Traffic to shift next week in US-95 work zone at Granite Hill

Aerial view of new pavement over Granite Hill

Traffic will shift early next week at the U.S. Highway 95 work zone at Granite Hill north of Athol. Drivers will be directed onto the newly paved lanes of the highway starting Tuesday, Sept. 13.

“We are very close to being done,” ITD Project Manager Steven Bakker said. “We plan to stop impacting traffic by mid-October.”

Traffic has been running on Mineral Ridge, the new frontage road to the east, since August 2021. The new frontage road to the west, called Vintage Road, will fully open north of Homestead Road roughly one week after the main traffic shift.

Drivers should still plan to slow down in the area as work will continue near the Trails End Road intersection; crews will also install signage, finish landscaping and add rumble strips before the project is complete.

This $21 million project began in fall 2020 and is expected to finish by November, one year ahead of schedule.

 

Nighttime repairs start again on US-95 Spokane River Bridge

US-95 where it crosses the Spokane River

Work has now been rescheduled to the following week. For the exact start date, drivers should refer to message signs placed on the highway closer to construction or 511.

Nighttime repairs will start again on the U.S. Highway 95 bridge over the Spokane River, with work beginning on Wednesday, Sept. 14. Drivers heading downtown after 7 p.m. over the next two months should plan for congestion.

Last summer crews sealed the driving surface and began work on the railing. This fall crews will replace the railing as well expansion joints that allow the structure to expand and contract with the weather.

“Generally drivers should only have to contend with the shoulders being closed, but there will be a few weeks when the contractor is working on the joints that we’ll also close a lane,” ITD Project Manager Cole Mosman said.

Construction this year will be followed by a larger project in 2023 that will repair the concrete piers and paint the underside of the bridge.

Find live traffic impacts at 511.idaho.gov.

Changes to I-90 work zone between Wallace and Mullan coming next week

View from an overpass of milling on I-90

Next week conditions will change in the I-90 work zone where the freeway is being repaved between Wallace and Mullan, with funding for the project provided by “Leading Idaho.” All traffic will shift from the eastbound lanes to the westbound lanes by the end of the week.

“This roughly marks the halfway point of the project,” ITD Project Manager Cole Mosman said. “We’re keeping traffic to one lane in each direction and moving it to other side of the freeway so we can get to the remaining work.”

Eastbound ramps that were closed with the first phase of paving will now be open, but drivers heading westbound will only be able to get on or off at Exit 62 in Wallace or Exit 69 in Mullan.

“We want to remind drivers to stay engaged, especially through work zones,” Mosman said. “All season long we have seen drivers become impatient and try to pass. Passing isn’t allowed in the work zone and trying to do so can have terrible consequences.”

Construction began in mid-July to repave this 5-mile section. This next phase of work also includes the building of an 85-foot-long wall and fencing at milepost 67 to protect drivers from potential rockfall.

These improvements were added to the project after boulders fell down a steep chute onto the freeway during two separate events in June and November of 2020.

The project was originally scheduled to be constructed in 2024 but was advanced to this summer with funds from Governor Brad Little’s “Leading Idaho” investment, which includes a one-time transfer from the state’s budget surplus of $126 million dedicated in 2021 by the Idaho Legislature.

Work will wrap up in late October.

Other work zones on I-90 include paving near the bottom of Fourth of July Pass, bridge replacements in Kellogg and a range of smaller projects to address bridges, concrete barrier and ramps. Drivers should plan extra time for commuting and check 511.idaho.gov for traffic conditions and restrictions on up to seven planned work zones east of CDA this summer.

Transport of oversized windmill loads through North Idaho to begin next week

Image on oversized windmill load.

More than 80 oversized loads will depart the Port of Lewiston bound for Canada over the next 2.5 months, with the first load scheduled to leave next week. Richards Transportation is in the process of delivering windmill blades to Jenner, Alberta, with the largest loads measuring up to 325 feet long and weighing 137,000 pounds.

