Northbound I-15 traffic between the Northgate and Fort Hall interchanges shifts this week

I-15 with construction being conducted on the new lanes between northbound and southbound lanes.

The Idaho Transportation Department will shift northbound Interstate 15 traffic between the Northgate and Fort Hall interchanges (Exits 73 and 80) the night of Wednesday, Nov. 12. Northbound traffic will move into the newly constructed lanes in the median to allow crews to begin work on the east side of I-15.

During the traffic shift, motorists can expect:

  • The northbound on-ramp at the Northgate Interchange (Exit 173) will close for a few hours on Wednesday night, Nov. 12.
  • Lane closures may occur in the project area.

After traffic is shifted, motorists can expect:

  • Two lanes will remain open in each direction on I-15 during the daytime.
  • A concrete barrier will separate opposing lanes of traffic.
  • Reduced speeds in the work zone.

Once the new northbound lanes are completed in late 2026, crews will complete the southbound lanes on the west side of I-15. Construction on the I-15 Northgate to Fort Hall widening project is anticipated to be completed in 2027. This project is funded by Governor Little’s Leading Idaho initiative and will result in three lanes in each direction on I-15.

For more information and to sign up for email or text updates visit itdprojects.idaho.gov/pages/i15northgatetoblackfoot or call 208-252-5553.

The safety of motorists and construction crews is ITD’s top priority during construction. When driving through the work zone, please stay alert, follow work zone signage and drive the posted speed limit. Drivers are encouraged to plan extra time when traveling through the project area and check 511.idaho.gov or the 511 mobile app for the latest updates on restrictions and delays.

28 hours to reopen I-15 after catastrophic bridge strike

A police officer stands below a pilar hanging loose from the overpass.

At approximately 8:45 p.m. Thursday October 30, an empty milk tanker traveling on Interstate 15 near Blackfoot, Idaho went off the road and struck a pillar of the Riverton Road Overpass. The crash nearly obliterated the cab of the Kenworth semitruck with the engine tumbling yards down the median. The northernmost supporting pier nearest to the southbound lanes was violently bent, pushed several feet, and broken by the catastrophic impact. Yards of guardrail and ties were ripped up, broken and tossed about the scene. The pier cap bent downward and cracked over the central pier.

The driver of the semi-truck was life-flighted to Eastern Idaho Regional Medical Center in critical condition where his identity and status have not been shared officially. Idaho State Police, local law enforcement, and ITD employees from the Blackfoot shed moved quickly to close traffic on both the northbound and southbound lanes as well as the overpass.

Immediately following the crash Engineer Manager II Zak Johnson and Operations Engineer Greydon Wright were called to the site to inspect the damage. District Engineer Todd Hubbard also left for the site shortly after. Initial photos from the scene were sobering, and the decision was made to keep both the northbound and southbound lanes of the interstate closed. State Bridge Engineer Mike Johnson in Boise received cell phone photos and confirmed that the wisest course of action was to close the interstate until he could arrive on Friday morning to inspect the damage.

With the interstate closed between Exit 89 and Exit 93, traffic was diverted on to U.S. Highway 91 including through the city of Blackfoot. With an average daily traffic count of more than 30,000 vehicles, traffic quickly began to back up on I-15, along US-91, and in the city of Blackfoot. Adding to the confusion, the ramps at Exit 89 are not signalized, causing long delays for drivers trying to turn left. Traffic flowed better at Exit 93 due to special light timing plans enabled by electricians Landon Larsen and Kamron Hatch. Additional traffic began spill over to alternate local roads as drivers tried to find their way around the massive traffic jam.A badly damaged column hangs from the pier cap beneath a bridge. Rebar and shattered concrete are visible.

Word spread quickly throughout the community in large part due to photos shared late at night from operators out of the Blackfoot shed that showed the extent of the damage and helped the community to realize the importance of the closure of I-15. That post garnered nearly 500,000 impressions showing high interest in the community and across the state. Local media picked up the story from ITD’s Facebook page and ran the photos on their websites and on the morning news.

