ID-55 project between Smiths Ferry and Round Valley to start September 8

ID-55 at Smiths Ferry

The Idaho Transportation Department (ITD) starts road work on the Idaho Highway 55 safety-enhancement project between Smiths Ferry and Round Valley on September 8.

The public is invited to attend a virtual public meeting on Wednesday, September 2, from 6 p.m. – 7 p.m. where ITD representatives will give an overview of the project and take questions. The link to attend will be posted on the project website, itdprojects.org/ID55smithsferry, 15 minutes prior to the meeting.

Work will largely be done in fall, spring and summer months, with construction stopping during the winter. This fall, travelers can expect full closures on the roadway Monday through Thursday from 10 a.m. – 2 p.m. to allow for blasting and rock removal.

Motorists can find additional details on road closures and traffic patterns on the project website, and can sign up for email and text updates.

“Our goal with this project is to enhance the safety of this mile-long section of the roadway,” Project Manager Alex Deduck said. “Construction crews will remove about 146,000 tons of rock from the hillside, which we want to do very carefully to not create rockslides or impact the river.”

Crews will work on widening shoulders and straightening the curves of the road. This project will also provide a smoother, safer ride for motorists by adding guardrail.

Motorists should anticipate reduced speeds and lanes reduced to one-way alternating traffic during construction. Seasonal closures and traffic patterns will be as follows:

  • Fall (September – November): One-way alternating traffic controlled by a temporary signal; daytime and nighttime work, seven days a week; full road closures Monday – Thursday from 10 a.m. – 2 p.m.
  • Winter (December – Mid-March): No construction expected; all lanes open
  • Spring (Mid-March – Mid-May): One-way alternating traffic controlled by a temporary signal; daytime and nighttime work, seven days a week; full road closures Monday – Thursday from 10 a.m. – 2 p.m.
  • Summer (Mid-May – August): One-way alternating traffic controlled by flaggers; daytime and nighttime work, Monday – Friday

The project is expected to be completed by late fall 2022. ITD and the Idaho State Police advise motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-­1-­1 or visit 511.idaho.gov for information on the state highway or interstate system.

Memorial Day Travel Advisory for Treasure Valley residents

Traffic Congestion Generic

Memorial Day weekend is nearly upon us, and ITD is issuing the follow travel advisory to inform those planning to drive from the Boise area of conditions on and along the area highways.

Construction Impacts

Interstate 84

There are two projects active on I-84 to the east and west of the Boise area.

Bridge rehabilitation on the bridge over Purple Sage Road west of Caldwell has reduced the Interstate to a single lane in each direction. Speed limits are reduced and motorists should anticipate delays.

Pavement rehabilitation and construction of a third westbound lane are active east of Mountain Home. Motorists will be channeled into a single lane and speed limits are reduced.

U.S. 95

There are two construction projects that will have active impacts over the weekend. Both are bridge replacements that currently have only one travel lane. The first project is located approx. 10 miles north of Council. The second is the Little Rainbow Bridge, approx. 13 miles north of New Meadows. Both construction zones are controlled by temporary signals. Motorists should anticipate delays on this route.

Idaho Highway 55

One active project on ID-55 is the repavement of the highway south of Smiths Ferry. Work will be suspended starting Friday, May 24 and not resume until Tuesday, May 28. Motorists should use caution in the area and obey traffic signs. There will be uneven surfaces as the project remains partially constructed.

Another project on ID-55 in Canyon County is the bridge and road reconstruction in Marsing. Construction impacts will remain active over the weekend. Travel will be reduced to one lane in each direction. Motorists should expect delays in the area.

Travel Conditions

Prolonged rainfall and cooler temperatures mean the mountains are saturated. This increases the risk of rockfall and mudslides. Motorists should be aware of the possibility of hazards on the road and drive with caution. Remember to remove distractions and Drive Well, focusing on the important task of engaged driving.

Congestion is common on these mountain highways during summer holidays. In particular, the intersection of ID-55 and Banks-Lowman Road sees heavy traffic. To mitigate this increase, ITD will flag this intersection on Memorial Day, the Fourth of July, and Labor Day.

ITD is encouraging vehicles traveling from the Sun Valley region to the Boise area consider alternate routes or travel outside the busiest times (noon to early evening) to avoid delays at the intersection of ID-55 and Banks-Lowman Rd.

Be sure to check 511 before leaving to see the latest road conditions and impacts. You can call, visit the website, or download the app for Apple or Android devices.