“This first load is the only one currently scheduled and will provide an opportunity to refine the transportation plans,” Operations Engineer Jared Hopkins said. “After the initial run, we expect operations to increase in frequency.”

Nine loads will depart each week in groups of three from the Port of Lewiston to travel north on U.S. Highway 95 to Coeur d’Alene before heading east on Interstate 90 into Montana. Three loads are expected to leave every other day, with each individual load departing roughly 30 minutes apart.

Click here to see an oversized windmill load.

Pilot cars will escort each load on the one-night journey, with flaggers in place to close the following intersections:

  • State Highway 128 and US-12/US-95 in Lewiston
    • US-95 and Lincoln Avenue/Walnut Way in Coeur d’Alene
    • the I-90 and US-95 interchange in Coeur d’Alene.

Drivers can expect delays as the loads move through these intersections at night. The transportation company arranged for a new on-ramp to help oversized loads make the turn from northbound US-95 onto eastbound I-90 in Coeur d’Alene. This ramp will not be open for other traffic. Traffic on the interstate will be slowed down by pilot cars to allow each load to merge.

Given the length of the loads, navigating to and through Moscow will be especially slow-going and will require significant closures.

The two-lane section of US-95 between Thorn Creek and Moscow will be closed as loads travel through for an estimated 30 minutes each. Timing of the closures will vary but could start around 9 p.m. Traffic will be allowed to pass before each subsequent closure.

“That section of US-95 is windy and narrow, and the loads will not be able to make those turns without taking up part of the oncoming lane, so we are shutting it down,” Hopkins said.

Each night loads depart the port, no parking will be allowed in Moscow starting at 6 p.m. on the following streets:

  • Washington Street north of the US-95/SH-8 intersection to where southbound and northbound US-95 reconnects at the north end of Moscow.
    • Near the Main Street and A Street intersection.

While loads move through Moscow on US-95/Washington Street, traffic will be unable to pass. It could take up to an hour for each load to pass through.

“Given the extreme length of these loads and how narrow the highway section is in Moscow, the transport company will move each load at walking pace with staff on the ground to ensure that nothing next to the road is damaged,” Hopkins said.

Weather may impact the schedule. Traffic impacts will be identified on 511.idaho.gov.

Project starts next week to reduce likelihood of rockfall on US-2 and SH-200

Rocky cliff face above US-2

Over the next two months specialized crews will target five locations for rockfall mitigation on two highways near Sandpoint, including U.S. Highway 2 to the west and State Highway 200 to the east.

“At each location, crews will scale the slope, which involves wedging and prying loose rock that has the potential to fall onto the highway,” Project Manager Josh Nisson said. “This project is meant to be proactive, reducing the risk of drivers encountering rocks on the road and bringing it down safely on our own terms.”

The locations to be addressed include:

  • SH-200 at milepost 41 near Trestle Creek (two sites)
  • SH-200 at milepost 53 west of Clark Fork
  • US-2 at milepost 11 between Priest River and Laclede (two sites)

“While they are actively scaling and rocks are falling down towards the highway, we will not let drivers travel underneath,” Nisson said. “They’ll do that for about twenty minutes, let waiting traffic pass through, and then temporarily close the highway again.”

Crews will spend less than two weeks at each location. Drivers should plan for these delays while workers are on site, typically Monday through Friday from 7 a.m. to 5 p.m. Otherwise, all lanes will be open.

Signage at each location will be in place roughly one week before work starts, and drivers are encouraged to check 511.idaho.gov for all impacts before they travel.

First widening project begins on SH-53 near Hauser

SH-53 looking WB from Hauser

The first of several projects to add a center left turn lane to most of State Highway 53 from the Washington state line to Rathdrum begins next week.

“SH-53 serves more than 12,000 vehicles a day, including many drivers who commute between Washington and Idaho,” Project Manager Megan Koski said.

Work over the next two years will focus on a two-mile stretch starting near McGuire Road and continuing through Bruss Road, with additional safety improvements included at the Hauser Laker Road intersection. Two lanes will remain open through construction, but starting Monday, Aug. 22, speed limits will be reduced.

