Work ongoing to extend passing lane on US-95 near Winchester

US-95 climbs through a green Culdesac Canyon.

Update from April 4: Although most complete closures of US-95 will be scheduled at night, during the second week of April, traffic will be stopped in both directions to allow the construction of an equipment access trail above the rock slope. Rock and other debris will be pushed off the slope into a catchment area for cleanup. Drivers should expect delays of at least 15 minutes; if rock falls onto the road, delays could become longer as crews remove it.

Speeds are now reduced on US-95 near Winchester as contractors replace signage and guardrail in advance of construction to extend the passing lane by three miles in the canyon.

For the next month, drivers can expect continued work on the shoulders as well as the creation of a trail for equipment to access the rock slope west of the highway. One lane in each direction will typically be open during the day, with work over the weekends possible throughout the season.

Once that work is completed around late April or early May, crews will start rock removal.

Rock removal will require some evening blasting and periodic closures of US-95. Closures will be scheduled around 6 p.m. and are expected to last approximately one hour, after which one lane of the highway may remain closed for cleanup.

“Closures will not be scheduled over the holidays and will generally be timed to avoid peak travel,” resident engineer Curtis Arnzen said. “Rock removal will be necessary for the duration of this project, and we strongly encourage drivers to plan around these closures if possible as there will be no detour in place.”

Closures will be advertised via digital message signs on the highway, 511 and updates on the project website.

Work this season is expected to end by November, with the entire project scheduled for completion in fall 2020. Construction in 2016 extended the passing lane in the area 1.5 miles, and future work will finish the passing lane between Winchester and Culdesac.

Nez Perce Tribe and ITD share new website for the Aht’Wy Plaza interchange

A semi passes the east entrance to Aht'Wy Plaza on US-12 near Lewiston.

Those interested in safety improvements at Aht’Wy Plaza on US-12 in Lewiston may now get their questions answered by visiting itdprojects.org/ahtwyinterchange.

The Nez Perce Tribe and ITD published a joint website that offers visitors the opportunity to view the final report from the road safety audit, understand how the plaza developed and subscribe for updates.

Email updates will be sent to all subscribers and posted to the website after team meetings about the planned interchange’s design, which is scheduled for completion in winter 2019/2020.

“The intent of the website is to provide updates on safety efforts as well as the design progress that is being made for the interchange at Aht’Wy Plaza,” said ITD engineering manager Doral Hoff. “It will be the best point of information on the interchange and any other improvements in the meantime.”

Work on US-12 improvements in Lewiston begins in March; open house Feb. 28

Vehicles move through the US-12 and 21st Street intersection, which is set for reconstruction in 2019.

The Idaho Transportation Department invites the public to attend an open house on Feb. 28 about upcoming improvements to the US-12 and 21st Street intersection.

The open house will be held from 4 to 7 p.m. at the Red Lion Hotel in Lewiston (621 21st St.). Attendees will have an opportunity to view construction phasing and detours for work that is scheduled to begin in March and last through October.

Construction will improve safety and traffic flow at the busiest intersection in Central Idaho by creating a more standard intersection. View the full list of changes.

The intersection will remain closed for the season, with the following detours in place:

  • East of the intersection, drivers may use 24th Street to go south on 21st Street or 26th Street to go north on 21st Street to and from East Main Street. During construction, both streets will be converted to one-way streets.
  • West of the intersection, drivers may use 18th Street and Idaho Street to head north and south on 21st Street to US-12.

Through traffic on US-12 will not be detoured but will be reduced to one lane in each direction. A temporary signal will be installed at East Main Street and the highway to allow drivers to directly travel east on US-12 or Main Street.

Crews will typically be on site throughout the week during the day, but work is allowed on weekends. Visitors to Locomotive Park can expect short closures during the first phase of construction as city stormwater improvements are installed.

Interested members of the public may sign up for an e-newsletter by visiting the project website.

