I-86 to I-15 detour scheduled for tonight

POCATELLO – Beginning this evening at approximately 8:00 p.m. paint crews will be restriping the ramp from I-86 to I-15 southbound. Work will continue through the night and will end at approximately 6:00 am tomorrow. During the restriping work the ramp will be closed and southbound traffic will be detoured through the Northgate Interchange. While it is hoped the work will be completed in one night, there is a possibility the detour will also be used Thursday night to finish striping.

Motorists should carefully follow road signs, obey work zone speed limits, and share the road with other vehicles navigating detours.

Those interested in receiving regular updates on the project can visit the project website at https://itdprojects.org/i-86-i-15-system-interchange and sign-up for email updates.

I-86/I-15 October Detour

 

Public invited to attend public scoping meeting for I-15/US-20 Connector Study on October 18, 2022 in Idaho Falls

RIGBY -The Idaho Transportation Department (ITD) will host a public scoping meeting for the I-15/US-20 Connector project on October 18, 2022.

ITD is initiating an Environmental Impact Statement (EIS) in cooperation with the Federal Highway Administration (FHWA) for the I-15/US-20 Connector project. The EIS will analyze three alternatives (E3, H2 and the no-build) from the Planning and Environmental Linkages (PEL) study.

This meeting is an opportunity for the public to review the outcomes of the PEL study and provide comments as the project moves into the next phase. Public input will be an important part of choosing the final project that best fits the community’s needs.

The meeting will be held from 4 p.m. to 8 p.m. at the Snake River Event Center in Idaho Falls. Presentations are scheduled for every half hour beginning at 4 p.m., followed by a guided tour and an open house. ITD is asking participants to please consider a later presentation slot to avoid crowds at the start of the meeting.

For those unable to attend in person, an online meeting will be available at http://i15us20connector.com from October 11 through October 25, 2022. Please submit comments by October 26, 2022.

For questions or to learn more, please call 208.813.0027 or visit http://i15us20connector.com

 

I-15/I-86 Detour at Pocatello Ends

I-86/I-15 Construction

Leading Idaho LogoPOCATELLO – The northwest ramp from I-15 to I-86 reopened this morning at the System Interchange in Pocatello. Traffic heading from I-15 toward Chubbuck and American Falls is no longer detoured through the Northgate Interchange. The detour was needed to lower the ramp so new bridges can be built for I-15 through the System Interchange.

Motorists should carefully follow signs and posted speed limits while travelling through the construction area. With crews working day and night it is especially important that drivers be alert and proceed safely through the work area. Drivers are encouraged to check https://511.idaho.gov or the 511 app to keep track of road conditions and construction. Project details are available on ITD’s projects website — https://itdprojects.org/projects/i-86-i-15-system-interchange/

This project is partially funded with Transportation Expansion and Congestion Mitigation (TECM) funds as part of Governor Little’s Leading Idaho initiative. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure today that would otherwise take many years to fund and build.

View of System Interchange showing northwest ramp with traffic

System Interchange Detour Begins Tonight

TECM Program

POCATELLO – Beginning tonight, Tuesday September 6 at 10:00 p.m., the northwest ramp of the System Interchange at Pocatello will be closed for construction. The closure will allow the ramp to be lowered prior to beginning bridge construction.

Motorists travelling north on I-15 wishing to proceed west on I-86 toward Chubbuck will be detoured through the Northgate Interchange. The closure and detour will remain for approximately three weeks until the new ramp is completed.

Motorists should carefully follow signs and posted speed limits while travelling through the construction area. With crews working day and night it is especially important that drivers be alert and proceed safely through the work area.
Drivers are encouraged to check https://511.idaho.gov or the 511 app to keep track of the project detours. Project details are available here on ITD’s projects website — https://itdprojects.org/projects/i-86-i-15-system-interchange/

This project is partially funded with Transportation Expansion and Congestion Mitigation (TECM) funds as part of Governor Little’s Leading Idaho initiative. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure today that would otherwise take many years to fund and build.

