The Idaho Transportation Board has approved $200,000 to begin a study exploring replacement options for the Long Bridge on US-95 near Sandpoint.

US-95 Long Bridge replacement study

The Idaho Transportation Board has approved $200,000 to begin a study exploring replacement options for the Long Bridge on US-95 near Sandpoint.


Overview

For more than a century, the Long Bridge has connected the Sandpoint area across Lake Pend Oreille—beginning with a record-setting wooden structure completed in 1908. Since then, it has evolved through multiple iterations, including the current vehicular bridge built in 1981 and the original 1956 concrete structure which now serves as a pedestrian path. With both bridges showing their age and capacity needs growing, the time has come to begin planning for a replacement that can better serve drivers, cyclists, and pedestrians into the future.

Side view of the Long Bridge near Sandpoint

Project information

In December of 2024, the Idaho Transportation Board approved $200,000 to start studying replacement options for the Long Bridge on U.S. Highway 95 near Sandpoint. The study began 2025, with the goal of seeking grant funding to finish the study and begin design. It would include public outreach and updating environmental evaluations. 

The existing bridges—one for vehicles, and the other for pedestrians—were built in 1981 and 1956 respectively. The pedestrian bridge, which originally served vehicles, is no longer able to safely carry traffic and is severely weight restricted. 

Previous studies have identified one four-lane bridge with shoulders and a separated bike and pedestrian facility to replace the two existing two-lane bridges. Costs and staging would be identified in later studies, but the initial estimate for building the northbound half of the proposed structure, including a bike and pedestrian facility, is at least $225 million.

As the study progresses information about replacement options and future design and construction will be made available on this site. 

This project will be separate from ongoing plans to expand US-95 through the Sagle corridor to make the highway safer and more capable of handling increased traffic between Sagle and Lakeshore Drive, though neither is funded for construction at this time.

Did you know?

On May 26, 1908, the first piling for the wooden bridge was driven. When completed, the bridge was supported by 1,540 pilings and covered a distance of almost two miles. It was advertised as the longest wooden bridge in the world! 

Historical photo of the original wooden Long Bridge near Sandpoint

Timeline

The information below describes a brief history of some of the maintenance and major improvements that have been completed to maintain the Long Bridge since 1956, and will also include future planning and design milestones as the replacement study progresses.  

  • 1956

    Original concrete bridge was constructed

  • 1977

    Bridge deck was resurfaced, expansion joints repaired, and guardrail repainted

  • 1981

    Original bridge was decommissioned as a vehicular bridge and converted into a pedestrian facility

  • 1981

    Construction began on the existing vehicular bridge

  • 2008

    Epoxy overlay on vehicular bridge surface

  • 2015

    Pile preservation pilot project and bridge deck overlay on vehicular bridge

  • 2016

    Pedestrian bridge joints sealed

  • 2021

    Vehicular bridge improvement project to replace joints, repair cracks, preserve piles, repair sea wall and replace navigation lighting

  • 2021

    Pedestrian bridge joint replacement and navigation lighting replacement.

  • 2024

    Epoxy overlay on vehicular bridge surface

  • 2024

    ITD Board approves funding to begin studying Long Bridge replacement options

  • 2025

    Long Bridge replacement study begins

Historical photo of construction on the original Long Bridge
Black and white photo of ongoing construction of the original Long Bridge
Black and white photo of pilings used to construct the Long Bridge
Historical photo of the Long Bridge.
Historical photo of early construction of the Long Bridge
Historical photo of a barge being used in early construction of the Long Bridge
Side view of the pilings that support the Long Bridge on US-95

Contact the project team

For questions or comments about this project, please contact the project manager at carrieann.hewitt@itd.idaho.gov or (208) 772-1200