Intersection closure to occur next week on 200 South Road east of Jerome

The west side intersection of US-93 and 200 South Road in Jerome County will be closed starting Monday of next week (Dec. 16). This closure will allow utilities work to occur in the area. Work is expected to be completed within the week.

Motorists will need to utilize 100 South Road or 300 South Road while this closure is in place. Drivers should be aware of crews and equipment while traveling through the area. US-93 will remain fully open during this time.

This work is in connection with the larger US-93, 200 South Road project, which will widen the existing roadway to four lanes.

“This project will improve safety at the US-93/200 South intersection for both passenger and commercial vehicles,” said ITD Project Manager Sam Purser. “The end result will be a divided highway similar to what drivers encounter two miles south of this area.”

Idaho Materials and Construction is the prime contractor for this project.

Northgate opening Dec. 6 marks fulfillment of extensive process, unique partnership

Northgate Interchange Ribbon Cutting Ceremony

Three years after negotiations began, and 11 years after District 5 first mentioned the need for a new interchange at the location, the new Northgate Interchange opened to traffic on Dec. 6. It was fueled by a unique public-private partnership that brought the Interstate 15 interchange to reality at least two decades sooner than anticipated.

The collaboration of developers, cities, county, and many many other agencies and parties is a first of its kind for Idaho. While planning and design took time to develop, construction lasted just a year.

Approximately 250 people attended the grand opening, which included a welcome and introductory remarks by ITD D5 District Engineer Todd Hubbard, followed by remarks from Speaker of the Idaho House of Representatives Scott Bedke, and Farhana Hibbert, regional director representing U.S. Senator Mike Crapo’s office, Buck Swaney, representing Millennial Development Partners, Bannock County Commissioner Steve Brown, Chubbuck Mayor Kevin England and Pocatello Mayor Brian Blad. Former ITD District Engineer Ed Bala wasalso able to attend.

Watch the video here from the Grand Opening celebration.

“The project was a celebration of great relationships built and excitement from the community,” said ITD Project Manager Greydon Wright.

“We are excited to see what this new interchange helps bring to the communities,” said Wright. “Thank you to everyone who helped and participated throughout this journey.”

The total project, which provides a new entrance to northeast Pocatello and adjacent Chubbuck, represents an investment of roughly $31 million, including connecting roads and infrastructure.

Before you go, don’t forget to pack your winter car emergency kit

Vehicles traveling in winter conditions

Of the many things that Idahoans know a lot about, one of them is how to be prepared. Prepared for the big game, prepared for the campout, and prepared for the road. Whether you’ve lived in Idaho your whole life or are a new resident, it’s important to do everything you can to prepare for an Idaho winter. As the cold weather sets in, so do winter road conditions.

So how do you prepare for Idaho winter travel? We recommend starting by calling or visiting 511.idaho.gov to check road conditions and alerting friends and family of your travel plans (especially if you are traveling through areas with poor cellular service). Take time to review a map and make sure you know your path of travel as opposed to relying solely on GPS navigation which can occasionally be incorrect. Once you’ve checked those things off your list, ensure you are prepared for whatever comes your way by packing a winter car emergency kit.

Keeping a winter car emergency kit on hand won’t just benefit you, but it could come in handy for others you come across while traveling. Here are some items we recommend you include when building your winter car emergency kit:

  • Flashlight with extra batteries to use as a light source and signal for help.
  • Jumper cables to jump your own vehicle or assist other motorists.
  • Tire pressure gauge to ensure you are driving with the optimum inflation.
  • Cat litter to use as traction on slick surfaces.
  • Small camping shovel to assist with removing snow around tires and tailpipes.
  • LED flares to alert motorists of a broken down vehicle or roadway obstruction.
  • First Aid Kit for minor injuries and emergencies.
  • High protein food and bottled water to keep you hydrated and give you energy should you be stuck for a period of time. If your food items are in cans, make sure you also have necessary items like a can opener and utensils in your kit as well.
  • Winter coats and gear such as hats, gloves, etc. to help keep your body temperature up.
  • Blanket or a small sleeping bag for warmth in freezing conditions.

