This project will reconstruct US-30 through Soda Springs from the east city limit to the west city limit.

Soda Springs US-30 Road Reconstruction

This project will reconstruct US-30 through Soda Springs from the east city limit to the west city limit.


Overview

This project will rehabilitate US-30 through Soda Springs and add a turn lane for the Sherriff’s office. A mill and inlay will be done between the east city limits and 3rd Street East. The reconstruction of the roadway will be between 3rd Street East and the west city limits. Construction is scheduled to conclude in the fall of 2026.

 

Construction Summary of Week of 11/9

We had a great week last week. We have completed paving on the South portion of US-30. Paving operations took place Sunday through Friday. Saturday was not worked due to inclement weather. Paving operations resumed on Sunday. Traffic control was adjusted to have traffic driving on the South portion of US-30 on Friday.

Upcoming Construction for Week of 11/16

Paving will take place on Monday Nov. 16. Inclement weather is expected throughout the week. We will assess each day and pave when weather allows.

The project is still proceeding as anticipated to be paved out by the first part of December. We appreciate the community’s understanding and patience as we continue to complete this work.


Construction Summary of Week of 11/2

Sunday and Monday were not worked due to inclement weather. Paving operations took place Tuesday through Sunday. Traffic control was adjusted to have traffic driving on newly placed asphalt pavement on Thursday. Paving operations have continued on the South portion of US-30.

Upcoming Construction for Week of 11/9

Paving will take place on Monday Nov. 9 and will continue every day through Saturday Nov. 14, provided that weather allows and no other unforeseen issues arise. Sunday work will be evaluated at the end of the week as it is showing a chance of inclement weather.


Construction Summary of Week of 10/26

Paving took place on Monday, Tuesday, and Wednesday. The Contractor used Thursday to work on their plant and asphalt mix to improve the material they are placing in Soda Springs. Paving operations resumed on Friday. Saturday and Sunday were not worked due to inclement weather.

Upcoming Construction for Week of 11/2

Monday had no paving as the project site was not ready to be paved due to the rain we received over the weekend that saturated the ground with water. Paving started again on Tuesday Nov. 3 and will continue every day that weather allows, and no other unforeseen issues arise. The contractor is planning to continue paving the north portion of SH-34. If everything goes well, traffic will shift onto this new pavement by this weekend when they plan to start paving the south portion of the road.


Nov. 2 Project Update

All underground utility, curb and sidewalk work is complete. The remaining work left to be done is paving and placement of a few manhole components. The contractor has staffed up to work 7 days a week until the road has been paved completely. Weather and other issues outside of their control may cause some paving delays. The project is scheduled to be completed by early December. This will include paving all 5 lanes from curb to curb including connections for approaches.

Next summer the contractor will come back to perform a seal coat and re-striping.


Past project updates

The Idaho Transportation Department has begun work on U.S. Highway 30 through Soda Springs, with lane closures expected to start April 30.

This week traffic control is being placed in preparation for full construction beginning next week. The $13 million project will rebuild US-30 through town. In addition, a turn lane will be added to improve access to the Caribou County Sherriff’s Office. During construction the city will also be replacing utilities.

The roadway will be constructed in phases to allow continuous use without need of a detour. Phase 1 will be replacing utilities on the eastbound side of US-30. Phase 2 will be replacing utilities on the westbound. Phase 3 will lay asphalt on the westbound side. Phase 4 will pave the eastbound side. Phase 5 will add another layer of asphalt on the westbound side.

Drivers should expect lane reductions in town during the reconstruction. Once resurfacing starts on July 6, a pilot car will guide traffic on the east end of town past the intersection of US-30 and South 3rd Street. ITD will maintain access to businesses and residences during construction. The project is expected to be completed this fall.

The road has needed multiple patches in recent years. This project will address the underlying causes of the road’s deterioration. US-30 will not only be smoother but will also require less construction in the coming years. 

East City Limit to West City Limit

US-30 through Soda Springs

This project is reconstructing a portion of US-30 through Soda Springs. In addition, a new turn lane will be placed in front of the Sherriff’s office to allow for safer turns into the office.

What safety improvements will be made? – A turn lane will be extended to accommodate left turns into the Sheriff’s office. This will prevent stopped cars in the lane of travel.

How will this affect business access? – The project will be phased to minimize impacts to businesses. We expect disruptions to last a few days. During construction, access to businesses will be maintained.

What about the sidewalk ramps at the intersection of US-30 and 3rd Street East? – ITD will be placing ADA ramps at all four corners of the intersection.

Where will the mill and inlay portion of the project be done? – The mill and inlay will be done between the east city limits and 3rd Street East.

Where will the reconstruction of the roadway be done? – The reconstruction of the roadway will be between 3rd Street East and the west city limits.

What about the 4th of July parade? – ITD is working closely with the city to ensure a safe route will be available for the parade. 

Will sidewalks and curbs be replaced? –  This project does not include replacing sidewalks and curbs.

How long will the water and sewer disruptions last? – Where required, the contractor will provide temporary bypass to maintain uninterrupted utility access to the existing users.

Contact Project Team

If you have questions or comments about this project, please contact the project team at Connor.Slack@itd.idaho.gov