Friday morning, Hubbard requested cribbing material (wood posts) stored in the D4 yard to be sent to D5 to help with shoring up the bridge. A scissor lift was also ordered to be delivered from the Soda Springs shed to the crash site. Finally, a loader and an excavator were also brought in.

Johnson and Wright huddled down in Hubbard’s office to come up with a game plan. Soon young engineers were lurking at the doors of his office to listen in and learn. As Hubbard said later, “What an opportunity for these young engineers to learn, right? By watching closely what happens with this event they are better prepared for ten, fifteen, or twenty years down the road. When they see something similar unfold in the future, they’ll be able to say they had seen something like this before and know what steps to take.”

Meanwhile on I-15, morning commuter traffic north and south of Blackfoot began to back up again onto the freeways north and south of the city. City, county, state, and tribal law enforcement were stretched as they attempted to manage Halloween traffic.

District 5 alerted media that another update would be sent out in the afternoon after the bridge engineer had a chance to survey the damage. The first on-site interview with KIFI Channel 8 happened during their noon broadcast. At that time Hubbard, Wright, Zak Johnson, and Mike Johnson also arrived on-scene to fully inspect the damage. Cognizant of the teaching opportunity previously mentioned, a half dozen other engineers were also invited along.

Also on site were D5’s Paul Archibald and Darrell Hanners with a drone to take close-up photos of the damage for Mike Johnson to review. ISP also had a drone to 3D map the scene of the crash for their investigation.

The first concern to address was how likely it was for the bridge to have a catastrophic failure that would drop the deck on the interstate below. There was a possibility that if the central deck fell it could pull the eastern side of the roadway down with it, hence the full closure underneath the structure. With that later determined to be less of a concern, ITD had more options for how to restore traffic.

Key to restoring traffic on I-15 was the stabilization of the central and western portions of the bridge. A hasty meeting was held between the engineers, maintenance staff and local contractors Cannon Builders and Wadsworth Brothers. By 3 p.m. the group had finished their assessment and settled on the plan: stabilize the bridge by using concrete blocks, each 3,000 pounds with interlocking groves to keep them together, placed beside the piers.Two large columns of concrete blocks support the bridge on either side of the damaged pillar.

ITD issued another update to the media and to the public to share the news that by mid- morning Saturday drivers could expect one lane of traffic in each direction to flow on the northbound lanes.

Cannon Builders worked long into the night, and at 12:46 a.m. State Comm sent out an alert that traffic was being allowed onto I-15 again. Two crossovers near the bridge were utilized to shift the southbound traffic on to the northbound segment and off again. Just 28 hours after the entire closure of I-15, traffic was moving again.

Monday morning Cannon Builders and A-Core Concrete specialists began removing the broken pier and part of the pier cap. Some shoring was moved into the southbound passing lane so southbound traffic could be allowed back on the driving lane. Riverton Road will not carry any traffic until repairs are complete, which likely won’t be until the spring.

Community interest remains high and is almost entirely positive. Altogether, Facebook stats show that more than 1.5 million views of posts about the closure. Morning, noon, and evening newscasts carried the story throughout the weekend as did the local newspaper.

Hubbard expressed his thanks to all involved: “This was truly a team effort with multiple districts, multiple sheds, and multiple law enforcement agencies working night and day to keep Idaho’s traffic moving on I-15. I couldn’t be happier with our response.”

 

A pillar of concrete blocks supporting the overpass stands in the passing lane. Concrete barriers are setup on the center line and the right lane is open for traffic.

I-15 traffic shift at Riverton Road

right hand lane of I-15 is open with a concrete divider protecting temporary pier supporting bridge.

The Idaho Transportation Department has shifted lanes to offer travelers one southbound lane and two northbound lanes separated by a median on Interstate 15 between Blackfoot Exit 89 and Exit 93. Traffic had previously been crossed over to the northbound lanes with little separation between oncoming traffic following a collision last week that badly damaged the Riverton Road Bridge.

ITD engineers estimate that southbound I-15 will remain one lane underneath the bridge and that the bridge itself will remain closed until next spring.

Motorists are encouraged to use 511.idaho.gov for the latest traffic conditions.