Some of the items may seem excessive but if you run off the road, breakdown or simply get stranded during an extreme storm, these items will help keep you warm and safe until roadside or emergency services are able to reach you.

For those that already have a winter car emergency kit in a vehicle, make sure you do an annual check of items to ensure they are in good condition and working order – remember, food expires and batteries don’t hold their charge forever. Also, if you do find yourself stuck in the snow, don’t run your vehicle without first ensuring the tailpipe and up to three feet behind your vehicle is free of snow; this, along with opening your windows, will prevent deadly carbon monoxide from building up inside the automobile.

As a parting note, be sure to replace worn windshield wipers, keep gas in your car and have the proper tires on before driving in winter weather conditions. Keeping all of that in mind, you’ll be well on your way to being prepared for an Idaho winter.

ITD to open Northgate Interchange with ceremony Friday at 11 a.m.

Northgate Interchange

POCATELLO – The Idaho Transportation Department will hold a Grand Opening for the new Interstate 15 Northgate Interchange in Pocatello Friday (Dec. 6) at 11 a.m. The interchange will officially open to traffic that afternoon after the site is cleaned.

The Grand Opening will begin with a welcome from ITD District 5 Engineer Todd Hubbard. Comments will follow from: Farhana Hibbert, regional director for Senator Mike Crapo; Scott Bedke, Speaker of the House of Idaho House of Representatives; Buck Swaney, representing Millennial Development Partners; Bannock County Commissioner Steve Brown; Chubbuck Mayor Kevin England and Pocatello Mayor Brian Blad.

Following the brief ceremony, mayor Blad and mayor England will drive across the interchange deck.

The project is the result of a unique public-private partnership, the first of its kind in Idaho. Just three years after the agreement was signed, the interchange is complete and ready to open.

The total project, which provides a new entrance to northeast Pocatello and adjacent Chubbuck, represents an investment of roughly $31 million, including connecting roads and infrastructure.

 

ITD launches annual winter driving safety campaign in advance of Thanksgiving travel

The Idaho Transportation Department is launching the annual winter safety campaign “Idaho Ready” to help drivers prepare for challenging conditions on the state’s highways. This launch comes as winter weather is expected to bear down on much of the state and holiday travel begins.

The campaign offers information via social media and a page on the department’s website to help drivers safely arrive at their destinations.

“Short videos will present information on using Idaho’s 511 Traveler Information system as a resource before heading out on the highway, how to maintain your vehicle during winter months, and driving safely in winter conditions,” said Reed Hollinshead with ITD’s Office of Communication. “Important safety information will be posted regularly to Facebook, Twitter, and the ‘Idaho Ready’ web page. New information this year will address new drivers on Idaho roads — those who recently moved here or have recently been licensed.”

Additional information on winter safety can be found at itd.idaho.gov/road-mtce.

Follow ITD’s Facebook page at www.facebook.com/IdahoTransportationDepartment, or the department’s Twitter account at IdahoITD.

Drivers are also encouraged to check the new and improved Idaho 511 Traveler Information website at 511.idaho.gov for the latest road conditions and for updates as those conditions change.

ITD remembers 1995 Noseeum Creek flooding on US-12

Picture of missing highway section on US-12 after Nov. 20, 1995 Noseeum Creek flooding.

When 400,000 tons of mud, rock, trees and other debris obliterated 1,200 feet of highway on Nov. 20, 1995, it created “the biggest slide of my career,” said Mark Schuster, maintenance foreman for US-12 for the last three decades. “When I got the call from Kati, I’ll admit I doubted her.”

Just weeks on the job, Kati Young was new to Schuster’s team, and the one who made the call that Noseeum Creek had overtaken the highway at milepost 124.6.

Heavy rains had kept the crew busy tending to little slides all week, and Young was listening to Schuster on her way home as he shared the forecast over the radio. She had slowed down to finish listening before she lost service, and ultimately, that’s what kept her out of the path of the creek washout just around the corner.

“I saw the trees coming down and water on the road,” Young said. “As water reached my tires, I backed up my oneton pickup. I did this for half a mile. It was like a fast tide coming in.”

Trees were strewn about like matchsticks, and boulders the size of Volkswagen Beetles had been pushed across the Lochsa River as Noseeum Creek crashed into the narrow channel, Young said.