Map of detour
Motorists travelling north on I-15 wishing to proceed west on I-86 toward Chubbuck will be detoured through the Northgate Interchange.
The detour through the Northgate Interchange will exit at Northgate, cross over I-15, and then proceed south on I-15.

Leading Idaho Logo

Fires burning along I-15 at Pocatello and at Malad Summit

Fire at Malad Summit

POCATELLO – Multiple fires are burning along I-15 at Pocatello. There is also a fire at Malad Summit on I-15. Fire crews are actively working in the areas, but traffic is delayed or blocked. Motorists are encouraged to slow down, watch for and move over for emergency vehicles and check 511.idaho.gov or the ITD 511 app to receive road status updates. The causes of the fires are not yet known.

Drivers should take extra care while driving through Idaho this weekend with fire danger high amid unseasonably warm temperatures. In particular, motorists should:

  • Ensure tow chains on trailers are not dragging which can cause sparks.
  • Tires on vehicles and trailers are in good condition for highway driving. A blown tire can cause the wheel rim to kick sparks into dry grass.
  • Never throw cigarettes or other combustible materials out of a vehicle.
  • Never throw glass or other litter out of a vehicle. Glass bottles and other objects can reflect or focus the sun’s rays causing ignition.
  • Do not park your vehicle over dry grasses when you pull off a road. The exhaust and other hot portions of the undercarriage can ignite a fire.
Fire crews responding to one of the fires along I-15
A burned area near the southbound lane of I-15
Pocatello Fire Department and other agencies quickly responded to the fires.

Historic rebuild of System Interchange at Pocatello begins

Looking at system interchange from the west

 
POCATELLO – Preliminary work on the Idaho Transportation Department’s project to rebuild the I-86/I-15 System Interchange is beginning this week. Originally built sixty years ago, the design needs to be updated to handle greater traffic volumes and to replace aging bridges that are reaching the end of their life. Joint venture contractors Sundt-Cannon is expected to begin moving equipment into the project area before the end of the week.

The scale of the endeavor is truly historic and took years to bring to fruition. When completed, approximately 900,000 cubic yards of excavation will be completed. In addition, about 225,000 tons of base material will be brought in; 111,000 tons of asphalt will be placed; and over 6,500 cubic yards of concreate will be poured. 70,000 square feet of retaining walls will also be built throughout the project area. Finally, ITD will build eight new bridges. Four of those will use precast concrete girders and four will have steel girders. In all, nearly 5,000,000 pounds of steel will be used in the bridges. Crews will work year-round for approximately three years to complete the project.

The two most significant changes motorists will see during construction are a detour for traffic travelling from I-15 northbound to I-86 westbound and the closure of the Chubbuck Road overpass.

In early August, northbound traffic from I-15 exiting west toward Chubbuck will be detoured through the Northgate Interchange and back onto I-15 South to then proceed to I-86 West. To maintain traffic for the anticipated 2-year construction of the project, the ramp will need to be lowered prior to beginning bridge construction. This necessitates the ramp closure and detour through the Northgate Interchange. This work should be completed by early September.

The Chubbuck Road overpass will be closed around August 1st, prior to the beginning of the school year, and will remain closed during the duration of the project. Construction will remove the existing bridge, excavate new embankments, and create bridges for I-15 to pass over Chubbuck Road. The final Chubbuck Road design will be easier and safer to navigate for motorists, bicyclist, and pedestrians. During construction motorists will be detoured through the Northgate interchange.

Westbound traffic detour map
During the first phase of construction traffic from northbound I-15 intending to travel west will be detoured through the Northgate interchange.

While demolition of the Chubbuck Road overpass will not begin immediately, an important concern for the school district and other interested parties was altering bus routes and student driving routes after the beginning of the school year. This could cause unnecessary delays and confusion for buses, faculty, parents, and students.