Single lane opened to traffic on Porterville overpass

A damaged girder under a bridge

The Idaho Transportation Department has installed traffic signals allowing single-lane traffic to pass over the Porterville overpass north of Blackfoot. The overpass was damaged Tuesday evening when it was struck by a backhoe being hauled by a semi on Interstate 15. The collision caused severe damage to one of the concrete girders under the overpass.

ITD has determined it is safe to allow traffic to pass over the undamaged portion of the bridge. The traffic lights will alternate, allowing vehicles to use the single open lane.

In addition, concrete barriers will be put in place to ensure traffic does not pass over the damaged girder.

ITD continues to investigate what will be required to repair the bridge.

Motorists are encouraged to check 511.idaho.gov for the latest traffic information and width restrictions.

 

Historic System Interchange rebuild nearing successful completion

Aerial view of the system interchange at Pocatello.

With the painting of final lane markers on the new roadway, construction at the I-86/I-15 “Flying-Y” System Interchange in Pocatello is coming to a successful conclusion. Begun in July 2022, the three-year $112 million project has dramatically changed the drivability of the interchange.

“We spent over eight years from design to actual construction of the project. We’re pretty proud of it. It’s one of the bigger projects we’ve designed. It’s one of the largest projects ever designed entirely by ITD staff and inspected with ITD personnel. Most of the people on the team live here locally and this has been a really meaningful project for us to make sure we did our very best,” said Project Engineer Aaron Baird.

Critical areas that were improved include the northbound Pocatello Creek on-ramp, the northbound-to-westbound collector distributor, and the eastbound-to-northbound ramp. Each of those improvements made merging from one Interstate to the other smoother and safer for motorists.

“We’re excited for people to use the final product. We hope it’s something that will last a long time and keep the travelling public safe as they use it,” said Project Manager Greg Roberts.

The scale of the endeavor has been truly historic. Approximately 1 million cubic yards of excavation have been completed. In addition, about 490,000 tons of base material was brought in; 116,000 tons of asphalt were placed; and over 7,700 cubic yards of concrete were poured. Nearly 70,000 square feet of retaining walls were also built throughout the project area. Finally, ITD built eight new bridges. Four of those have precast concrete girders and four have steel girders. In all, over 5 million pounds of steel has been used in the new bridges.

Construction crews worked year-round and around the clock for approximately three years to complete the project. To minimize disruption to traffic, key demolition operations were conducted at night. These efforts minimized the impact on traffic while the interchange was being reconstructed.

In addition to the major changes inside the Flying-Y design, the Chubbuck Road overpass was reconstructed as an underpass to improve site distances and vertical clearance on I-15, and to improve access to the Wellness Center from Chubbuck. The new underpass is significantly wider and includes bike lanes and sidewalks.

ITD also worked closely with the Portneuf Greenway to construct a pedestrian and bicycle path on the east side of the worksite to connect the Greenway to the Wellness Center.

Work left to wrap up the project will be off the roadway and conducted on the shoulders. In addition, ITD will be seeding open ground with native grasses.

“Thank you for being patient with us and seeing our vision, seeing what we’re trying to do to positively impact this community,” said Project Manager Zak Johnson.

District Engineer Todd Hubbard echoed those sentiments, “This project has been a great success and is an important addition to the community for the safety of drivers. It has been a lot of work to get all of it completed and to keep traffic moving. I want to thank everyone for their patience as we have worked on this project over the last three years. And a thank you to the project team and Sundt-Cannon Joint Venture for a project well done.”

Drivers are encouraged to remain attentive, move over for workers and emergency vehicles, and follow posted speed limits.

Chip sealing to begin Wednesday at I-86 and I-15 System Interchange

Aerial photo of the system interchange at Pocatello.

Beginning tomorrow the Idaho Transportation Department will chip seal the System Interchange in Pocatello. Once this work is complete, the roadway will be restriped to indicate the final lane configurations.

Chip sealing covers temporary lane markings used throughout various phases of construction and maximizes the taxpayers’ investment by extending the lifespan of the pavement. A sticky slurry is sprayed on the pavement then rock chips are applied on top for a long-lasting seal. This treatment protects pavement from sun, oxidation, weather, water, oil and gas, and increases traction for safety.

