ID-55 Smiths Ferry project transitions to summer work schedule

Spring construction is wrapping up on Idaho Highway 55 between Smiths Ferry and Rainbow Bridge. Thursday, May 27th marks the last day of planned full road closures until September. Friday through Monday during the Memorial Day weekend, both lanes of the highway will be open. Then Tuesday, June 1st, our summer construction schedule begins.

This project will help improve safety and mobility for drivers by widening shoulders, minimizing roadway curves, and installing guardrail in certain locations.

“Our spring construction started in mid-March, and with full road closures Monday through Thursday from 10 a.m. to 2 p.m. crews were able to safely blast rock away from the hillside,” said Project Engineer Alex Deduck. “In two and a half months crews excavated and removed nearly 55,000 cubic yards of material, that’s more than 4,500 truckloads. We’re close to a third of the way through the project now and appreciate everyone’s patience and cooperation as we make this a safer drive.”

Crews will continue their work on the highway this summer. June 1 through Labor Day drivers should plan for one-lane alternating traffic day and night Monday through early Friday morning. Both lanes will be open on weekends Friday through Sunday to accommodate busy summer travel.

Watch the video below to see the progress made so far.

Be the first to know project updates by signing up for our text alerts and emails. Just visit our website or text the word “alerts” to 833-480-0255. Project representatives are available 24/7 to answer your questions.

Thank you for your patience as we improve the safety and mobility of ID-55.

Full road closures on ID-55 Smiths Ferry project begin March 15

Spring construction picks back up on Idaho Highway 55 between Smiths Ferry and the Rainbow Bridge Monday, March 15. The Idaho Transportation Department’s project will widen shoulders, add guardrail, and straighten this curvy one-mile stretch of highway to improve safety. Watch the video below to see the project.

 

Earlier this month, crews removed snow and set up construction equipment in the canyon. Starting March 15, travelers should plan for full road closures Monday through Thursday from 10 a.m. to 2 p.m., due to controlled rock blasting needed to widen the road. When ID-55 is not closed, there will be one-way alternating traffic with 15-minute delays. This work schedule is expected through May, when crews will transition into summer operations.

To stay up to date and learn more, visit the project website itdprojects.org/ID55smithsferry.

 

ID-55 project between Smiths Ferry and Round Valley to start September 8

ID-55 at Smiths Ferry

The Idaho Transportation Department (ITD) starts road work on the Idaho Highway 55 safety-enhancement project between Smiths Ferry and Round Valley on September 8.

The public is invited to attend a virtual public meeting on Wednesday, September 2, from 6 p.m. – 7 p.m. where ITD representatives will give an overview of the project and take questions. The link to attend will be posted on the project website, itdprojects.org/ID55smithsferry, 15 minutes prior to the meeting.

Work will largely be done in fall, spring and summer months, with construction stopping during the winter. This fall, travelers can expect full closures on the roadway Monday through Thursday from 10 a.m. – 2 p.m. to allow for blasting and rock removal.

Motorists can find additional details on road closures and traffic patterns on the project website, and can sign up for email and text updates.

“Our goal with this project is to enhance the safety of this mile-long section of the roadway,” Project Manager Alex Deduck said. “Construction crews will remove about 146,000 tons of rock from the hillside, which we want to do very carefully to not create rockslides or impact the river.”

Crews will work on widening shoulders and straightening the curves of the road. This project will also provide a smoother, safer ride for motorists by adding guardrail.

Motorists should anticipate reduced speeds and lanes reduced to one-way alternating traffic during construction. Seasonal closures and traffic patterns will be as follows:

  • Fall (September – November): One-way alternating traffic controlled by a temporary signal; daytime and nighttime work, seven days a week; full road closures Monday – Thursday from 10 a.m. – 2 p.m.
  • Winter (December – Mid-March): No construction expected; all lanes open
  • Spring (Mid-March – Mid-May): One-way alternating traffic controlled by a temporary signal; daytime and nighttime work, seven days a week; full road closures Monday – Thursday from 10 a.m. – 2 p.m.
  • Summer (Mid-May – August): One-way alternating traffic controlled by flaggers; daytime and nighttime work, Monday – Friday

The project is expected to be completed by late fall 2022. ITD and the Idaho State Police advise motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-­1-­1 or visit 511.idaho.gov for information on the state highway or interstate system.

Construction will begin on Idaho 55 next week (July 16) near McCall

Idaho 55 Zachary to Goose Creek Map

The Idaho Transportation Department will begin a project next week (July 16) to resurface Idaho Highway 55 between New Meadows and McCall and construct a new retaining wall east of Brundage. The project will improve driving conditions and safety on this heavily traveled route.

From July to late August, crews will work between Zachary Road in McCall and Goose Lake Road near Brundage. View the postcard for details.

In order to keep traffic moving during the busy summer season, crews will work from 12 a.m. Monday to 12 p.m. Friday. All lanes will be open on weekends.

During the week, ID-55 will be reduced to one lane both day and night with a pilot car directing traffic. The speed limit will be reduced and 12-foot width restrictions will be in place.

“This will be a tight construction zone and we are asking for drivers’ patience during the work week. Please slow down in the work zone and pay close attention to signage, as crews will be working close to traffic,” said ITD Project Manager Jim Hoffecker.

Construction will move to the area between Goose Lake Road and Goose Creek Grade in late August. The project is expected to be completed this fall.