“The school district had some real concerns about making a change during the school year and we are doing what we can to accommodate them for the safety of the students and smooth operation of the schools,” said project co-manager Zak Johnson.

The $112 million project to rebuild the system interchange is a massive undertaking that requires extensive coordination with many different parties. ITD has been in close contact with city leaders, ISP, the Bannock County Sheriff’s office, emergency response, schools, regional transit, and others to ensure the safety of Idaho citizens and motorists passing through Southeast Idaho.

An important question some in the community express is, why now?

“The aging bridges will continue to get closer and closer to the end of their design lifespan,” said project co-manager Greg Roberts, “They would still be functional, but weight limits would start to have to be imposed on truck traffic. That would negatively impact Pocatello’s economic future.”

That is an important concern for Idaho businesses. Large loads, called “mega-loads”, travel through the Gate City to Montana and west to other regions of Southern Idaho. Local manufacturing companies need to be able to move their products to their customers quickly and safely.

However, it is not just the age of the 1960’s bridges that is a concern. When the System Interchange was built there was almost no development on the east side of I-15. Today the Highland area has subdivisions, a high school, the fairgrounds, and the Wellness Complex. In addition, development at Northgate has begun and will result in even more traffic.

“We can only expect traffic volume to increase and with it congestion,” said Roberts. “That will cause the ‘weave’ between the Pocatello Creek onramp and the Chubbuck exit to get worse. Traffic entering, I-15 intending to head toward Chubbuck already has difficulty during peak times crossing all the way to the left to head west on I-86.”

The issue for drivers now is finding a gap to slip into so they can head west toward Chubbuck.

“That will only get worse if we do nothing,” added Johnson, “Gaps between cars will become smaller and smaller making it more difficult to safely merge. Drivers will be forced to make more aggressive lane changes to head to Chubbuck. That kind of situation increases collisions. We don’t want to wait until things become dangerous and people get hurt.”

Safety is a primary concern for project managers and the contractors as motorists prepare to drive through the work site. “These are our neighbors and family working out there,” said Roberts. “We do everything we can to make the worksite safe, but it’s really important that drivers follow posted speed limits, watch for lane changes and signs, and give other motorists space on the road.”

Diagram of Chubbuck Road detour
The Chubbuck Road detour will take motorists through the Northgate Interchange.

Both Roberts and Johnson have seen severe worksite accidents caused by inattentive drivers. In one instance a motorist followed a work truck directly into the work site. Unfortunately, deaths do occur and it is often the result of a motorist that do not take care in a work zone.

“It’s something that never leaves you,” said Johnson as he reflected on a fatality on a previous project. “We do everything we can to keep people safe, but when it happens it’s hard not to take it personally. We just ask everyone to please keep themselves, their families, and their neighbors safe while this project is being completed.”

Once completed, the new System Interchange will be safer and ready to carry the increased traffic volumes for the fastest growing state in America.

This project is partially funded with Transportation Expansion and Congestion Mitigation (TECM) funds as part of Governor Little’s Leading Idaho initiative. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure today that would otherwise take many years to fund and build.

This video describes how the new interchange will work and improve mobility and safety for the public – https://youtu.be/KRdVBAyXweA

Project details are available here on ITD’s projects website — https://itdprojects.org/projects/i-86-i-15-system-interchange/

 

Overhead view of new Chubbuck Road underpass
The new design changes Chubbuck Road into an underpass with additional space for pedestrians and bicycle lanes.
Overhead view of interchange
Vehicles travelling northbound from Pocatello Creek Road will merge with I-86 traffic on a new ramp. Both lanes will then meet with I-15 northbound traffic near Chubbuck Road.

 

Overhead view of interchange
When completed, westbound traffic from Pocatello Creek Road will pass under I-15 to merge with I-86.

 

ITD to hold open house on I-15 planning project between Northgate and Blackfoot

Vehicles on I-15

 
POCATELLO – The Idaho Transportation Department (ITD) is hosting an open house from June 6 – 13 to share information and gather public input about designs to widen I-15 between the Northgate Parkway Interchange (Exit 73) and Blackfoot.