Recommendations to improve safety near Aht’Wy Plaza on U.S. 12/U.S. 95 delivered after conclusion of road safety audit

Traffic approaches on U.S. 12/95 near the Clearwater River Casino and Lodge in Lewiston.

An independent team assembled by the Idaho Transportation Department to conduct a road safety audit on U.S. 12/U.S. 95 in front of Aht’Wy Plaza delivered recommendations yesterday.

The team developed recommendations to address highway safety concerns near entrances to the Clearwater River Casino and Lodge after the deaths of two drivers within approximately three months. Team members came from Nez Perce Tribal Transportation Department, Nez Perce County Road and Bridge, the Local Highway Technical Assistance Council, the Federal Highway Administration, ITD and ITD’s Office of Highway Safety.

They recommended an interchange, which is already planned for the east entrance, as the long-term solution to provide safe access from the plaza to the highway. The following phased options could be pursued by the Nez Perce Tribe with ITD before its construction.

  • Short-term options: All incoming traffic would enter at the west approach, and all exiting traffic would leave at the east approach.
  • Later options: Three possible options were presented and could be implemented individually or jointly.
    • Add an acceleration lane for eastbound traffic at the east entrance.
    • Widen the westbound right turn lane at the east entrance to create separation between turning and thru traffic.
    • Create ThrU-turns for both intersections. All left turns into and out of the plaza would be accomplished by first turning right and then making a U-turn to reach a destination.

Lowering the speed limit was considered but not recommended.

As part of the audit, the team evaluated road conditions and driver behavior. Factors not considered in the audit include construction costs, environmental impacts and right of way impacts.

A final report will be issued in three to four weeks. ITD will start assessing the viability of all recommendations with the tribe in the meantime.

ITD joins officers on US-12 patrol near Aht’wy Plaza

Cop car sits at entrance to Clearwater River Casino and Lodge in Lewiston.

Highway safety partners came together on December 28 to raise drivers’ awareness near the Clearwater River Casino and Lodge on US-12 in Lewiston.

Officers from several local agencies participated in a special patrol near the entrances and allowed ITD traffic engineer Jared Hopkins to ride along.

For four hours, officers looked for traffic infractions and handed out a letter—instead of a ticket—to encourage drivers to discuss safety at home. Nearly forty drivers received a letter.

The letter read:

Dear Driver:

Today you’ll see extra officers from local law enforcement agencies in the area.

We’re working together for the safety of yourself and other drivers on this stretch of US-12/US-95 in front of Aht’wy Plaza (Clearwater River Casino and Lodge). We’ve lost too many from our community at this location recently, and we hope the sight of so many police cars reminds you to stay alert, whether you are exiting the casino or driving past it.

Several of these agencies will also be participating in a road safety audit next month to look at data regarding speed limits, crashes and driver behavior. The goal is to identify strategies to improve safety immediately in the area while design continues for a full interchange. The interchange’s design will be completed next winter, with construction following once funding is secured.

Our efforts today are to raise awareness, rather than write tickets. Follow our efforts on Twitter with #US12casino #live #patrolpartners and stay safe.

From Nez Perce Tribal Police, Nez Perce County Sheriff’s Office, Idaho State Police and Idaho Transportation Department

The joint patrol allowed law enforcement and ITD staff to watch the intersections together and share their thoughts.

“The patrol gave me the opportunity to observe, and I saw several vehicles failing to stop at the west exit and only one speeding,” Hopkins said. “I was also able to clarify how speed limits are set, so that the officers enforcing them knew why the limit is and remains 65 mph.”

Fresh perspectives will benefit the road safety audit, which is scheduled later this month.

View coverage of the event by typing in the hashtags or @IdahoITD on Twitter. For more information on commonly proposed ideas to improve safety in the area, visit the news tab at itd.idaho.gov/d2.

Commonly proposed ideas to improve safety near the casino on US-12

Crashes near Aht’wy Plaza have become too frequent of a sight for those who drive past them or see them on the news. Too many of them have ended with a loss to our community.

