Traffic will be detoured overnight next week for motorists heading eastbound on Interstate 84 from Burley toward Pocatello as crews work to place girders on the newly constructed bridge.
This is part of the Salt Lake Interchange replacement project, underway since May of last year. Construction is scheduled to finish by late 2020.
This temporary traffic pattern is expected to be in effect between the hours of 9 p.m. and 5 a.m. during the nights girders are placed. Work is anticipated to be completed within a week.
“Detouring traffic around this portion of the work zone ensures the safety of motorists who would otherwise be traveling underneath the bridge,” said ITD Project Manager Travis Hitchcock. “Crews will be working to place the girders at night in order to reduce traffic impacts during peak traveling hours.”
Drivers should still anticipate reduced speeds through the work zone and pay close attention to signage which will be in place to safely direct motorists through the area.
Wadsworth Brothers Construction, of Draper, Utah is the prime contractor on this project.
BOISE – Motorists can expect daytime lane restrictions, speed reductions and intermittent detours during construction this summer and fall.
The project includes repaving Idaho 55 between Pride Lane in Caldwell and Middleton Road in Nampa and improving the intersections at Farmway Road, Lake Avenue and Midway Road.
Each intersection will be widened to include five lanes on Idaho 55 and three lanes on local roads. ITD will install a new traffic signal at Farmway and Midway roads and replace the traffic signal at Lake Avenue.
“The best way to learn about traffic restrictions is to sign up for emails from ITD,” said ITD Construction Coordinator Merrill Sharp. “The work schedule may change based on factors such as weather and utility work. We will send regular updates about what motorists can expect each week.”
Map of construction zone for Idaho 55. Work begins Aug. 8.
During construction, lanes on ID-55 will be restricted during the day and the speed limit will be reduced. Traffic may be detoured around each intersection for several days.
The initial weeks of construction include widening the Farmway Road and Lake Avenue intersections and paving Idaho 55 between Pride Lane and Farmway Road.
“When complete, this project is expected to bring significant safety benefits for the 10,000 motorists who travel this stretch each day,” said Sharp. “While the road is under construction, however, we are asking motorists to plan ahead and expect delays.”
LEWISTON – Milling and paving on Idaho Highway 8 is expected to impact drivers and businesses during daytime hours for the next week and a half. Crews will block three of the lanes, leaving one lane open in each direction.
Intersections and driveways may be temporarily closed during the rehabilitation. The worst traffic impacts during milling are expected to occur today through Monday (Aug. 2-7).
Crews will begin milling off the top section of roadway surface around 5 a.m., with paving coming through around 10 a.m. in that same section. The work is expected to continue throughout the day and finish by that evening.
Work on this $3.55 million job, contracted to Poe Asphalt, of Clarkston, Washington, is expected to finish by late September.