Map of project area with description of anticipated improvements
Download full-resolution PDF
“Most of I-15 was constructed in the 1960s and 1970s and it is aging and nearing capacity in some areas,” said ITD District 5 Engineering Manager Eric Staats. “We are excited to be moving forward with a planning and design process to improve safety and capacity on I-15 between Pocatello and Blackfoot.”

The I-15 Northgate to Blackfoot Project is part of a multi-year planning process to improve I-15 between Pocatello and Idaho Falls.

“This project between the Northgate Interchange and Blackfoot will provide environmental clearance and develop widening options for future projects,” said Staats. “We would like the public’s input on the widening options that are being developed.”

The public is invited to stop by the open house any time between 4:00 p.m. to 6:30 p.m. on Wednesday, June 8 at the Shoshone-Bannock Casino Hotel, Chief Targhee Room (777 Bannock Road) in Fort Hall. ITD will be on hand to discuss the project and proposed widening improvement options.

The same information will also be available online at https://itdprojects.org/projects/i-15northgatetoblackfoot/ between June 6 – 13. Participants can review materials online and submit comments.

Elements of this project are being funded with Transportation Expansion and Congestion Mitigation (TECM) funds as part of the Leading Idaho TECM Program. To address the state’s rapid growth, the legislature passed a historic transportation revenue package that Governor Little signed as part of his Leading Idaho initiative in May 2021. House Bill 362 raised the percentage of sales tax going towards transportation from 1% to 4.5%, with bonding authority granted to ITD to invest in safety and capacity needs across the state. The program allows ITD to accelerate project timelines to address rapid growth and build critical infrastructure today that would otherwise take many years to fund and build.

For more information, please visit the project website at https://itdprojects.org/projects/i-15northgatetoblackfoot/

 

Public comment sought on I-15/Siphon Road Interchange project

I-15 Sign

POCATELLO – The public is invited to submit input via an online comment portal on the proposed Interstate 15/Siphon Road Interchange project. The project is currently being developed, with construction starting as early as 2018.

The interchange will be built approximately three-quarters of a mile north of the Chubbuck Road overpass (milepost 73.5) in Bannock County.

The public comment portal can be found at: http://arcg.is/1quH81.

The portal includes a comment form and map featuring the preliminary design of the proposed interchange and its local connector roads. Additionally, it allows users to view a listing of all submitted comments.

The I-15/Siphon Road Interchange project includes the construction of a bridge over I-15 with interstate highway entrance/exit ramps. Any new local roads connecting the existing local-road network to the new interchange will be built by local entities prior to the completion of the new interchange.

The need for the interchange arises from the following issues:

– Limited existing access to I-15 north of the I-15/I-86 junction causes out-of-direction travel that contributes to congestion on U.S. 91 (Yellowstone Avenue)

– Limited existing access to I-15 north of the I-15/I-86 junction is not expected to accommodate the area’s projected future growth northeast of Pocatello and Chubbuck in Bannock County

– Crash rates on U.S. 91 and I-15 in the Pocatello/Chubbuck area exceed statewide averages

Since the previous public outreach for the I-15/Siphon Road Interchange project was concluded more than five years ago, the transportation department will provide an update on the project and invite the public to submit comments on the proposed interchange layout.

Comments are being accepted through July 31. They can be e-mailed to adam.rush@itd.idaho.gov, or to greydon.wright@itd.idaho.gov. Comments also can be mailed to: Idaho Transportation Department, Attn: Adam Rush, 3311 W. State Street, Boise, ID  83703.

Those with questions about the project can contact Adam Rush at (208) 334-8119, or Greydon Wright at (208) 239-3317.

For questions or comments regarding the construction of the new local connector roads outside interstate right-of-way, please contact the city of Chubbuck, city of Pocatello, or Bannock County.