While it is not a new area of concern for drivers on US-12 near the Clearwater River Casino and Lodge, many have been motivated by two recent deaths to offer their own solutions.

Several have been considered by the Idaho Transportation Department as the area developed, but these inquiries provide an opportunity to clarify why certain actions have or have not been taken.

LOWERING THE SPEED LIMIT

Although this seems to be the easy answer, lowering the speed limit may not be the best solution.

Speed limits are generally determined by how fast drivers comfortably and naturally move in the area, usually set at a pace described as what is “safe and reasonable.” They are safest when the majority of drivers are traveling the same speed, which is why ITD conducts speed studies to determine the speed at which 85 percent of drivers are traveling at or below before establishing a limit.

Speed studies are typically prompted by changes to the area, including new businesses opening and fluctuations in traffic patterns, as well as requests to adjust any speed zones. Five studies have been conducted near the casino since its opening by both the Nez Perce Tribe and by ITD, with the earliest study occurring in 1997 and the most recent in October 2018. ITD has also met with the Idaho State Police multiple times to analyze crash data.

To date, these discussions and drivers’ speeds have not supported changing the limit, and without either a serious commitment of law enforcement resources or a serious change in roadway conditions, reducing the speed limit would not be effective in improving safety or slowing traffic to or from the area.

While vehicles moving at lower speeds would impact each other with less force, that would only be the case if all drivers were moving at that lower speed limit. But if one driver was following the lower, posted speed limit and another was moving at the natural pace allowed by the road, additional conflicts could arise.

The greatest concern is that some drivers would obey the slower posted speed limit and others would not. As these drivers encountered slower vehicles, they would likely make more abrupt and unpredictable movements (like last-minute lane changes), which could increase the crash rate.

Most crashes at the entrances have been related to exiting drivers failing to yield to oncoming traffic when turning left. Variation in vehicle speeds through the area would likely make that left turn tougher—with some vehicles approaching at lower speeds and others at higher speeds, it would be difficult to judge a safe gap in traffic.

ITD has repeatedly investigated the safety and appropriateness of the posted limit, with each study supporting the current limit to prevent a possible increase in crashes.

INSTALLING A SIGNAL

If most crashes are related to drivers experiencing difficulty turning left, then it is reasonable that a signal could improve safety.

Just as speed limits are set a certain way based on data collection and analysis, signals are normally installed at specific locations once shown to be warranted.

Signal warrants are based on a variety of engineering factors, including how many vehicles make which turning movements. Although an engineer’s judgment can influence the final decision, these warrants are the primary basis for signal installation to ensure that traffic continues to flow smoothly.

Signals should only be installed when warranted as they typically increase certain kinds of crashes, including rear-end collisions.

Data collected from the entrances in 2012 did not support installing a signal or merit interrupting the flow of traffic on the highway.

IF NOTHING ELSE, CLOSING ACCESS

ITD uses access agreements all over the state to ensure that new or changing developments near highways do not create safety or mobility issues for drivers.

In the case of the casino, access to US-12 was initially provided by a county road which already had an agreement in place. When the county transferred the road to the casino in 2000, it altered its use, prompting a fresh access agreement.

A traffic impact study performed near the time of the development of the access agreement proposed an interchange as the ultimate solution, especially given expansion plans for the facility. It also outlined smaller improvements that could be implemented in the meantime to keep up with the growth of the facility and traffic to it while design continued on the interchange.

The tribe agreed to these terms, giving ITD the authority to restrict access if the commitments were not met. In the intervening years, some phased improvements—such as lighting, turn bays and acceleration lanes—have been constructed, but the final commitment remains unfulfilled.

Rather than close access and hinder productive relationships, ITD chose to work as a partner to the tribe. The department has remained involved in the design process, providing input on the development of the interchange to guarantee it will meet standards when incorporated into the public transportation system. ITD has listened to the tribe’s concerns, granted extensions when necessary and helped aid environmental discussions needed to complete the proposed interchange.