When Schuster joined her, they realized that the road would have to be closed for the night—around the next bend, a section of US-12 had been completely taken out by the creek, which was estimated to be a 30-foot wall of water and mud at the time it collided with the river.

Rocks, trees, mud and other debris carried downstream by the creek created a dam, choking the river below and causing the tide-like effect above stream. Now divided by tons of material and missing a section of road, Schuster warned his crew downstream to seek high ground and assess the situation from Fish Creek Hill.

Dispatch took care of notifying nearby towns, and that was it – there was no 511 in 1995.

Given the late hour, ITD didn’t get a good look at it until the next morning. The detour—a nine-hour trip to Interstate 90, US-95 and then US-12—was put in place to get over the Bitterroot Mountains, and the department knew it would be closed for weeks until the mess could be cleaned up and the road rebuilt.

Watch a 1995 update from Q6.

Those who were able to drive home enjoyed the Thanksgiving holiday with families, and those caught on the wrong side of the closure enjoyed it with each other.

After the holiday, multiple ITD crews began working with excavators, track hoes, dozers and dump trucks to clear debris, while engineers prepared to realign the road and put the emergency project out to bid to area contractors.

They removed an estimated 20,000 cubic yards in the first 19 days, but the 13-foot culvert for Noseeum Creek was never recovered.

“The river took care of itself,” Schuster said.

But after that, the river wasn’t the same—it was now eight feet higher than before, requiring surveyors and engineers to draw plans for drilling and blasting to realign the road.

Poor weather continued, undermining progress as crews worked seven days a week, daylight to dusk.  Nighttime work wasn’t considered safe.

The closure affected the travel routes of fuel and chip trucks from Montana, as well as garbage trucks heading from Idaho into Montana. While services didn’t cease, the detour impacted staff times and fuel costs. ITD still maintained Lolo Pass for U.S. Forest Service employees to access work sites at Powell.

Forty-seven dump trucks would eventually carry 3,000 tons of rock from Lewiston to lay the base for 1,200 feet of highway that would be reconstructed. Emergency efforts and permanent repairs totaled $660,000.

Twenty-five days after the flood, US-12 reopened. It was December 23, a few days before holiday travelers would be looking to cross Lolo Pass to return home.

The gift to the highway department: reuniting families and a shorter commute home.

Duran brings vision, motivation to Public Transportation Manager’s role

Ron Duran will soon move from the Division of Motor Vehicles to become the new Public Transportation Manager. Duran, currently the Driver Records Program Supervisor, will ascend to the PT management position Dec. 1. The position has been vacant since Jeff Marker left to become the Aeronautics Administrator last month.

“I am thrilled for this new challenge and I am humbled by the opportunity to lead an exceptional team,” Duran said. “I can’t wait to get started building relationships with my new team, stakeholders, and industry.”

Duran started at the Idaho Transportation Department in July 2018 in Driver Records, overseeing a staff of 15 employees. The unit processes suspensions, hearings, court packets, SR22s, and more.

“Leaving the DMV is bittersweet, as the people and leadership are phenomenal,” Duran added. “I am eager for this new chapter in my career and to build on the success of the Public Transportation Office.”

Duran came to the department after 10 years as an operations manager for a private security contractor. He attended Boise State University.

He volunteers as an EMT in Wilder, and has served on the State-2-State Governance Committee as the Idaho Representative.

“Ron has an amazing ability to envision what is possible and make positive changes,” ITD Chief Deputy Scott Stokes said. Duran will report to Stokes in his new position.

“This vision, combined with his proven record on motivating teams and partnership, will be something that will help us find the best way to provide transportation services and to be the best department,” Stokes added.

Districts come together to patch Interstate bridge

Blackfoot Bridge Repairs

Months of preparation with multiple delays and last minute changes, the I-15 Blackfoot bridge was finally able to get repaired. After years of temporary patches to fill in potholes and disintegrating concrete, crews were able to come together as one big team to help fix the bridge and pulled off one of the biggest traffic control plans ITD has ever done internally.

