Construction will begin on Idaho 55 next week (July 16) near McCall

Idaho 55 Zachary to Goose Creek Map

The Idaho Transportation Department will begin a project next week (July 16) to resurface Idaho Highway 55 between New Meadows and McCall and construct a new retaining wall east of Brundage. The project will improve driving conditions and safety on this heavily traveled route.

From July to late August, crews will work between Zachary Road in McCall and Goose Lake Road near Brundage. View the postcard for details.

In order to keep traffic moving during the busy summer season, crews will work from 12 a.m. Monday to 12 p.m. Friday. All lanes will be open on weekends.

During the week, ID-55 will be reduced to one lane both day and night with a pilot car directing traffic. The speed limit will be reduced and 12-foot width restrictions will be in place.

“This will be a tight construction zone and we are asking for drivers’ patience during the work week. Please slow down in the work zone and pay close attention to signage, as crews will be working close to traffic,” said ITD Project Manager Jim Hoffecker.

Construction will move to the area between Goose Lake Road and Goose Creek Grade in late August. The project is expected to be completed this fall.