“The goal of this project and future ones is to make the highway safer by providing turn lanes for drivers,” Koski said. “Drivers won’t have to be worried about being rear-ended as they wait to turn left off the highway.”

Right turn lanes and lighting will be installed at the intersections of McGuire Road, North Church Road, Bruss Road and Hauser Lake Road. An acceleration lane at Cloverleaf Road will help drivers get up to speed and merge with eastbound traffic.

“This year, crews will add temporary pavement to the south so that we can maintain traffic as we build the base for the expanded road on the north side of the highway,” Koski said. “Then next spring we’ll pave over that base and open the new lane to traffic.”

Other similar projects are scheduled near Rathdrum in 2023 and state line in 2027. A maintenance project in late September will resurface patches within the first two miles near the state line at night to keep it in acceptable conditions until the 2027 project.

Since this project overlaps with future plans to build an interchange at Pleasant View Road in 2028, minimal improvements will be constructed near the intersections of Pleasant View Road and Hauser Lake Road at this time.

The department plans to fund a project at the next opportunity to build similar improvements to the four miles between Bruss Road and Latah Street.

Drivers are encouraged to check live traffic conditions at 511.idaho.gov.

Construction begins Sunday night on US-95 near Sagle

US-95_Lakeshore Drive_PH 2 after striping_spring 2022

The Idaho Transportation Department is beginning the second phase of construction on U.S. Highway 95 between Sagle Road and Lakeshore Drive to increase safety for drivers on the highway and reduce delays for drivers turning onto it. Impacts to traffic will begin during the evening hours of Sunday, August 14.

For approximately two weeks, crews will work at night to repave US-95 from Pit Road in Sagle to the Long Bridge. Motorists can expect the following impacts:

  • Flaggers will control one lane of alternating traffic on US-95 Sunday through Thursday from 7 p.m. to 5 a.m.
  • Nighttime lane closures will intermittently affect the Long Bridge
  • Speed limits lowered to 45 mph
  • Up to 15-minute delays
  • For live traffic impacts, check 511.idaho.gov

“The highway needs to be resurfaced this fall to avoid severe potholes in the winter,” ITD Project Manager Phil Stout said.

Work during this phase also includes building a U-turn for drivers and installing a signal at Sagle Road.

After the Labor Day weekend, crews will begin building a U-turn as an option for drivers to use when trying to head northbound on US-95 from Lakeshore Drive. The U-turn will be constructed northeast of Bottle Bay Road. Work will take place during the day, and one lane will remain open in each direction.

“Due to long lead times on some key materials, parts of the project will likely not be finished until the spring, including opening up the U-turn for traffic,” Stout said.

Sagle Road improvements are planned to start in mid-October. Drivers on US-95 will not be able to turn east onto Sagle Road, and westbound drivers on Sagle Road will not be able access the highway. Instead, they will be temporarily detoured to Monarch Road for up to one month.

“Our goal is to have the detour in place only as long as necessary, so we have put an incentive in the contract to encourage that work to be completed early,” Stout said.

Work this year will realign the intersection, add turning lanes and prepare for signal installation next spring.

Improvements and anticipated impacts during construction were presented at an open house held in April.

Visit the website at itdprojects.org/us95lakeshoredrive to sign up for construction updates and for more information.

Limited services available at the I-90 Huetter Rest Area until further notice

Drone shot of both exits for the Huetter Rest Area between Post Falls and CDA

September 6, 2022 update

Rest area reopened today

Today services at the Huetter Rest Area were restored through a temporary cleaning contract. The department will continue to pursue a long-term cleaning contract. The status of rest areas can always be checked at 511.idaho.gov.

August 2, 2022 update

Limited services available at the I-90 Huetter Rest Area until further notice

Limited services will be available until further notice at the Huetter Rest Area on I-90 between Post Falls and Coeur d’Alene.

At the eastbound rest area commercial vehicles may stop at the Port of Entry and travelers with watercraft like kayaks and boats must stop for inspection by the Idaho State Department of Agriculture to prevent the spread of aquatic invasive species.