This project involved many tasks. Of those tasks crews had to sandblast and resurface the bridge deck, replaced guardrail and completed other much needed shoulder work. This repair project was intended to temporary fix the bridge until we are able to begin a full bridge deck rehab project planned in the summer of 2020.

From October 7 – 9 crews shut down north bound I-15 and from October 15 – 17 south bound I-15 was temporarily shut down. With the intent to utilize all 3 days on each side of the interstate, crews worked diligently and fluidly to complete the project 1 day early on each side. Completing this project early on each side was no easy task but crews made it happen and it couldn’t have gone any smoother.

Originally planned for September, the bridgework had been delayed a few times due to project complications and local concerns. After working with the community and local politicians regarding the bridgework and road closures, ITD crews were able to work around the holidays and harvest. In working with the community so closely and openly, the project was incredibly successful and well received by many.

As numerous districts and crews from all over came out to help, the traffic control was also a key part to the success of this project. Spear heading the traffic control plans, D5 Blackfoot TTO’s Jared Loosli & Rocky Messick worked with numerous people and pulled off one of the largest traffic control jobs done internally throughout the state.

There was close to 10 miles of traffic control setup with crossovers, road closures barricades and numerous flaggers. The crews set the speed limit to 55 mph and with the help of ISP playing a huge role in transitioning and patrolling travelers, the project did not have any crashes…a few close calls but no crashes!

Crews provided 24hr coverage while traffic control was in effect. In closing each side of the interstate down and having such great traffic control, not only were crews able to get in and done with the project quicker but it was significantly safer. By doing this our crews felt safe and gave them the extra confidence that we (ITD) has their back to keep them safe.

As this project ended as a huge success, there was a little bit of a learning curve for the guys to take back for future projects. Learning with even a speed of 55mph to use bigger basses for the candlesticks so they don’t blow over as much and also to adjust exit ramps for the southbound for an easier and clearer transition for drivers.

“It was impressive to see the success of taking one project, bringing in so many people from different areas and working to well together”, said Jared Loosli, “It just goes to show that we can do big things if we’re asked to do big things, we can make it happen!”

ITD to hold open house for I-90/ID-41 interchange redesign on Nov. 20

Aerial view of the current I-90/ID-41 interchange.

The Idaho Transportation Department invites the public to view and give comment on the selected design of the Interstate 90 and Idaho Highway 41 interchange at an open house next Wednesday, November 20.

Members of the public may arrive at any time between 4 p.m. and 7 p.m. at the Red Lion Hotel in Post Falls.

Since the last public meeting in November 2018, ITD has coordinated with the city of Post Falls and other stakeholders to select the preferred design to improve safety and mobility. The latest plans feature an offset single-point urban interchange (SPUI).

View proposed plans for the interchange.

Earlier this year another project originally planned for 2025 to address similar concerns on ID-41 between Seltice and Mullan avenues was combined with this 2023 project. Additional lanes will be added at the Mullan Avenue intersection, and a raised curbed median will limit left turns from side streets onto the highway.

ITD will also ask the public to share concerns about construction of this $39-million project.

Those unable to attend may visit the project website to learn more and to comment. Comments will be accepted from November 20 to December 4.

 

Idaho drivers must provide proof of insurance to DMV, or have registration suspended, as new law takes effect in 2020

Drive Insured! Be safe, be smart! Insure your vehicle or lose your registration.

Vehicle owners will need to provide proof of insurance for two consecutive months or risk having their registration suspended beginning in 2020.

The law (Idaho Code Section 49-1234) was passed during the 2019 Idaho legislative session and goes into effect in January. It requires the Idaho Transportation Department’s Division of Motor Vehicles to determine monthly whether the owner of a vehicle has insurance. The law applies only to non-commercial vehicles, and excludes trailers and off-highway vehicles.

A notification letter will be sent to affected vehicle owners to alert them of the law change.

Owners without insurance coverage for two consecutive months will receive a warning and be given 30 days to provide proof of insurance or obtain an exemption before their registration is suspended.

To reinstate a suspended registration, owners will need to provide proof of insurance and pay a fee of $75.

Some vehicles are exempt from this mandate. For a full list of frequently asked questions, please visit itd.idaho.gov/driveidaho