Wet Paint: Striping crews hitting the Treasure Valley

Wet Paint Sign

The last pockets of snow are melting off the Boise Foothills – the annual sign that Spring is in full swing in the Treasure Valley. As you begin to de-clutter your garage and spruce up your yard, the Idaho Transportation Department’s Southwest Idaho office is out in force laying fresh paint on faded road stripes.

During these operations, ITD is asking motorists to use extra caution around the striping machines and the wet paint they are applying.

How the Process Works

Striping crews consist of four vehicles.

  • A lead vehicle to warn approaching vehicles of the wet paint ahead
  • A paint truck that applies the paint and reflective beads
  • A crash truck immediately behind the paint truck for protection and to warn motorists of the fresh paint on the road.
  • A trailing truck with a message board to warn motorists of the wet paint and the painting crew working ahead

When weather allows, striping crews will spend the Spring and Summer repainting all of the lane lines on the state highway system in southwest Idaho. The paint truck sprays two different materials almost simultaneously; the paint first and then retro-reflective beads. The combined materials help the lines remain visible under different conditions: daylight, nighttime, or rain.

Once applied, the paint cures quickly. In ideal conditions, it can be as soon as 30 seconds.

What to do if you drive on wet paint

Wet paint is considered a roadway hazard – similar to animals, debris, or potholes. It’s the responsibility of all drivers to look out for these hazards and try to avoid them.

If you do find yourself driving through wet paint and some of it splashes on your car, you can take immediate action to remove it. ITD suggests two options:

  • Test a small, hidden part of your car first to ensure no side-effects to the paint or finish. Spray the painted areas with Pam cooking oil. Let it sit for a few minutes. Spray off with pressure washer.
  • Use a chemical solvent, such as Goof Off (latex). Test a small, hidden part of your car first to ensure no side-effects to the paint or finish. Spray and wipe off small sections at a time. After you wipe off each section wash that section immediately.

 

I-84 resurfacing between Nampa and Caldwell begins

I-84 Repaving Map

BOISE – The Idaho Transportation Department will begin initial construction activities next week on a summer project to resurface deteriorated pavement on Interstate 84 between Nampa and Caldwell.

ITD will share details about construction activities and sequencing at a community open house Thursday, May 25 at the Hampton Inn at 5770 Franklin Road in Nampa. Community members are invited to come at their convenience from 11 a.m. to 1:30 p.m. or from 3 p.m. to 6:30 p.m.

ITD is using weekend and nighttime traffic control to minimize traffic impacts during the weekday commute.

During four weekends this summer, ITD will shift all I-84 traffic to one side of the interstate (eastbound or westbound) while crews work on the other side. On these four weekends, one lane of traffic will be open in both directions between Nampa and Caldwell from 7 p.m. Friday to 5 a.m. Monday. All lanes of I-84 will be open during the weekday.

Check out the project website here.

Final weekend dates will be scheduled based on factors such as traffic counts, weather predictions, equipment and materials availability, and the project schedule.

Community members may request email notification of the weekend dates by texting INTERSTATE84 to 22828. ITD will announce exact dates as soon as they are scheduled.

Other traffic impacts for the project will include occasional nighttime lane restrictions, shoulder closures and speed-limit reductions. The project includes resurfacing I-84, the Northside Boulevard interchange ramps and two ramps at the Franklin Boulevard Interchange. Guardrails will be improved throughout the project area.

Idaho Materials Construction is the contractor for this $9.5 million project.

Bridge replacements and pavement rehabilitation to begin on U.S. 95 near Parma in mid-April

Parma Bridge U.S. 95

Reconstruction of two bridges on U.S. 95 in Parma will begin in mid-April.

Work will occur at the junction of U.S. 95 and U.S. 20/26 and include the reconstruction of the Union Pacific Railroad overpass, Sand Hollow Creek Bridge and nearby pavement rehabilitation.

*The project is scheduled to be complete this winter.

*A posted detour will be in place during the project. A separate truck detour will also be posted. The speed limited will be reduced to 45 mph in the work zone. The speed limit will be reduced to 45 mph on U.S. 20/26 when shoulder or median work is occurring. Flaggers will assist motorists through the work zone during different phases of the project.

*Most work will occur Monday through Friday, and some Saturdays.

Motorists are encouraged to check 511.idaho.gov for construction updates and detour information. For a full list of construction projects scheduled to begin across southwest Idaho, please visit our website at itd.idaho.gov/d3 and click on the construction tab. Some updates will also appear on Twitter and Facebook.

With nearly 45 projects scheduled across the region this year, please plan ahead, slow down, and give yourself enough time when traveling through each work zone.