Tabs will be placed on the new chip seal to indicate lanes for the short time before striping work can occur.

The previous connection between I-86 and I-15 was originally built in the 1960s. Now nearing completion, the System Interchange is a $112 million redesign to improve safety and replace aging infrastructure that began construction in 2022.

Motorists should carefully follow signs and slow down to posted speed limits while traveling through the construction area. With crews working day and night at the System Interchange, it is especially important that drivers be alert and travel safely.

Motorists are encouraged to use 511.idaho.gov or the 511 app to keep track of related detours. Project details are available on ITD’s website at itdprojects.idaho.gov/i-86i-15-system-interchange.

Seven-person crash in Southeast Idaho caused by impaired driver; officials urge DUI education

Flowers laying on the dirt beside a road

The Idaho State Police (ISP) and the Idaho Transportation Department (ITD) urge drivers to make safe, sober choices behind the wheel following confirmation that the at-fault driver in a recent fatal crash on U.S. Highway 20 near Henry’s Lake had a blood alcohol content of 0.20 — more than twice the legal limit of 0.08.

The May 1 crash on one of the main corridors to Yellowstone National Park, which claimed the lives of seven people, occurred just as Idaho entered the 100 Deadliest Days — the period between Memorial Day and Labor Day when traffic fatalities typically rise due to increased summer travel, holidays, and impaired driving. Law enforcement and transportation officials say this preventable tragedy underscores the consequences of impaired driving.

“This tragedy should be a wake-up call,” ISP Captain Chris Weadick said. “No one plans to cause a crash or take a life when they get behind the wheel, but choices have consequences. Impaired driving isn’t just illegal — it’s deadly. If you see someone unfit to drive, speak up. Lives depend on it.”

Alcohol-related crashes remain one of the leading causes of traffic deaths in Idaho.

“Idaho’s roads are especially busy during the summer,” ITD Operations Manager Bryan Young said. “With more construction, increased travel, and an influx of visitors, we’re seeing more families and more drivers on the road. It only takes one impaired driver to change lives forever. This is a preventable problem, and it starts with each of us making responsible choices.”

DUI Prevention Tips

  • Plan ahead: If you plan to drink, arrange for a designated driver, rideshare, taxi, or public transportation.
  • Always buckle up: Seatbelts save lives and reduce injuries, though they do not replace the need for safe driving.

This summer, ISP and ITD are partnering to strengthen DUI enforcement and expand public outreach. We ask everyone to help protect lives by staying sober behind the wheel. The public is encouraged to report suspected impaired driving by calling *ISP (*477) or 911 if they observe erratic or dangerous behavior on the road.

Crack sealing planned for Yellowstone Avenue in Pocatello

Photo of crack sealing operation on a highway.

The Idaho Transportation Department has begun crack sealing US-91 in Pocatello. Work began Monday on 5th Street and has continued onto 4th Street. Crack sealing north through Pocatello on Yellowstone Avenue will continue as weather permits.

“Once we reach Cedar Street, we will shift to nighttime work to minimize disruption to businesses,” said Pocatello Foreman Anthony Richards. “Other than where the pavement is concrete, we’re planning on continuing north all the way to Walmart.”

The sealant prevents water from entering the pavement causing further erosion and extending the lifespan of the road

Motorists should expect single lane closures in the work zone.

Drivers are encouraged to use the Idaho 511 system for traffic impact updates for this project, and all ITD projects statewide.

I-15 Inkom corridor construction and detour begins Monday

The Idaho Transportation Department and its construction partner Wadsworth Brothers Construction is beginning reconstruction of Interstate 15 at Inkom.

Work will replace I-15 bridges in three locations:

  • Over the Union Pacific Railroad (UPRR) tracks and Old Highway 91.
  • Over Rapid Creek Road (Main Street).
  • I-15 bridges and reconstructing the West Interchange.

ITD combined and streamlined the projects to reduce the construction timeline to approximately two years rather than doing one location at a time over three years. This approach minimizes disruption to the local community and the traveling public and efficiently uses construction funds.