THE LONG-TERM SOLUTION

Although development of the interchange has been delayed for a few years as the tribe encountered environmental issues common to this type of project, they have funded other improvements proposed by ITD in the meantime, including the construction of a concrete island and the placement of additional signage in the area in the last year.

In January, a team of diverse professionals will meet to examine the data—all refreshed in the last month—as well as driver behavior to identify any and all solutions.

The best solution remains—and has always been—an interchange, but the road safety audit aims to determine effective steps that can be implemented immediately. ITD will work with the tribe to carry out any viable solutions the team recommends.

The interchange’s design is set for completion next winter, with construction following the tribe’s procurement of funds.

Construction of the interchange will reduce the possibility and frequency of crashes. Engineering and enforcement can help improve safety, but only engaged drivers can truly ensure safety while accessing and using the highway.

ITD to conduct road safety audit near Aht’wy Plaza in Lewiston

The Idaho Transportation Department is forming a team to conduct a road safety audit near Aht’wy Plaza.

Road safety audits can help identify creative solutions to safety concerns by asking a diverse group of professionals to examine a particular stretch of road. This safety audit will focus on the section of US-12 near the entrances to the Clearwater River Casino and Lodge.

The team will meet in January to evaluate road and environmental conditions as well as driver behavior. They will use that data to provide recommendations for safety enhancements.

“The goal of the team is to come up with solutions that can be implemented immediately while we continue to work with the tribe to develop a long-term fix,” ITD Traffic Engineer Jared Hopkins said. “This process will be a continuation of our partnership with the Nez Perce Tribe and Idaho State Police to improve safety at this location.”

This year ITD and the tribe worked together on multiple safety improvements near the casino. These projects include the installation of a concrete island at the west entrance to prevent exiting drivers from turning left, and last week new signs were installed to alert exiting drivers of oncoming traffic.

The department will continue to work with the tribe to evaluate and implement solutions developed from the road safety audit while the tribe continues design work for a full interchange at the east entrance.

The interchange design is scheduled for completion next winter.

Appellate court rules in favor of US-95 expansion south of Moscow

The picture above shows four lanes of US-95 between Thorncreek Road and Genesee. 

The U.S. Court of Appeals for the Ninth Circuit ruled in favor of the Idaho Transportation Department and the Federal Highway Administration on December 7 during the latest appeal about US-95 expansion south of Moscow.

Per the decision, ITD will finish right-of-way acquisition and submit a permit application regarding wetland mitigation to the U.S. Army Corps of Engineers. After those two steps, the project can be put out to bid for construction.

Work could begin as early as late summer 2019. Project details can be found online at us95thorncreek.com.

In January 2018, the Paradise Ridge Defense Coalition appealed an August 2017 ruling from the U.S. District Court for Idaho that found the two agencies appropriately followed the environmental process during the development of the project between Thorncreek Road and Moscow.

 

US-12 transformed through ITD’s efforts this summer

As early as February, ITD engineers were reaching out to the public to discuss a major undertaking for US-12 this season: two bridge replacements and 50 miles of paving.

That’s no small amount of work for the highway that follows the Lochsa River through abundant U.S. Forest Service lands and provides access to popular fishing spots and hot springs; it also gives the trucking community a scenic shortcut into Montana as it winds its way up to Lolo Pass.

Used by locals and tourists alike, this two-lane highway would see significant work and miles of orange barrels for the first time since 2000. ITD cautioned all drivers that working on so much in the remote location could lead to delays upwards of two hours.

“There are not many places to pass in the corridor, and with all of the summer traffic it normally sees, we definitely wanted to overstate delays rather than understate them,” project manager Janet Zarate said. “Thankfully, we were able to keep delays at 60 minutes or less all summer.”

ITD specifications limit delays through projects to 30 minutes, but the contractors working in the corridor phased the work to improve their efficiency and further minimize delays. Hotspots installed specifically for the projects provided connectivity that enabled project staff to promptly address any issues with delays.

