Passing lane added to US-95 south of Potlatch this summer

Cars drive by each other on US-95 with no passing lanes

Construction on a new northbound passing lane begins Tuesday, June 22 on US-95 near Potlatch. The existing passing lane for southbound drivers at Cove Road will also be extended to provide safer opportunities to pass.

Motorists will have one lane of travel in each direction for most of construction. During initial operations, however, the highway will be reduced to one lane as crews place barrier around their work zone for safety.

Extension of the existing passing lane won’t begin until August.

Work on this mile-long project will be completed this September. The Idaho Transportation Department also plans to add northbound and southbound passing lanes north of Potlatch near Freeze Road and Beplate Lane in 2026.

Lack of cement forces pause on ID-13 repairs

Contractor on ID-13

Repairs that began in May to six miles of Idaho Highway 13 east of Grangeville will pause due to a cement shortage.

“The supplier for this project has informed us that they are facing a shortage of cement,” Resident Engineer Joe Schacher said. “Unfortunately, it may take up to a month for us to receive what we ordered and get back to work on this project.”

Repairs call for the asphalt surface of the highway to be milled, mixed with cement and then reapplied to the highway to form a stronger base. Crews would then finish the project by adding another layer of pavement. This process is known as cement recycled asphalt base stabilization, and it cannot be done properly without the cement.

“As of now, we have done everything we can do with the materials we have,” Schacher said.

To date, crews have replaced approximately 50 drains and milled the surface of the highway.

All lanes of ID-13 will remain open until work can resume, and drivers will travel primarily on a milled and gravel surface at a reduced speed of 30 mph. The contractor and ITD will continue to monitor the work zone to maintain conditions.

At this time, this is the only ITD project thought to be impacted by the shortage. Depending on the length of the delay, construction could be completed by mid-August.

Until it can be finished, ITD urges drivers to take extreme care and slow down while traversing this section of highway.

Slide on Idaho Highway 11 near Headquarters to disrupt traffic over Memorial Day Weekend

The slide condition just days after being discovered

The Idaho Transportation Department would like to advise travelers over the holiday weekend of unexpected delays on Idaho Highway 11 near Headquarters. This will impact drivers on their way to popular sites up the North Fork of the Clearwater River and the Grandad Recreation Area.

“Last month we noticed that the shoulder of ID-11 was falling away from the road,” Engineering Manager Bob Schumacher said. “Since then, the northbound lane has sunk further and is now estimated to be an eight-foot drop off.”

A man stands on the highway where the shoulder is starting to sink
A man stands on the highway where the shoulder is starting to sink on April 16
The drop off is now closer to eight feet as of April 23
The drop off is now closer to eight feet as of April 23

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The northbound lane of ID-11 is closed, with drivers required to yield to southbound traffic. A drill will be on site today and tomorrow to bore below the highway and into the slope. While boring beneath the highway, flaggers will stop all traffic for approximately 15 minutes at a time. Crews will also install monitoring devices to track further movement.

“We will collect soil samples at various depths,” Schumacher said. “We are looking for layers that appear to be saturated so we can determine the severity of the slide.”

Repairs will then be designed and added to a resurfacing project that was already planned for this summer between Grangemont Road and Headquarters. It is unclear at this time how the repairs will affect the timing and budget of the project.

Drivers should continue to expect at least a lane closure in the area and should check 511.idaho.gov for impacts before traveling.

Idaho Transportation Board puts new money to work across Idaho

LEWISTON – The Idaho Transportation Board approved dozens of new road projects across every corner of the state Wednesday afternoon (May 19) during its regular monthly meeting in Lewiston. The projects include $350 million in construction work that is expected to begin sometime next year.

Many of the projects are part of Idaho Governor Brad Little’s “Leading Idaho” transportation funding solution.

“Idaho is the fastest growing state in the nation. To keep up with the demands of a fast-growing state, our historic transportation funding solution helps save Idahoans’ time, keeps us safe on our roads, and makes our state’s economy even stronger,” Governor Little said. “I appreciate the Idaho Transportation Board for acting quickly to put these new funds to work.”

Projects approved today that are ready now include $170 million of Transportation Expansion and Congestion Mitigation (TECM) funds to expand Idaho State Highway 16 from its current location at US-20/26 (Chinden Blvd.) to Interstate 84. The board also dedicated $37 million of TECM funds to expand US-20/26 to four lanes from Middleton Road to I-84. Both projects should be under construction next year and will likely be bonded.

In addition, the board approved about $140 million in projects with one-time funds from the Building Idaho’s Future program, along with federal and state COVID Relief funds. This statewide group of projects is focused on critical maintenance and safety needs for highways and bridges from Ashton in eastern Idaho, to the Magic Valley and north to Wallace.

Check this link to see the full list of projects approved across the state.

“We want to thank the Idaho Legislature and Governor for one of the most significant transportation investments in state history,” said Idaho Transportation Board Chairman Bill Moad. “Our goal as a board is to be great stewards of this funding. We will work with the department to pick the projects across Idaho that will have the greatest return on investment in improving safety, increasing mobility and addressing Idaho’s rapid growth.”