No services are available at the westbound rest area.

“Back in late June, we had to terminate our contract with the cleaning company,” Operations Engineer Ryan Hawkins said. “The restroom and grounds were not being maintained per the standards of the contract and were posing a health risk.”

The Idaho Transportation Department has hired another contractor to perform a deep clean of the facilities and will solicit a new contractor for continued, ongoing maintenance.

“In the past, we have not had many companies interested in providing this service, so we are not sure when we will be able to fully restore operations,” Hawkins said. “In the meantime, we encourage travelers to stop in Post Falls or Coeur d’Alene.”

Rest area closures and traffic impacts across the state may be found by visiting 511.idaho.gov.

Construction begins next week on the I-90/SH-41 interchange

Aerial photo of the I-90 ID-41 interchange in 2020

POST FALLS – The Idaho Transportation Department (ITD) is beginning work to replace and upgrade the interchange at Interstate 90 and State Highway 41 in Post Falls, with impacts to traffic beginning MondayAugust 1.

Construction will be underway until the summer of 2025. Over the next four seasons work will generally shift from I-90 to SH-41 and then to Seltice Way. To learn about the full range of improvements and how to use the future interchange, watch this video.

“The beginning of this project is a significant milestone for ITD and the surrounding area,” said Shannon Stein, ITD project manager. “Once finished, the reconstructed interchange will improve safety, increase capacity, provide better connectivity to SH-41 and position I-90 for future expansion.”

In 2022, crews will work along I-90, begin reconstructing ramps and begin building the new eastbound bridges. Motorists can expect the following impacts:

  • Two 12-foot lanes of I-90 will be open during the day. Shoulders will be reduced to 2 feet.
  • Speed limits will be lowered to 55 mph on I-90 and 25 mph on SH-41 and Seltice Way.
  • Intermittent lane restrictions will occur on I-90 at night (8 p.m. to 5 a.m.). During special events, night work will begin at 10 p.m. Initial efforts include primarily night work.
  • Live traffic impacts will be available for individuals to check at 511.idaho.gov.

Construction may be noisy at times and require nighttime lighting or additional closures or delays on roads in the project area.

“It will be important to plan extra time when traveling around the interchange. ITD will communicate regularly throughout construction with those who live, work and commute in this area,” Stein said.

The best way to stay informed is to sign up for email updates by visiting itdprojects.org/i90sh41ic or by calling 866-774-4454.

The $78 million interchange reconstruction is beginning one year earlier than expected, thanks in part to Transportation Expansion and Congestion Mitigation (TECM) funds through Governor Little’s “Leading Idaho” initiative. This deliberate investment of TECM funds allows ITD to accelerate project timelines to address rapid growth and construct critical infrastructure sooner in Post Falls.

Garwood Bridge over US-95 to open to traffic by end of July

View from the ground of workers preparing to open the overpass for US-95 at Garwood Road to traffic

Construction of the new Garwood Bridge is nearing completion, with a tentative date for the bridge to open to traffic next Friday, July 29. The overpass allows for seamless north-south travel on US-95 and a safer crossing over the railroad. Completion of the bridge represents the conclusion of a multi-year project that began in summer of 2019 to improve the safety and efficiency of the US-95 corridor.

The project began with construction of a new single-point urban interchange at the junction of US-95 and ID-53. The interchange increased efficiency and safety of traffic flow by directing traffic through a single centralized signal. This interchange opened in November 2020 and is the first of its kind in North Idaho.

As a result of the two new structures, the project was able to remove two at-grade signals along US-95, so the last signal heading north from Coeur d’Alene is now at Lancaster Road.

A temporary signal that was installed at the intersection of ID-53 and Ramsey Road to accommodate detour traffic and will be replaced by a permanent signal through a separate project next year.

ITD would like to thank drivers for their patience during construction and reminds everyone to check https://511.idaho.gov for traffic impacts from other ongoing projects before traveling.