Old Highway 91 will be closed under I-15 beginning Monday, weather and other factors permitting, to allow Idaho Power to relocate utilities. Local access will be allowed. Other drivers will be detoured along Rapid Creek Road (Main Street). The detour will remain in place until mid-June.

I-15 traffic will be reduced to one lane in each direction from early March until late October.

For project progress and to sign up for construction updates, go to the project webpage at itdprojects.idaho.gov/pages/i15-inkom-corridor. Motorists are encouraged to use 511.idaho.gov or the 511 app to keep track of project detours.

 

‘The Salt Seeing Eye:’ the snowplow driver’s crystal ball

A hand points out the screens inside the cab of a snowplow, one of which shows the truck bed holding salt.

If we each had a crystal ball, just think of all the time, money, pain or heartache we could save!

While not exactly a crystal ball, Idaho Transportation Department plow operator Skylerr Valentine, with help from the Idaho Falls shed crew, has come up with an innovation that’s a little bit close. Well, for ITD operations folks in terms of work that is.

Valentine pondered on the fact that while plowing, he would need to make multiple stops through his route to climb up the truck bed and see how much salt was left. This of course involved pulling over, getting out of the cab and physically climbing on the heavy equipment. On newer dump/ plow trucks, a small ladder is fitted to the side of the bed. On older ones that still operate in force across the state, this salt check involves navigating from the stairs of the cab across to one of the rims of the truck bed. Valentine actually once fell while doing just that.

He figured that surely a camera could be installed to show down into the sander box that holds augers and salt. This would allow salt levels to be monitored visually just like wing plows are. He happened to be aware of a truck in east Idaho that was on the surplus sale line and talked to ITD Fleet Manager Dalton Rice about using the outdated wing plow camera from it to test out this innovative idea.

With the help of the entire Idaho Falls crew and ITD electricians Josh Harris and Justin Romrell, that older camera was mounted to the truck bed and wired around, then into the cab, with concern for easy disconnect points to retain dump truck functionality. The smaller screen of the unit was mounted inside, just underneath the tablet typically used by plow operators. Valentine dubbed it the “Salt Seeing Eye.”

“It was a lot of work, figuring it all out just right,” he said. “We really tried to make sure it was waterproof and could stand up to the elements. I wanted to see it put to the test this winter.”

Tablets equipped inside plow trucks show drivers video of where their wing is at, and relay salt and brine output numbers right on the screen. They don’t, however, indicate when salt in the truck bed is gone. Those numbers keep on ticking, and the operator keeps on driving, thinking he’s covering the road when in fact, he’s sure not.

Multiple times Valentine, and surely other operators anywhere, would stop to check salt levels in the bed, only to see that it’s empty and have no idea how long it had been. Then begins backtracking to determine where to pick back up with salt application, essentially doing the same thing over again and wasting time.

“I would make a 70-mile round trip, having run out but no idea where,” Valentine said. “I had no idea how long ago it had been or how many miles really had nothing on the road.”

There are formulas and historical knowledge that can help operators determine just how far so much salt will cover.  Let it be said that ITD operations folks could certainly be given science and math degrees for the calculations they’ve mastered when it comes to doing the work they do. They rely on the output readings on the tablet in each truck also. Where those reading don’t stop even if the salt is empty, calibrations aren’t without a significant margin of error though.

“This could really help us find discrepancies in our calibrations,” Idaho Falls Operations Foreman Jared Loosli said. “It has the potential to save a lot of money when it comes to salt ordering.”

This winter, Valentine has indeed had the chance to put the new tool to the test. While plowing the five-lane section of US-20 west of Idaho Falls, he’s determined from the safety of the cab that he can in fact make one more pass on his route, where he normally would have stopped to check or headed back to the shed to refill.

The “Salt Seeing Eye” may not be the crystal ball that can help any one of us avoid bad personal life decisions, unfortunately. But with substantial time saved while snowplows are out doing the vital work they do, increased safety for operators that would no longer have to climb on heavy equipment in slick winter conditions, and visible cost savings through more accurate salt use calculations, this innovation certainly has the potential to greatly benefit operations across Idaho.

Ideally, this camera could come standard on all new ITD trucks and be paired with the typical tablet, becoming one of the options right on the screen operators use now.