In addition to $350 million in construction that will begin next year, the board also approved nearly $170 million for project development. This includes environmental planning, design and right-of-way acquisition.

“Project development is very important. The Board wants the department to have projects ready for the Building Idaho’s Future program and to be constantly advancing additional work for any future federal or state funding opportunities,” said Idaho Transportation Board Chairman Bill Moad. “It is our goal to put the money to work as soon as it becomes available.”

The TECM fund was increased to $80 million through House Bill 362 signed by Governor Little earlier this month. The Idaho Transportation Department will leverage those ongoing funds into a Building Idaho’s Future bonding program that could yield as much as $1.6 billion. The goal is to have major safety and expansion corridors financed over the next six to eight years with the bond proceeds.

ITD staff will present potential projects and corridors to include in the bonding program to the Idaho Transportation Board by the end of this year.

Twelve miles of US-95 south of Culdesac to be repaved this summer

Log truck at top of the grade on US-95

Twelve miles of US-95 south of Culdesac will be repaved this summer, with impacts to traffic starting Monday, May 3. Motorists should plan up to 15 minutes of extra time to navigate through the work zone.

Until work is complete this October, drivers should expect one lane to be closed during working hours. The highway will open to two lanes at night and on the weekends when crews are not working.

Work will be focused between mileposts 267 – 271 south of Craigmont, portions of US-95 between mileposts 273 – 283 north of Craigmont and at approximately milepost 289 in the canyon. Crews will begin with the section in the canyon and progress south past Craigmont.

These repairs cost $7.3 million and will be completed by Valley Paving & Asphalt of Cottonwood.

Over the last two years, the Idaho Transportation Department has improved safety in the area by widening the highway to accommodate 2.5 miles of passing lane for southbound drivers. While no expansion work will take place this year, three more phases of work to extend the passing lane another 6.5 miles are programmed for 2023, 2024 and 2026. Paving this year will address the lanes that were not improved with previous projects.

Reconstruction of Idaho Highway 13 east of Grangeville begins May 3

Smoky horizon in ID-13

Idaho Highway 13 east of Grangeville will undergo construction this summer. Work will resurface the highway, replace drains and address soft spots.

Repairs to ID-13 from milepost 1 to 7—which does not include Harpster Grade—will start on May 3 and will last through mid-July.

Drivers should be prepared for delays up to thirty minutes while crews are on site. During daylight hours, a pilot car will guide one lane of traffic through the zone. The highway will open up to two lanes at night and on the weekends, but traffic will still be slowed by the gravel surface.

“Construction will be short but intense,” ITD Resident Engineer Joe Schacher said. “It’s desperately needed, so we were able to move up construction from 2022 to this year.”

Community members are invited to stop by an informal open house at Grangeville City Hall at 225 West North Street on Wednesday, May 5 from 11 a.m. to 1 p.m. to learn more.

Poe Asphalt will complete the repairs for $3.3 million, with work inspected by Jacobs.

Subcommittee for the Idaho Transportation Board to review reclassification of Idaho County highways on Thursday

Seven Mile Canyon on Idaho Highway 162

The Idaho Transportation Board 129,000 Pound Route Subcommittee will meet Thursday, April 22 to review an application to reclassify the weight limits of several highways in Idaho County. After review, the subcommittee could provide a recommendation to the Idaho Transportation Board, which will make a final decision on the reclassification, or require further analysis by the department.

The subcommittee will convene at 12:15 p.m. PT / 1:15 p.m. MT in Jerome to discuss engineering analysis completed by department staff and comments received during the public hearing process.

The meeting will be held at the Idaho Department of Fish and Game office at 324 South 417 East, but members of the public may participate remotely via instructions located on the agenda. Since this meeting will be held after the Idaho Transportation Board meeting, participants should be prepared for any scheduling changes.

Public comments were sought in March and April on the application submitted by KBC Trucking to increase the limits on the following highways from 105,500 pounds to 129,000 pounds:

  • Idaho Highway 13 from the KBC Trucking yard at milepost 24.4 to its intersection of US-12 outside of Kooskia
  • US-12 from Kooskia to Kamiah
  • Idaho Highway 162 from Kamiah to its intersection with Old Highway 7

The applicant has also requested the use of Old Highway 7 from its intersections with ID-162 and US-95. This route is not being evaluated by ITD as it is under the jurisdiction of the Greencreek Highway District, Union Independent Highway District and Grangeville Highway District.

No further public comment will be taken at the subcommittee meeting.

The application, analysis by ITD and FAQs about 129,000-pound loads are available at itd.idaho.gov/freight.

A final decision by the Idaho Transportation Board could be made as early as the next regular board meeting on May 19.

Comment period open for proposed changes to commercial trucking limits on some Idaho County highways

Seven Mile Canyon on Idaho Highway 162

The Idaho Transportation Department is hosting a virtual public hearing to collect comments on a proposal to reclassify several highways in Idaho County as legal for carrying heavier loads. If approved, these highways could support commercial loads weighing up to 129,000 pounds.

