Nighttime lane restrictions begin soon for Broadway, Front and Myrtle (US-20) repaving

Myrtle Street

Nighttime lane restrictions will begin in tonight, Wednesday May 16 on Front Street, Myrtle Street and Broadway Avenue in Boise as the Idaho Transportation Department prepares to repave all three roadways.

The project will include milling off the worn asphalt and replacing it with new pavement. Construction is anticipated to begin on Myrtle Street, then move to Front Street, and on to Broadway Avenue in late June or July.

The repaving work is expected to be completed in late summer.

Work includes:
• Myrtle Street between I-184 (Connector) and Broadway Avenue
• Front Street between I-184 (Connector) and Broadway Avenue
• Broadway Avenue between Rossi Street and the New York Canal north of I-84

The majority of construction will occur from 8 p.m. to 6 a.m. All lanes will be open during the day. Occasional work will be scheduled on Friday and Saturday 10 p.m. to 7 a.m.

During nighttime paving operations, two lanes will be open on Front and Myrtle Streets. One lane will be open in each direction on Broadway Avenue.

“To get construction updates, sign up for emails or text messages from the ITD Office of Communication,” said ITD Southwest Idaho Resident Engineer Jayme Coonce. “Dates and plans can change quickly due to unpredictable weather and other factors. ITD will send regular updates to keep motorists, residents and businesses informed.”

To request email updates, text US2026 to 22828. Updates also will be posted to itd.idaho.gov/D3.

ITD estimates 30,000 vehicles travel on Myrtle, Front and Broadway each day. The U.S. 20 resurfacing project is expected to extend the pavement lifespan approximately 10-12 years.

Sunroc Corporation, of Boise, is the contractor for $3.14 million project.