish sidewalks and gutters along US-95 from 6th Avenue to north of 7th Avenue in Payette. Crews are also working on approaches and driveways north of 7th Avenue.

What to expect:

  • Reduced to one lane with temporary signals directing traffic at NE 10th Ave and 6th Ave
  • Some approaches fully or partially closed
  • 35 mph speed limit in work zone
  • Delays, allow extra time and consider an alternate route

Construction activity, locations and schedule may be subject to change.

Alternate Route

This project is expected to create congestion and significant delays in the Payette/Fruitland area. Please plan ahead, check 511 and allow for extra time or consider an alternate route.

Please remember:

  • Use caution when driving in work zones and be courteous of other motorists
  • Watch for flaggers in the roadway
  • Slow down
  • Don’t block intersections, driveways and entrances to businesses

Project Schedule

  • Early spring 2026

    Replace utilities

  • Late spring/early summer 2026

    Begin paving operations

  • Fall 2026

    Finish construction


Expected Traffic Impacts

  • Lane closures on US-95 depending on activity and location
    • Single lane closures
    • Reduced to one lane with flaggers when necessary
  • Daytime and nighttime work
  • Delays, consider using an alternate route

Frequently Asked Questions

Downloads and Resources