Creative thinking also led to a partnership with Three Rivers Rafting out of Lowell, which ITD hired to shuttle bicyclists through the work zones.

“This partnership makes sense because at that time of year, the river doesn’t run as high, and there are fewer rafters,” resident engineer Joe Schacher said. “During their season, these companies routinely shuttle their customers up and down the river, and we didn’t see a reason for that to end this year. They have the right equipment, and we could give them an opportunity to economically benefit from construction.”

According to the rafting company, the shuttle operated for nine weeks and hauled 263 bicyclists who were visiting from all over the country and the world.

The service did not go unnoticed by the Adventure Cycling Association, which organizes some of those trips and was contacted personally by ITD engineers prior to construction.

In a letter to ITD, the association commended their efforts, which they said may be a model for construction managers in other states to follow to accommodate their groups.

As ITD engineers found ways to ease the impact of construction, they were also able to work with operations to advance more projects, including a preservation project between the two paving jobs.

In total, more than $17 million was spent to replace two bridges and resurface roughly 55 miles of US-12.

“We appreciate the patience of drivers who encountered us on the roads all summer,” Zarate said. “Now we look forward to years of driving on an improved highway.”

Remembering the Goff Bridge challenge 20 years later

 

Nearly twenty years later, the Goff Bridge—better known as the Time Zone Bridge near Riggins—remains one of a few tied-arch bridges in Idaho.*

But its unusual design is not the only thing that makes it unique.

The distinctive bridge stands out due to the dedication of several ITD engineers who oversaw its successful replacement, which began in 1996 and lasted until 1999.

At that time, Dave Kuisti was not yet the district engineer but was graduating from ITD’s Engineering in Training Program.

“I moved to the maintenance yard at Lucile for more than two years to be the project engineer,” Kuisti said. “My wife wasn’t particularly thrilled about the location.”

Located on US-95, the Goff Bridge would be a challenge to replace. The structure, built in 1935, spanned the Salmon River and served 2,000 vehicles per day, as well as 12 river outfitters in nearby Riggins.

The new structure would have to withstand consistent pressure from a slow landslide at its south end, be tall enough to stay above high water and wide enough to accommodate two trucks crossing at once.

To maintain mobility for the traveling public on the state’s primary north-south route during the construction of this three-year project, the design and construction teams planned to temporarily relocate the original structure to serve as the detour. It was the best option given the absence of an alternative route and the close confines of the canyon.

Hydraulic jacks and an estimated 72 hours would be required to move the 1.24 million-pound steel bridge to its new location 65 feet to the west. At that time US-95 would be completely closed to traffic through Riggins, prompting ITD to stipulate stricter penalties should contractor Harcon Inc. cause additional delays.

A 1996 Spokesman-Review article quoted Kuisti as saying that he felt “pretty confident” that the structure would not fall into the river. In a follow up article in 1997, public affairs specialist Ralph Poore mentioned the engineers’ eagerness to transition to the next phase of the project and described the construction challenge as “the kind of thing that makes and breaks careers.”

To advertise the closure, ITD placed notices all over the state, and even out of the state in Lolo, Montana, which sits on US-12 just across the state line. In the end, US-95 was reopened 36 hours ahead of schedule.

Watch a video of the relocation.

Robert Gordon, the lead inspector involved with surveying the area for the relocation of the bridge, said he was relieved when it went as smoothly as it did.

“It was a very critical move,” Gordon said. “If anything went wrong, the state was basically cut in two and would require a 500-mile detour to get from South Idaho to North Idaho.”

“It was not without its own tribulations,” Kuisti said. “In the end though, we got a pretty amazing structure that will be there long after I’m gone.”

According to its latest inspection, the Goff Bridge will likely last another thirty to fifty years.

*The Goff Bridge was the only tied-arch bridge in the state until the Shoup Bridge over the Salmon River was built last year south of Salmon.