KBC Trucking of Kooskia submitted an application to ITD earlier this month requesting the reclassification of the following routes to allow for more efficient transport of logs and lumber to Boise Valley:

  • Idaho Highway 13 from the KBC Trucking yard at milepost 24.4 to its intersection of US-12 outside of Kooskia
  • US-12 from Kooskia to Kamiah
  • Idaho Highway 162 from Kamiah to its intersection with Old Highway 7

The applicant has also requested the use of Old Highway 7 from its intersections with ID-162 and US-95. This route is not being evaluated by ITD as it is under the jurisdiction of the Greencreek Highway District, Union Independent Highway District and Grangeville Highway District.

These highways are currently rated for commercial loads weighing up to 105,500 pounds. Analysis of the state routes by ITD subject matter experts found that allowing heavier loads on the specified highways could be accommodated without affecting safety or pavement conditions.

A similar application was filed by Arlo Lott of Montana in 2015 but included all of ID-13 from Kooskia to Grangeville. After engineering analysis deemed the proposal would not negatively affect safety or pavement conditions, a public hearing was held and received significant public comment. The applicant later withdrew his request.

“While similar to an earlier application, the latest request excludes much of ID-13, which was the most controversial segment,” said Jan Vassar, the Idaho Transportation Board Member representing North Central Idaho. “Staff are approaching this proposal with fresh eyes, and as before, comments received will influence the decision regarding reclassification of the routes.”

The application, analysis by ITD and FAQs about 129,000-pound loads are available at itd.idaho.gov/freight. Comments are being sought until April 12 and can be submitted in the following ways:

Commenters can also call ITD Freight Program Manager Scott Luekenga at (208) 334-8057 with questions.

The department is required to conduct an analysis and public hearing on all requests to operate 129,000-pound loads on the state highway system before the Idaho Transportation Board makes a final decision. The board could make a decision as early as May.

 

With approved permit, US-95 expansion south of Moscow could start this fall

Photo of wetlands that will be impacted by US-95 expansion

Plans to expand US-95 south of Moscow are one step closer to construction, as the Army Corps of Engineers granted a permit to the Idaho Transportation Department on March 9, 2021.

“This permit was one of the last few hurdles to get our plans out to construction and make the highway safer,” said Ken Helm, the ITD project manager who has overseen expansion efforts since 1998. “Now we can finally address the last two-lane section between Lewiston and Moscow.”

The permit approves the evaluation and mitigation of permanent wetlands that will be affected by shifting the highway less than a mile to the east and adding two more travel lanes. The new route will be flatter, feature wider shoulders and have fewer access points to improve safety and reduce travel times for the 7,300 drivers who take this route each day.

“Our next step is to finish working with property owners to acquire the last remaining parcels of land necessary for expansion,” Helm said. “We aim to bid this project this summer, which means we could start construction this fall.”

Construction is expected to take two years and estimated at $60 million. For more information, visit itdprojets.org/us95thorncreektomoscow.

ITD considering partnership to reinitiate maintenance of backcountry airstrip in Lemhi County

Hoodoo Meadows Airstrip corridor and borrow trench - Photo taken near entrance facing North.

The Idaho Transportation Department’s Division of Aeronautics (ITD) is seeking public comments as it considers restoring and managing a backcountry airstrip in the Salmon-Challis National Forest.

The Hoodoo Meadows airstrip (as shown in image above) is the highest in the state at an elevation of 8,200 feet, and provides access to the Frank Church – Wilderness of No Return. The airstrip is located just south of Yellowjacket Lake and near the popular Bighorn Crags area. It has not been used since the 1980s.

The site was managed by the U.S. Forest Service (USFS) after its construction in 1936 by the Civilian Conservation Corps, and traditionally used to gain recreational access for alpine lake fishing, wildlife viewing, and big game hunting. Although there were no reported accidents, in the early 1980s the airstrip was rated marginal for safety, and by 1989 trees had encroached the site and made it unusable.

In 2016, the Idaho Department of Fish and Game (IDFG) initiated the effort to restore the Hoodoo Meadows airstrip, due to repeated public inquiries about recreational accessibility. Together, USFS, IDFG, and ITD, with support from the Idaho Aviation Association and the Recreation Aviation Foundation, are working on an agreement that would open the site for air travel and provide for future maintenance.

“This effort has been underway for several years. Our role would be making the airstrip safe for pilots to land again, by clearing vegetation and installing safety features like runway markers,” Aeronautics Administrator Jeff Marker said. “It would take about a month of initial cleanup work on our part, but would provide more access for those who wish to explore some of the most remote places in Idaho.”

Visit itd.idaho.gov/aero to review the proposed partnership, then please provide ITD your feedback on the plan. Public comments will be accepted March 15 to March 29 through the following options:

  • Email jillian.garrigues@itd.idaho.gov
  • Record verbal testimony by calling (855) 785-2499
  • Send your written comments by mail to
    ATTN: Jillian Garrigues
    Idaho Transportation Department
    PO Box 7129
    Boise, ID 83707

The USFS sought comments in 2018 on reopening the Hoodoo Meadows airstrip. Now, the public can voice their support or concerns regarding ITD’s involvement in the partnership.